Flush sliding doors look simple on a drawing: a panel that disappears into a wall pocket and finishes level with the surrounding surface. That simplicity is exactly why they get approved too early. The visual outcome depends on decisions made long before the door reaches site — clearances, wall build-up, track support, finish continuity and who signs off the final opening dimensions. Before your project team approves Santerson Flush Sliding Doors for a villa, apartment or hospitality scheme, here is the checklist we recommend closing out item by item.
1. The opening dimensions, and who measures them
Every Santerson sliding door in this family is made to measure, with finish, layout and dimensions specified for each space. That means the number on the drawing becomes the number we manufacture to. Confirm which party is responsible for final site verification, and at what stage. A pocket opening measured off a design drawing before the wall build-up is fixed will not match the finished reveal.
Ask for the confirmed dimension sheet to be re-issued after the wet trades and finishes are complete, and treat that as the production release point rather than the concept stage.
2. Wall build-up and structural support for the pocket
A flush sliding door is only as good as the wall it sits in. Before approval, get the wall section agreed: frame type, lining, the finished thickness of each face, and the fixing detail that carries the track and the door weight. Where the surrounding wall is part of a larger joinery or panelling package, decide early whether the same supplier produces both, because the flush line between door and panel is judged at the joint, not on the door alone.
Our Integrated Door & Paneling range exists for exactly this situation, where the door must read as part of a continuous wall surface.
3. Clearance and circulation, not just the leaf size
Sliding doors save swing space, but they consume wall length. Confirm three numbers on the layout: the clear opening you actually need for circulation and furniture movement, the pocket length required to receive the leaf, and the fixed wall segment left for hangings, switches or sockets. In a compact bathroom, laundry or bedroom corridor, that leftover segment is where conflicts appear.
Where the wall length is tight, compare the sliding option against Santerson Glass Pocket Doors or a hinged flush detail before the layout is frozen.
4. Finish selection and how it will be matched
Material and finish options are part of the configuration, so approval should name the exact finish — not a mood-board reference. If the door face is to be painted on site, say so in the order and confirm what preparation the leaf arrives with. If it is supplied finished, request a physical sample for sign-off against adjacent joinery, since paint colour and sheen are where flush doors most obviously fail.
For projects specifying veneer across several door types, our Santerson Flush Hinged Doors can be specified in a matching finish so that hinged and sliding leaves in the same corridor read consistently.
5. Hardware duty, frequency of use and access for service
Agree the expected use level per opening before hardware is fixed. A bedroom door in a private villa and a store or service door in a hotel corridor carry very different cycles. Confirm track and runner specification against that use level, and confirm how the hardware remains accessible after the wall is closed — pocket doors that cannot be serviced become demolition jobs.
6. Sequencing, delivery and site protection
Sliding door leaves and frames are vulnerable in the last months of a job. Set out in the programme when frames go in, when leaves are delivered, and who protects them while other trades finish. For projects ordering doors alongside cabinetry, flooring and wall finishes from one supplier, coordinate these as one package with a single release schedule rather than separate orders arriving on different dates.
7. Who inspects the finished installation
Agree the acceptance criteria before installation: leaf alignment to the wall face, smooth travel across the full width, absence of binding at the pocket entry, and consistent gap lines. Put those criteria in the pre-installation brief so that site teams and the client's representative are inspecting against the same list.
How we support this stage of a project
SANTERSON is a China-based furniture and building materials manufacturer working as a one-stop supplier for villa, hospitality and office projects. Doors are usually part of a wider package that includes joinery, wall panelling, flooring and fixtures, which is why we run specification confirmation, production coordination, logistics and on-site installation guidance as one workflow rather than separate purchases. Production is in China and delivery goes to site, coordinated through the same project contact.
Send us the door schedule, the wall sections and the finish schedule, and we will return a specification sheet for each opening — dimensions, material, finish and hardware duty — for your team to approve before anything goes into production. If you are comparing sliding against hinged or pocket options on the same layout, ask and we will price both so the decision is made on cost as well as appearance.
Talk to our project team about door specifications for your villa, apartment or hospitality scheme: https://www.santerson.com/contact/