Floor-to-ceiling modular systems sit at the awkward boundary between furniture, joinery and interior fit-out. That is exactly where procurement errors hide: a unit approved as "furniture" on the bill of quantities still has to meet the finished floor level, the ceiling set-out and the services running behind the wall. When we prepare Santerson Floor to Ceiling Modular Systems for a residential or villa project, our documentation follows a fixed order, and every line in it exists to remove one specific risk from site. Below is that record, written so your team can hand it straight to a main contractor or client.

1. The room record: dimensions taken against finishes, not structure

Made-to-measure production only works if the numbers describe the room as it will be when the unit is installed. We ask for, and confirm back in writing:

  • Floor-to-soffit height at several points across the run, not one measurement — slab levels and ceiling constructions vary along a wall.
  • The completed floor finish level, with the build-up called out (screed, adhesive, tile or engineered board thickness), because that determines whether the base of the unit is trimmed on site or in the factory.
  • Wall plumb and square, plus the position of skirting, architraves and any reveal or shadow gap.
  • Fixed obstructions: switches, sockets, radiators, sprinkler heads, ceiling lights, return air grilles and door swings that cross the elevation.

Our recommendation is simple: send the raw survey, and let our technical team draw the shop drawing from it. A dimension adjusted twice — once by the client's draftsman, once by the factory — is where tolerances disappear.

2. The configuration record: what each module actually does

Modular systems are specified as a layout, not as a model number. For each elevation we document the mix of closed units, open display shelving, drawer units and floating components, and we state which modules carry load (media equipment, stone or marble panels, dense books) and which are decorative only. Where a project combines open and closed modular systems, the split is drawn on the elevation with door swing directions, handle detail and shelf spans marked.

If a run includes lighting, we treat it as an electrical item from day one: fitting type, driver location, cable route, switching or dimming control, and who terminates the supply — our electrician's requirement is written into the drawing rather than discovered during installation.

3. The material and finish record

The product pages list material and finish options, but an option name on a screen is not a specification. For each surface we confirm the substrate, the surface material (veneer, lacquer, laminate, glass, metal frame), the sheen level, and the edge treatment — 2 mm edge banding versus a mitred veneer edge changes both price and appearance under raking light. We supply physical samples for sign-off before production release, and we record the approved sample reference against the drawing number so the factory and the site are matching the same object.

Where a floor-to-ceiling system abuts building finishes such as wall panels or engineered flooring, we document the junction detail: which material butts into which, and what gap is expected.

4. The interface record: floor, ceiling and wall

This is the section most often missing from a purchase order, and it decides whether installation runs in a day or a week. We document how the unit meets the floor (plinth, recessed toe, or glass/stone floor protector), how it meets the ceiling (fixed shadow gap, flexible mastic joint, or a scribe to follow slab movement), and how side returns handle out-of-plumb walls. For very long runs we state the number of joints and where they fall in relation to visible module lines.

5. The commercial and delivery record

Modular systems are made-to-order, so a change after release is expensive. Our order confirmation records the drawing revision that production was released against, the pack list with crate numbers mapped to each elevation, and the delivery address with access notes — lift dimensions, stair widths, parking restrictions and any crane or hoist requirement. Under our logistics and door-to-door delivery service, freight mode, Incoterms and packaging are stated on the same document, so nobody is guessing who is responsible at which point.

For multi-unit developments we also record whether configurations repeat. A "standard" bathroom or living-room module that varies in one dimension between unit types should be issued as separate drawings, not one generic detail with a footnote.

6. The installation and handover record

Before the crates arrive we confirm site readiness: wet trades complete, floor finishes laid, painting at final coat, heating running, and secure storage for components. After installation we produce a snag list with photographs, an as-built mark-up of any dimension adjusted on site, and a maintenance note covering surface cleaning agents and hardware adjustment. Warranty scope and spare-parts availability are written into the handover pack rather than quoted verbally.

A short checklist for your next enquiry

If you send these six items, we can usually return a priced, production-ready proposal without a second round of questions: room survey with finish levels; the elevation or layout intent; the module mix and load requirements; finish selections with sample approval; interface details at floor, ceiling and adjacent materials; and delivery access information. Our turnkey project solutions team can also take the survey and shop drawings in-house when your programme needs them.

Send drawings, a room list or even a photograph of the wall to our project desk, and we will come back with the documentation gaps before you commit to a price.