A decorative moulded paneled wardrobe looks simple on a mood board and complicated on site. The profile depth, the way the panel meets the frame, the door opening direction and the finish all have to agree before production starts — otherwise the correction happens after the cabinet is already in the container. The checklist below follows the order a buyer actually works in: space first, then specification, then supplier terms.
1. Room and access data
Collect the numbers before you look at styles. For each wardrobe position record the finished floor level, the finished ceiling or soffit line, wall straightness, and the position of skirting, cornices, downlights, air grilles and switch plates. Note the door swing in the bedroom and the clear width of the corridor or stairwell the assembled units have to travel through.
- Width, height and depth measured at three points each, with the smallest dimension used for clearance
- Out-of-plumb walls and out-of-level floors, with how much packing or scribing is allowed
- Obstructions: bulkheads, pipes, radiators, skirting, architraves, handle clearance against adjacent doors
- Delivery route — lift dimensions, stair turns, doorway widths at the property
For made-to-measure work these figures go to the factory as finished-line dimensions, not as raw structural measurements. Say so explicitly on the drawing.
2. Door type and opening geometry
The door type decides internal layout more than any other decision. Hinged doors need clear swing space in front of the unit; sliding doors save that space but halve the accessible opening and usually reduce overall depth allowance for the track. Corner and L-shaped positions need a defined strategy for the return — carousel, open shelf, or a blank end panel.
- Hinged paneled doors: check handle clearance against the opposite wall or bed
- Sliding doors: confirm track depth, floor guide type and how many leaves overlap
- Corner positions: decide what is genuinely reachable before adding internal hardware
If the project calls for a traditional paneled look on hinged doors, compare Paneled Hinged Wardrobes against the moulded option before fixing the elevation.
3. The panel itself — what to specify in writing
This is where decorative moulded work goes wrong most often. A "paneled wardrobe" can mean several different constructions, and the visual result depends on details that are easy to leave out of a purchase order.
Profile and depth
State how deep the moulded profile is, whether the field of the panel is recessed or raised, and whether the moulding is machined from one substrate or applied as a separate moulding. Applied mouldings introduce joints at the corners; state whether those joints are to be mitred and filled, and what tolerance you will accept.
Substrate and finish
Name the substrate and the finish system separately. Painted and lacquered mouldings behave differently at edges and detail lines, and a finish sample under site lighting tells you more than a catalogue image. Where the brief is closer to a classic solid-wood joinery look, Classic Paneled Solid Wood Wardrobes sit in a different specification bracket and should be quoted as such.
Consistency across the set
Where wardrobes appear alongside other paneled cabinetry — vanity units, linen cabinets, media walls — require matching panel profile, edge radius and sheen level across all items. Order these as one package with one finish reference rather than as separate line items from separate schedules.
4. Internal layout and hardware
Work the internal layout from actual storage requirements: hanging lengths for short and long garments, drawer count, shelf spans and their load, shoe and luggage positions, and anything that needs lighting.
- Hanging heights: double hang for mixed wardrobes; keep long-garment runs where the ceiling allows
- Drawers: front-fix or side-fix runners, soft close, and whether drawer fronts are paneled to match doors
- Shelf spans: state the load and confirm shelf thickness and support type for wide spans
- Lighting: recessed or surface fittings, driver location, switch or sensor, cable route before assembly
Hardware brands vary by market. If the project already has a preferred hinge, runner or handle supplier, name it in the enquiry rather than accepting an equivalent at quotation stage.
5. Tolerances, scribing and site interface
Decide in advance how the unit meets an imperfect building. Common options are a scribed filler, a recessed shadow gap, or a face frame that bridges the deviation. Each looks different once installed, so agree it on the drawing.
- Ceiling interface: crown detail, shadow gap, or box to ceiling — and who supplies any bulkhead
- Floor interface: plinth height, toe-kick material, and whether adjustable feet are acceptable behind the plinth
- Adjacent finishes: tiling, plaster line and skirting removal/reinstatement responsibility
- Expansion allowance for humidity where the room is heated, cooled or damp
6. Documentation to approve before production
Nothing should enter manufacturing until these are signed off. This single step prevents most on-site corrections.
- Dimensioned elevations for every unit, with finished-line dimensions and facing directions
- Section through the door and panel showing profile depth and edge detail
- Internal layout plan per unit with hardware schedule
- Approved finish sample, referenced by code and held on site
- Packaging and assembly method: fully assembled carcasses or flat-pack, and who assembles
7. Commercial terms a buyer should not leave open
- What the price includes: carcass, doors, panels, internal hardware, plinth, scribing pieces, lighting
- Packaging standard for glazed and moulded components, and container loading plan
- Shipping terms, insurance responsibility and named delivery address
- Inspection point before shipment, and what is inspected
- Spare-parts provision for hinges, runners and handles, and how replacements are ordered later
- Installation scope: supplied drawings only, factory installer on site, or local trades under your supervision
Where wardrobes are one part of a wider fit-out, grouping them with the rest of the joinery under one coordination process usually reduces interface disputes. The Custom & OEM Service covers bespoke profiles and finish selection, and Installation & After-sales Support sets out what happens after delivery — confirm the current scope for your specific project rather than assuming it.
8. The short version of the checklist
- Finished-line dimensions, floor level and ceiling line verified on site
- Door type confirmed against available swing or slide space
- Panel profile, substrate, edge detail and finish stated by drawing and sample
- Internal layout driven by real storage needs, with a hardware schedule
- Scribing method, ceiling and floor interface agreed on paper
- Elevations, sections and approved finish sample signed before production
- Inclusions, packaging, shipping terms, inspection point and spares agreed in writing
- Delivery route and installation responsibility assigned to a named party
If every line above has a written answer before the order is placed, the wardrobe arrives as an assembly problem rather than a remedial one.
SANTERSON manufactures Decorative Moulded Paneled Wardrobes to project-specific dimensions, layout and finish, alongside the wider wardrobe and cabinetry range. Send elevations or a room sketch and the specification points above, and the quotation can be built against the same details you intend to approve.