A set of decorative moulded paneled wardrobes can look flawless in the showroom and still fail on site. Moulded door panels are wide, shallow and easy to chip; a carcass that is out of plumb by a few millimetres will bind every hinged door on the run. The difference between those two outcomes is almost never the joinery itself — it is whether someone planned the delivery sequence and the installation window before the wardrobes left the factory. This guide walks through that planning in the order a buyer actually needs it: specification lock, packaging, freight, site readiness, installation and handover.
Why moulded panel wardrobes are harder to schedule than flat-pack units
SANTERSON's decorative moulded paneled wardrobes sit in the Classic Paneled Wardrobes family and are made to measure: dimensions, layout, substrate and finish are specified per project. That flexibility is what makes them fit a villa bedroom or a hotel guest room properly, but it also removes the safety net that flat-pack cabinetry offers.
- Made-to-measure carcasses cannot be trimmed on site to absorb a wall that has moved out of line during other trades' work.
- Moulded and raised panels carry profiled edges and mouldings that chip if they are dragged, stacked flat or loaded against a container wall.
- Hinged door alignment depends on the carcass being level, plumb and square — so site preparation is part of the product outcome, not a separate concern.
- Because each run is project-specific, a measurement error discovered after production starts becomes a remake, not a stock substitution.
Plan the calendar backwards from the installation date, and treat the delivery date as something you control rather than something that happens to you.
Stage 1 — Lock the specification before anything is scheduled
Every downstream date depends on one confirmed drawing set. Before production is released, close out these items in writing with your supplier:
| Decision to close | Why it blocks delivery and installation |
|---|---|
| Final room dimensions and floor levels | Carcass heights and scribe allowances are set from these; late level changes force remakes or on-site packing out. |
| Door type and swing | Hinged, sliding and corner configurations need different clearances and different hardware fixings. |
| Panel profile and finish | Moulded profiles in lacquer or veneer are more handling-sensitive than a flat melamine door; this drives the packing spec. |
| Interior layout | Shelf, drawer and hanging arrangements determine panel weights and which units need two installers. |
| Adjacent finishes | Flooring, skirting, plaster and architraves must be scheduled around the unit, not after it. |
| Delivery address and access | Lift sizes, stair widths and gate clearances determine crate dimensions and whether units can be brought in whole. |
SANTERSON's design coordination service covers drawings, production coordination and on-site guidance, so use it at this stage rather than after the goods ship. Confirming dimensions and selected specifications for each project before release is the single cheapest way to protect the programme.
Stage 2 — Specify the packing before production starts
Packing is a specification item, not a supplier courtesy. Ask for it on the quotation and confirm it against the finish you have chosen:
- Moulded door panels should travel upright in timber crates with edge protection on the profiled long edges — flat stacking concentrates load on the moulding.
- Carcasses ship knocked down or assembled depending on size; confirm which, because it changes both the crate count and the install sequence.
- Glass-fronted variants and mirrored doors need separate crating and should be labelled for last-in, first-out unloading.
- Hardware, hinges, slides and handles travel in a marked box that opens first on site, so the fitters are not unpacking panels to find fixings.
- Every crate carries a room or unit mark that matches the layout drawing, which is what makes an unload of eight crates manageable in one shift.
If the wardrobes share a container with other fit-out goods — cabinetry, doors, wall panelling — say so early. Loading order matters more than most buyers expect: wardrobe crates buried under heavier joinery get damaged on the voyage, not in your warehouse.
Stage 3 — Choose the freight mode around the site date, not the price
SANTERSON arranges freight forwarding by sea, air and rail, together with customs paperwork, container loading and door-to-door delivery. For made-to-measure wardrobes the choice between those modes is a scheduling decision:
| Situation | Practical approach |
|---|---|
| Full villa or multi-unit fit-out, no hard on-site date | Sea freight with the wardrobes consolidated alongside other joinery; one delivery event to coordinate. |
| Remake, replacement panel or hardware shortage | Air freight for the single component rather than re-scheduling the whole installation crew. |
| Several apartments on the same specification | Batch production with staged deliveries by building, so each install team works on one set at a time. |
Two points to settle with your forwarder before booking: who clears customs and who is the named consignee, and exactly where the truck is allowed to stop. Door-to-door delivery only helps if the last hundred metres have been checked — a street with no parking, a basement loading bay with a 2.1 m height limit, or a lift too shallow for a carcass crate will each cost you an install day. Transit time, duties and Incoterms should be confirmed case by case for the specific destination; treat any quoted figure as provisional until your forwarder confirms it in writing.
