A wardrobe panel with a mirror finish on one side and a matte finish on the other is easy to specify and easy to damage. The difference between a clean handover and a snag list usually comes down to paperwork prepared before the two tone acrylic wardrobes leave the factory, not to what happens on site. An installation plan is that paperwork: a single document that tells the site team what arrives, what it must fit into, who does what, and how any defect is settled.
For contractors and procurement teams ordering built-in joinery from overseas, the plan also protects the commercial relationship. It records the agreed tolerances, the sequence of works and the responsibility boundaries between trades, so a dispute about an out-of-square wall does not stall the whole built-in furniture package.
1. Confirmed dimensions and the as-built survey
Our two tone acrylic wardrobes are made-to-measure: sizing, layout and finish are specified per project, so nothing on site can be adjusted once the panels are cut. The plan should therefore attach the survey that production worked from, not an architectural drawing.
Record for each unit the finished width, height and depth; the floor-to-ceiling variation at three points across the run; the plumb deviation of the back wall; and the position of every fixed obstruction — switch plates, skirting, air-conditioning returns, downlights, door architraves. State which figure governs where drawings and site measurements disagree, and note who signed off the difference.
2. Finish schedule and grain direction
A two tone scheme fails on details rather than on colour. Put in writing: the acrylic surface for each panel (gloss or matte), the light side and the dark side, the edge-matching rule, and the direction of any wood-effect grain across the elevation. Gloss acrylic reflects the room, so also note where strong daylight or downlights fall on the frontage — a reflection line is a finish decision, not a defect.
Include the door style and opening method, handle or handleless groove, and any glass or illuminated insert, cross-referenced to the approved quotation. If the same acrylic appears elsewhere in the project, list those items too so that panels from different batches are compared before installation.
3. Internal configuration and hardware
The plan should carry one shelf-plan drawing per unit: hanging rails and their heights, drawer stacks, shelf spans, shoe or trouser slides, lighting channels and cable routes. Hardware is where a wardrobe feels cheap or solid, so specify the hinge and slide type, the soft-close provision, the load rating for shelves, and which items ship loose for on-site fitting versus pre-assembled.
Mark anything that must be decided before panels are cut — an integrated vanity light transformer, a ventilation gap behind a drawer bank, or clearance for a sliding door track. Decisions left open until installation days are the most expensive ones.
4. Site conditions and pre-installation checklist
Built-in joinery is a finishing trade and must follow, not lead, the wet and messy work. The plan lists what has to be complete before delivery reaches the room: plastering cured, floor levels laid and protected, painting completed behind and around the footprint, electrical final fix in position, doors and architraves hung, and dust-controlled storage for the crates.
Add an access route check — lift dimensions, stair turns, corridor widths, crate size and weight per piece — plus a receiving date that allows inspection before other trades vacate. For apartments this single line often saves a return trip.
5. Installation sequence and responsibility boundaries
Set out the order of work: pack layout and dry-stack in the room, carcass levelling and packing to uneven walls, wall fixing method by wall substrate, doors hung and adjusted, drawers and slides fitted, trims and scribes cut on site, then protective film removed last. Name the party responsible for each step — joinery installer, general contractor, electrician, plasterer — including making good around scribed edges and patching fixing holes.
State the adjustment tolerances you will accept: door gaps and parallelism, drawer run-out, slide smoothness. Agreeing these in advance prevents a subjective snag from reopening a settled order.
6. Packaging, unloading and damage control
Acrylic frontages scratch at the corner first. The plan should describe how panels are packed and identified, which crate holds which unit, edge protection type, and the inspection window after arrival. Include a photographic receiving record — crates before opening, each panel face, corners — because that evidence is what allows a replacement to be ordered without argument.
Note handling rules for gloss faces: no dragging panels across each other, cotton gloves for frontage handling, panels stored upright and off the floor.
7. Snag list, handover and after-sales
Close the plan with a snag sheet template listing unit reference, defect description, photograph, responsible party, target date and sign-off. Attach the care and cleaning note for acrylic frontages — soft cloth, no abrasive or solvent-based cleaners — and record what the warranty covers, what spare parts are held, and how a replacement panel is ordered.
Our Furniture Installation and After-sales Support service covers on-site installation, inspection and snagging, warranty handling, spare parts and ongoing maintenance; the same document that guides fitting becomes the reference for any later claim. As part of our Custom & OEM Service, we produce wardrobe panels to project-specific dimensions and finish options, so the plan you sign before production is also the specification we manufacture against.
8. Common failures the plan prevents
- A depth taken from a drawing rather than a survey, leaving sliding doors binding against an architrave.
- Gloss and matte faces swapped on elevation drawings, discovered only after the room is furnished.
- Wood-effect grain running in opposing directions across a run of doors.
- Wardrobes delivered before painting and flooring are complete, with panels stored in a dusty corridor.
- No agreed snag sheet, so door adjustment is argued as extra work instead of recorded and closed.
A short pre-production checklist
- Attach the signed as-built survey with levels, plumb and obstructions.
- Confirm every finish, tone assignment and grain direction in writing.
- Fix the internal configuration and hardware schedule before cutting.
- List site preconditions, access route and receiving inspection window.
- Define installation sequence, trade boundaries and acceptance tolerances.
- Agree packaging standard, damage evidence and the snag sheet format.
Prepared this way, an installation plan does two jobs at once: it lets us manufacture to a fixed specification, and it gives the site team one document to work from. If you are specifying built-in joinery for a villa or apartment package, send us the drawings and survey together with your finish schedule, and we will confirm dimensions and selected specifications for each project before production begins.