A metal-frame modular wall system looks simple on a drawing: uprights, shelves, closed units, maybe a strip of integrated lighting. On site it is one of the least forgiving items to receive, because the frame has to land square against walls that were never built perfectly straight. Delivery and installation planning therefore starts long before the container is booked — it starts while the sizes are still being confirmed. The notes below follow the way our project team works with Santerson Metal Frame Modular Systems and the wider modular shelving range, so you can hand your site team a plan instead of a stack of boxes.

Why modular systems need planning earlier than loose furniture

Loose furniture can be re-ordered or replaced part-way through a programme. A made-to-measure metal-frame system cannot. Each bay is cut to the dimensions we agree with you, and one altered wall changes several parts at once. Three practical consequences follow:

  • Sizes are fixed at production release, so final site dimensions have to be taken from finished floor and wall finishes, not from architectural drawings alone.
  • The system usually shares a wall with electrical work — shelving accessories and integrated lighting both need points in the right place before the frame closes up.
  • Installation sits late in the programme, after wet trades and floor finishes are complete, which leaves little room to absorb a late delivery.

Planning around those three constraints is what most of the coordination work actually involves.

Before production: what we need from your site

For a wall system in a villa bedroom, study or apartment living area, we ask for the following while the layout is still open. Send it as one pack rather than in pieces — split information is where dimension errors creep in.

ItemWhat good looks like
Final wall dimensionsWidth, height and available depth measured to finished surfaces, with the floor-to-floor height noted for floor-to-ceiling runs.
ObstructionsPosition of skirting, architraves, switches, sockets, radiators, downlights and any recess or column.
Layout intentWhich bays are open shelving, which are closed units, and where display niches sit — a sketch with dimensions is enough.
Finish referenceThe board or sample reference you have approved, so the frame, shelves and any adjacent cabinetry match.
Electrical pointsLocation of feed and driver access where lighting or accessory power is specified; ratings confirmed by your electrician.
Access routeLift size, stair width, corridor turns, parking for the vehicle, and whether panels can be brought through the front door.

Site conditions such as out-of-plumb walls and uneven floors are common in renovation work. Tell us about them early: we can set the frame back, scribe it, or split a bay so the install team is not cutting on the day.

Delivery planning: packaging, sequence and dock

Our logistics service covers freight forwarding by sea, air and rail, export paperwork, container loading and door-to-door delivery. For a modular system the details that matter most are these:

  • Consolidation. Shelving bays, closed units and accessories travel together where possible, so nothing arrives after the install crew has been booked.
  • Packaging. Panels are protected for ocean transit and marked per room or bay, which turns an unloading job into a sorting job.
  • Delivery window. Confirm the receiving hours, dock or kerb position, and who signs. On apartment projects this usually needs building-management approval in advance.
  • Inspection on arrival. Open the packaging against the packing list while the carrier is still present, photograph any damage, and send us the photos with the item numbers the same day.
Transit time, import terms, duties and delivery scope vary by destination and change with freight conditions. We confirm them for your address and Incoterms at quotation stage rather than quoting a generic lead time in writing.

Installation sequence that avoids rework

The order below is the one we follow on residential wall-system work, and it holds whether our team installs on site or your builder does with our drawings:

  1. Confirm all finishes are complete behind and around the system: paint, flooring, skirting, glazing.
  2. Check the delivered parts against the packing list and layout drawing before opening every carton.
  3. Set out the first upright on a marked line; everything else follows from it.
  4. Fix uprights to wall and floor, checking plumb and line as each one goes up — not at the end.
  5. Run wiring and test any lighting or powered accessories before shelves close off access.
  6. Fit shelves, then closed units, then glass and display elements.
  7. Adjust doors and drawer runners, wipe down, and walk the snag list with your site contact.

Loading matters at this stage too. Tell us what the shelves will carry — books, ceramics, media equipment — so shelf depth, span and fixing details are confirmed for that use rather than assumed.

Handover and after-sales

Our installation and after-sales service covers on-site fitting, inspection with your representative, warranty handling, spare parts and ongoing maintenance. Two things make that stage painless:

  • A signed as-built sheet listing the bays, finishes and any site adjustment made during fitting. It is the reference we need if a replacement panel or shelf is ordered years later.
  • Photographs of concealed wiring and fixings before closing panels, which saves opening the system up if an electrical fault appears.

Warranty terms, response times and installer availability depend on the project location and the scope agreed in the contract. We set those out per project rather than publishing a blanket promise.

A short checklist to send with your enquiry

  • Room and wall dimensions taken to finished surfaces, plus photographs of the wall.
  • Layout sketch showing open shelving, closed units and niches, with heights marked.
  • Approved finish reference and any adjacent cabinetry we should match.
  • Electrical point locations and who is responsible for the connection.
  • Delivery address, access constraints, receiving hours and named contact on site.
  • Target installation date and the trades that must finish before it.

Send that pack and we can price production, freight and fitting as one coordinated package rather than three separate line items. As part of our logistics and door-to-door delivery and installation and after-sales support services, we keep the delivery date and the install booking on the same schedule, so the system arrives when the wall is ready for it.

If you have drawings or site measurements ready, contact our project team and we will come back with a production, delivery and installation plan for your address.