A paneled hinged wardrobe looks simple on a drawing: doors with a framed panel field, hung on hinges, in a niche or along a wall. It fails on site for reasons that have nothing to do with the door itself — an out-of-square wall, a floor that rises across the run, skirting that was fixed before the joinery was measured, or a hinge line decided after the wardrobes were already packed. The installation plan is where those problems get solved on paper, at no cost, instead of solved with a saw and a shim in front of a client. Below is the working checklist we use for paneled hinged wardrobes on villa and apartment fit-outs, from site survey to handover.

1. A survey that records the room, not just the opening

Send one measurement sheet to site with three columns: nominal dimension, measured dimension, and deviation. Wardrobe runs rarely sit in square rooms, so the plan needs the actual numbers at high, middle and low points of the opening, plus the floor level at both ends of the run and at the door swing. Note everything that will interfere with a leaf swinging open: light switches, thermostat heads, curtain tracks, air-conditioning returns, door handles of the room itself, and skirting depths.

Record the finish build-up as well — the floor covering that has not been laid yet, the plaster thickness still to come, the tiled set-out in an adjoining bathroom. A height agreed before the screed is poured will arrive short of the ceiling line and turn a full-height unit into an awkward gap that has to be scribed or boxed on site.

2. A door schedule, because "hinged" is not a specification

Every leaf needs its own line in the plan: width, height, panel style, orientation (which way it opens), hinge side and handle side. Panelled doors are read from the front, so a reversed hand cannot be corrected after the panel field is routed. For a classic wooden hinged wardrobe, also state whether the panel field is raised or flat, and how the moulding meets the carcass edge.

Add a swing check to the schedule. A standard leaf needs clear floor in front of it, and the plan should show what happens when two leaves meet at a corner — which one stops first, whether a corner post is needed, and whether the internal shelf layout can still be reached with the door open. Corner runs are where hinged door corner wardrobes earn or lose their keep, and an error in the return depth leaves a shelf hard to reach for the life of the project.

3. Hinges, clearances and opening hardware written down

The plan should name the hinge type, the cup diameter and inset, the opening angle, and whether soft-close is fitted — and then state the resulting door-to-door and door-to-side clearance. Panelled leaves are bulkier at the stile than flat doors, so a clearance copied from a flat-door detail will show as a rub over time. Count the hinges per leaf against the leaf height and weight the schedule declares, rather than relying on a default of two.

Decide the handle or pull detail in the same document, because it fixes the reveal between adjacent leaves and any glass, mirror or ribbed insert next to a panelled door. If a project mixes finishes across one wall — as with two tone hinged wardrobes — the plan should show where the break occurs and who is responsible for protecting the lighter face during installation.

4. Interface responsibilities: wall, floor, ceiling, services

One page of the plan should list what has to be finished before the wardrobes land on site: plaster complete and dry, floor covering laid to the wardrobe line, skirting removed or omitted in the run, electrical outlets relocated away from the carcass back panel, and any downlight or strip-light provision inside the niche. Built-in joinery is unforgiving of "we will paint behind it later".

Also fix who supplies and who fixes the scribing, beading and any pelmet or valance needed to close an uneven ceiling line. If that decision is left open, it becomes a variation on installation day.

5. Internal layout agreed before manufacture

Shelf heights, hanging heights, drawer positions and any lighting inside the carcass belong in the plan, with dimensions from the finished floor. Hinged doors mean the interior is hidden, so mistakes surface after handover as complaints rather than as visible defects. Where a project needs a different balance of shelf and drawer storage, confirm it at this stage — shelf focused modular wardrobes and drawer-led layouts are not interchangeable once the carcass is cut.

6. Finish schedule with a physical sample sign-off

Name the substrate, the finish system and the sheen for every visible face, including the inside of the panel field and the edges that meet a wall. For lacquered and veneered panelled doors, approve a physical sample board against the paint or laminate code before production starts; a colour number alone does not carry sheen or grain direction. Keep the signed sample with the plan — it is the reference for any later replacement leaf.

7. Sequence, access and storage on site

Write the installation sequence into the plan: delivery date, storage location, acclimatisation if the site is damp or unheated, the trade that must be finished before joinery starts, and the order of rooms. Panelled leaves are the component most easily damaged in transit and among the slowest to replace, so note how they travel — upright, faced to faced, edged protected — and who signs for them on delivery.

8. A snag list that is closed before handover

The final page of the plan is the acceptance list, filled in on site: every leaf closes onto its reveal without pressure, no stile rubs its neighbour, soft-close engages on every door, handles sit at the stated height, scribing is tight to the wall along its full length, and internal fittings match the drawing. Sign it with photographs of one typical run per room type. That record protects both the installer and the client when a hinge needs adjusting a year later.

How this fits a made-to-measure supply

Our wardrobe ranges are built to project dimensions, with material and finish selected per project and layout set out from your drawings — the same approach across built-in furniture for villa and hospitality fit-outs. If you send the survey sheet and the door schedule described above, we can price the run against it, flag anything that will not clear on site, and produce a sample board before production. For projects that need joinery coordinated with cabinetry, flooring and wall finishes under one supply, our turnkey interior project solutions cover design coordination, production, delivery and installation support.

Send drawings and measured deviations for a quotation, or ask for the wardrobe survey template before your site measurement is taken.