A door quotation goes wrong in two directions. Too little detail and every supplier prices a different product, so the numbers cannot be compared. Too much unstructured detail and the factory still has to ask the same questions twice before it can cost the job properly. A good request for quote (RFQ) for Santerson Decorative Interior Doors does neither: it fixes the things that drive price and lead time, and leaves the rest as clearly marked options for the factory to advise on.

Start with the schedule, not a single door

Decorative interior doors are almost never bought one at a time. In a villa or hospitality fit-out they appear as a set across corridors, guest rooms, bathrooms and service areas, and the unit price depends heavily on how many openings share the same construction and finish. Send a door schedule rather than a single drawing: one line per opening, with a unique mark that matches your drawings.

Schedule columnWhat to record
Opening markYour reference code, so the quotation can be cross-checked against the drawings and the delivery note later.
Clear opening sizeWidth and height of the structural opening, plus wall build-up thickness if known. These doors are made to measure, so state the sizes you are working to and who is responsible for final site verification.
Quantity per markRepeats of the same construction and finish are what make a bespoke price workable.
Leaf count and handingSingle or double leaf, hinge side, and which way the leaf opens. For pocket and sliding openings, state the pocket depth or the wall cavity available.
Collection requiredWhether the opening takes a decorative panelled door, a flush door that sits proud of the frame, or a concealed door aligned with the wall finish.

State the operating type and the frame detail you expect

Two openings of identical size can carry very different costs depending on how the leaf moves and how the frame meets the wall. Name the type in the RFQ instead of leaving it to be inferred from a photograph, and group your schedule lines by type so each family is quoted cleanly:

  • Hinged doors — the everyday case; specify hinge type, quantity and whether ironmongery is included or supplied separately.
  • Flush sliding doors and pocket doors — give the track, hardware and pocket details you intend to use, or ask for them to be quoted as an option.
  • Folding doors and slim frame French doors — state the number of leaves, the intended span and whether glass is required.
  • Decorative concealed doors and handleless concealed doors — confirm the wall finish to be applied to the leaf, the reveal depth and how the handleless detail is to be formed.
  • Flush interior doors — say whether the frame should be flush with one face or both, and what architrave (if any) is part of the scope.

If you are open to more than one construction, ask for both as priced alternatives on separate lines. That is far more useful than a single number that hides a choice nobody agreed to.

Specify finish and surface treatment in words, not just a picture

A reference image is helpful but not sufficient. For decorative interior doors the visible result is decided by material and finish selections that have to be named: painted or lacquered surface, wood veneer species and cut, glass type where glazing is involved, and the sheen level expected on site. Attach a mood board or project reference, then confirm in writing what the factory is quoting against.

  • Name the finish system and colour reference (for example a RAL or paint code), and state whether samples are required before production.
  • For veneered leaves, ask which cut and grain direction will be used and whether matching is required across a run of doors.
  • For glazed openings, state glass thickness, safety requirement and whether glazing beads are included.
  • List ironmongery separately — hinges, locks, handles, door closers — with make and model where the design has fixed them, or request the factory's standard offering as a priced option.

Where your drawings leave a finish undecided, mark it as an option in the RFQ rather than leaving it blank. A quotation that flags open items is easier to compare than one that quietly assumes them away.

Cover the commercial and delivery terms you will be held to

Doors are a trade-sensitive package: they arrive late in the programme, they need storage on site, and rework is expensive once walls are closed. Make the surrounding terms part of the same request so the price you compare is the price you will actually pay.

ItemWhat to ask for in the RFQ
Packaging and protectionHow leaves and frames are packed, edge protection for finished surfaces, and whether crates suit your site access.
Delivery termsDestination port or site, Incoterms basis, and how the consignment is split across shipments if phases of the job complete at different times.
Site verificationWho measures final openings, and the cut-off date after which sizes are frozen for production.
IronmongeryHinges, locks, handles and closers: make, model and quantity, or a request for the factory's standard range as a priced option.
Spares and toleranceWhether spare leaves or adjustable frame sections are available for late openings and future replacement.
After-sales scopeWhat is covered if a leaf is damaged in transit or on site, and how replacement is handled.

Santerson supplies doors as part of a wider package — joinery, wall panelling and other interior products coordinated by the same project team. If your enquiry combines several trades under one programme, say so in the RFQ and ask for coordinated shipping marks per room or floor. It is usually easier to manage than reconciling three separate deliveries at site level.

Attach what the factory needs to see

Send a short, complete pack with the request instead of answering questions one by one:

  • Door schedule in spreadsheet form, with every column above filled in or marked "to advise".
  • Relevant elevations and sections as PDF, showing wall build-up and floor levels.
  • Finish references, sample photographs or a project finish board.
  • Ironmongery schedule, if your specifier has fixed the hardware.
  • Programme dates: required on-site delivery date and any phased handover.

One page of notes is worth more than a long email. State plainly which items are firm, which are provisional, and which decisions you want the supplier to recommend.

Check the returned quotation line by line

Before comparing prices, confirm that each offer answers the same question. For every schedule mark, check: the construction and collection named; overall size versus clear opening; whether frame, architrave and ironmongery are inside or outside the price; finish system and colour reference; packaging and delivery basis; and the date the sizes must be frozen. Where two quotations differ materially, the reason is nearly always one of those six items.

A quotation for made-to-measure doors should also confirm what happens when an opening moves on site. Ask how a revised size is handled after approval — that answer often matters more than the margin on the unit rate.

Send the enquiry

If you are sourcing doors alongside other interior products for a villa, hotel or office project, send your door schedule and drawings through our contact page. We will price the schedule mark by mark, flag anything that needs site verification, and quote alternative constructions where your design is still open.