Stage 4 — Make the room ready before the crates open
This is where most programmes lose a day. A wardrobe installation crew arriving to find wet plaster or an unfinished floor will leave, and their next available slot may be weeks away. Confirm site readiness against this checklist:
- Flooring laid and level, with levels recorded at the unit position — not just "complete".
- Walls plastered, dried and painted up to the line where the carcass meets them, with scribe areas left clean.
- Electrical positions for in-cabinet lighting confirmed against the approved layout drawing.
- A clear, dry, lockable storage area at the delivery point for the crates between arrival and installation.
- Access route from kerb to room measured and free of other trades on the delivery day.
- Other trades — flooring, curtains, upholstery — scheduled after the wardrobes, not alongside them.
Stage 5 — Sequence the installation day
SANTERSON provides furniture installation and after-sales support for interior projects, including on-site installation, inspection and snag resolution. Whether the fitters come with the goods or are your local crew, the day runs better in this order:
- Inspect before unpacking everything. Check each crate externally on arrival, then open one unit and inspect the panels while the packing is still intact — that is when a transit claim is easiest to document.
- Lay out against the drawing. Match every crate mark to the layout before fixing anything to a wall.
- Level and fix the carcasses first. Pack, shim and fix each case to plumb and square before any door goes on.
- Hang doors from one end of the run. Adjusting a long run of hinged moulded doors works best progressively, ending at the reveal where the profile meets the wall.
- Fit drawers, shelves and lighting last, then set handle positions once door gaps are correct.
- Walk the snag list with the client on site and record it in writing before the crew leaves.
For a multi-unit project, install one complete room first as a reference unit and have it signed off. Every subsequent room then has an agreed benchmark for gaps, finish and hardware position, which removes most of the argument at handover.
Stage 6 — Handover, warranty and after-sales
Close out the job with documents rather than a handshake:
- A signed snag list showing what was rectified on site and what remains open.
- The approved specification sheet — panel profile, substrate, finish code, hardware model — filed against the unit for future reorders.
- Written warranty terms covering what is included, what is excluded, and how a claim is raised.
- A spare-parts route for hinges, slides and replacement moulded panels, since these wear or get damaged over a building's life.
- Care and cleaning guidance appropriate to the finish you specified, passed to the facilities or household team.
Response-time promises on supplier websites vary by destination and by what is under warranty. Get the terms that apply to your project confirmed in writing before installation, rather than relying on published marketing copy.
A practical timeline template
| Milestone | Owner | Evidence that it is complete |
|---|---|---|
| Specification sign-off | Buyer + supplier | Approved dimensioned drawings and finish codes |
| Packing spec agreed | Supplier | Crating detail on the order confirmation |
| Production release | Supplier | Order acknowledgement with the agreed ship window |
| Freight booked | Buyer + forwarder | Booking confirmation, named consignee, delivery address validated |
| Site readiness walk-through | Buyer / site manager | Signed readiness checklist against the list above |
| Delivery | Forwarder | External crate inspection recorded on the delivery note |
| Reference unit sign-off | Client | One completed room approved as the benchmark |
| Full installation and snag list | Install crew | Written snag record with owners and dates |
| Handover pack issued | Supplier | Specification sheet, warranty terms, spare-parts route |
Dates are deliberately left blank. What matters is that each milestone has a named owner and a document that proves it closed — that is what stops a delivery arriving into a room nobody has finished.
Frequently asked questions
Should decorative moulded paneled wardrobes be delivered before the flooring is laid?
No. Carcass heights and scribe allowances are set from the finished floor level, and fitters need a hard, level surface to work on. Deliver after the flooring is complete and the level has been recorded at the unit position.
Can damaged moulded panels be replaced without re-doing the whole run?
Usually yes, if you have the approved specification sheet on file — panel profile, substrate and finish code let a replacement door be made to match. That is why the specification document belongs in the handover pack, not only in the pre-production email chain.
What goes wrong most often on delivery day?
Access. Crates sized for a loading bay that has a tighter turn than the drawing suggested, or a lift too shallow for an assembled carcass. Measure the route from kerb to room before the crating specification is fixed.
Who should install — the supplier's crew or local labour?
For made-to-measure moulded panel work, the party that supplied the units should at least supervise the first room, because door adjustment on a long run is where finish quality is won. SANTERSON offers on-site installation and site coordination as part of its project services; local crews work well once a reference unit has been signed off.
If your project needs made-to-measure joinery coordinated end to end, SANTERSON's turnkey solutions cover design consultation, material selection, manufacturing and quality control, project management, site coordination and final handover — with logistics and door-to-door delivery arranged by sea, air or rail. Send your drawings and site access details early, and the delivery and installation plan writes itself.