A wall-mounted display cabinet looks simple on a drawing and complicated on a finished wall. Nothing can be corrected after the cabinet is hung: the fixing line, the reveal against the panelling, the shelf heights and the lighting feed are all fixed the moment the bracket goes into the substrate. Our Santerson Wall Mounted Display Cabinets are made to measure for each space, with finish, layout and dimensions specified project by project, so the installation plan has to carry that information forward from the workshop to the site. Below is the checklist we work through before a wall-hung unit leaves the factory.

1. A measured survey of the wall itself

The first drawing is never the cabinet; it is the wall. Record the floor-to-soffit height, the position of studs, noggings and any embedded services, and whether the substrate is masonry, plasterboard on battens, timber framing or an existing panelling system. A made-to-measure unit that is 20 mm wider than the survey assumed can be corrected in the workshop; a cabinet specified over a hollow plasterboard section cannot be corrected on site.

Note everything that interrupts a flat plane: skirting and architraves, cornices, switch plates, air grilles, curtain recesses and the return of an adjacent wall. If the design calls for the cabinet to sit proud of a cornice or flush with a panel joint, say so on the drawing rather than leaving it to the installer's judgement.

2. Load path and fixing method

Decide what carries the weight before deciding how the cabinet is hung. Glass-fronted units with shelving for ceramics, glassware or a collection are heavy, and the load is concentrated along one line of fixings. The plan should state:

  • the substrate type and its safe fixing method, including anchor type and spacing;
  • whether a continuous timber batten or backing frame is required behind the unit;
  • the finished weight of the cabinet with shelves and contents, not just the carcass;
  • who supplies the fixings — us with the unit, or the site contractor to our specification.

Where a wall cannot take a direct fixing, plan the reinforcement into the wall build-up while the wall is still open. Retrofitting a backing frame into a finished hotel room or villa living area means patching, repainting and a delay nobody budgets for.

3. Dimensions, clearances and the reveals

Our display cabinets are supplied to the dimensions you specify, so the plan needs the same level of detail the workshop works from: overall height, width and depth; the setting-down or floating dimension above the floor; and the gap intended at each edge. State whether the unit is meant to appear inset into a niche, proud of the wall face, or wrapped into a run of full height storage walls.

Then check what the cabinet has to clear once it is hung: door swing and handle projection, the opening arc of any lift-up or hinged front, drawer run if a drawer is specified, and the sightline from the main viewing position. A cabinet that clears the skirting but fouls a radiator cover is still a site problem.

4. Interior layout and shelf specification

Fix the interior before the carcass is built. The plan should show shelf positions and heights, and identify which shelves are fixed and which are adjustable — adjustable shelving gives a homeowner or a housekeeping team room to rearrange without re-fixing anything. For display items of known height, such as a set of books or a group of vases, dimension the shelf spacing to the objects rather than to a standard module.

Decide the mix of closed and open storage at this stage. A glass front display cabinet shows what is inside it, so the interior back panel, shelf material and edge detail all become visible design decisions. An open display unit reads lighter on a wall but needs the objects themselves to carry the composition.

5. Lighting and electrical routing

If the plan includes an illuminated display cabinet, the electrical work belongs in the wall, not in a surface trunking added afterwards. Specify the fitting type, colour temperature and where the driver sits — an inaccessible driver behind a sealed cabinet is a maintenance call you will repeat. Confirm the switch arrangement: a door-activated contact, a wall plate beside the unit, or a feed on a shared circuit.

Agree who runs the cable and who terminates it. On most projects the site electrician brings the supply to a termination point inside the cabinet zone, and we prepare the carcass with the necessary cut-outs and a concealed channel. Both parties should be working from the same marked-up elevation.

6. Finish, material and site protection

Record the selected finish on the order drawing — lacquer, laminate, veneer or aluminium-framed glass front — together with any sample reference, so the item arriving on site is checked against something agreed rather than remembered. Wall-hung cabinets are usually one of the last items installed, which means they travel into a building where painting and flooring are already complete. The plan should say how the unit is delivered to store, where it is stored, and what protection is fitted around it once installed if other trades still have access to the room.

7. Sequence, access and handover

Put the cabinet in a programme position that makes sense: after wet trades, flooring and painting are finished, and before soft furnishing and final cleaning. Confirm the delivery route — lift dimensions, stair widths, corridor turns and lift loading — for a full-height or wide unit, because a cabinet that cannot reach the wall is a delivery failure rather than an installation one.

Close out with an inspection against the drawing: level and plumb line, fixing security, door and shelf alignment, light output and driver access, and finish condition. Any snag should be raised while the room is still open to us. Our service covers installation and after-sales support, including inspection, warranty coverage, spare parts and ongoing maintenance, alongside custom and OEM manufacturing and logistics with door-to-door delivery, so a single supplier can carry the unit from the drawing through to the room.