Matte lacquer cabinets read beautifully on a rendering and can behave very differently on site. Fingerprints along the door edges, two shades of the same grey meeting at an island return, a handle rebate that no longer clears the bench top: most of these problems are decided long before production starts. If you are specifying cabinetry for a villa or apartment package, the coordination work happens between three documents - the design drawing, the site survey and the specification sheet. Below is the sequence we follow when a project arrives as matte lacquer cabinets with drawings attached.

1. Start from the drawing, not the finish board

A finish sample answers one question: what does the colour look like. A drawing answers the questions that drive cost and lead time - how tall the carcass runs, whether the doors are slab or framed, how the run terminates at a ceiling void, and which appliances have to be built in. Before choosing anything, mark up the elevations with four items:

  • Every dimension already set by someone else - floor finish levels, window reveals, existing service runs, appliance housings.
  • Every junction where cabinet meets another trade: stone worktop, tiled splashback, plastered wall, engineered timber floor, ceiling.
  • Every door and drawer front that opens into a traffic aisle, including the swing arc at full extension.
  • Every element you intend to repeat elsewhere in the project, so the same finish can be ordered in one batch.

Our cabinetry is made to measure from your elevations and sections rather than a standard module grid, which means the drawing has to be the version you are willing to build from. Send the revision number with the enquiry, not just a PDF.

2. Fix the finish language before anyone quotes

"Matte" is not a specification. On one project it means a low-sheen lacquer over sprayed panels; on another it means a matte acrylic or melamine foil, and those behave differently around edges, under kitchen lighting and after years of daily use. When you issue the enquiry, state the finish family, the colour reference and where the units will be used, then ask for a physical sample of the exact construction being quoted - a door with its edge treatment, not just a flat panel offcut.

Three practical checks on that sample:

  • View it under the actual site lighting, at both day and night colour temperatures. A cool grey matte can pull green under warm downlights.
  • Run a thumb across the edge and the face. Edge banding, wrapped foil and sprayed lacquer take oil from skin at different rates.
  • Lay two sample panels side by side and look at them from a low angle. Sheen variation is invisible head-on and obvious obliquely.

Where the same matte tone needs to continue onto walls, media units or wardrobe fronts, keep those items in one enquiry. Our matte lacquer panels and built-in storage are specified the same way as the kitchen run, which keeps colour and sheen consistent across rooms instead of matched after the fact.

3. Reconcile the drawing with what is actually on site

Drawings assume perfect walls. Site conditions do not. Before production release, take the marked-up elevations back to the space and record:

  • Floor-to-ceiling height at several points along each run, not one averaged figure - renovated apartments and older villas can move by centimetres across four metres.
  • Wall plumb and square, especially at returns and inside corners where two runs meet.
  • Positions of waste, water supply, extraction ducts and sockets measured to the finished line of the cabinetry, including the thickness of any back panel.
  • Door and skirting clearances for anything that slides, folds or pockets into a wall.

For project work we treat this as a coordination step rather than an afterthought: production drawings are prepared from the survey, then confirmed with you before manufacturing starts. That one confirmation loop removes most of the on-site cutting that damages a matte surface.

4. Settle hardware and clearances while the drawing is still open

Matte fronts show every compromise around them. Handleless profiles, integrated handles and plain slab doors each need different gaps between fronts, and those gaps have to be drawn, not left to the installer. Agree these before the drawing is frozen:

  • Handle or profile type, and whether the profile runs continuously along a run or is cut at each unit.
  • Door swing direction against appliances, islands and adjacent tall units, checked at full opening.
  • Drawer runner type and pull-out depth where the cabinet abuts a wall, island or appliance column.
  • Integrated lighting positions, transformer access and the cable route - an inaccessible driver becomes a snag on handover day.

Corner units, L-shape and U-shape runs are where drawings most often drift from reality. Decide early whether a corner is solved with a carousel, a pull-out or open shelving, because the carcass dimensions differ for each option and the change is cheap on paper and expensive in finished panels.

5. Batch the order against the site programme

Cabinetry that arrives before the wet trades finish gets damaged; cabinetry that arrives after the flooring gets cut to fit. Plan delivery around two gates:

  • Release production only once floor levels, wall finishes and service positions are fixed.
  • Schedule drop-off after hard flooring, painting and glazing are complete, with a clear route from the delivery point to the kitchen or utility room.

For international projects we handle freight documentation and door-to-door delivery as part of the package, so the site team receives the consignment rather than collecting it at port. Share the practical completion date at enquiry stage; it changes what can realistically be batched together.

6. Protect the finish through installation and handover

A matte surface is judged on its first week. Agree the handling rules before the doors come off the packing:

  • Carcasses levelled and fixed to solid fixing points before any door is hung; scribed fillers cut on site, never front edges.
  • Doors left in protective film until other trades have finished in the room, then aligned with consistent gaps.
  • Cleaning limited to a soft cloth and mild solution - abrasive pads and solvent-based cleaners are what turn a matte front shiny in patches.
  • Snag list closed on site, with spare panels from the same production batch stored for future replacement.

Ordering spares with the main run costs little and protects you later; a replacement panel made years afterwards can sit slightly off the original tone.

What to send with your enquiry

To move from drawings to a firm quotation in one pass, include:

  • Marked-up elevations and sections with revision number, plus floor plans showing room dimensions and levels.
  • Finish family, colour reference and the rooms where each finish appears - kitchen, wardrobes, media wall, laundry.
  • Appliance schedule with model references and housings.
  • Hardware preference, lighting intent, and the site address with practical completion date.

SANTERSON is a China-based furniture and building materials manufacturer supplying custom cabinetry and interior fit-out for villa, hospitality and office projects worldwide. Send your drawings and we return production-level detail, a specification to confirm, and a delivery plan matched to your programme - contact our team to start the coordination.