A metal-frame modular wall system looks simple on a render: uprights, shelves, a few lit niches. It fails on site for reasons that have nothing to do with the product itself — a dimension taken off an old drawing, a skirting line nobody recorded, an electrical outlet that sits exactly where an upright was planned. If you are specifying Santerson Metal Frame Modular Systems for a villa, apartment or hospitality fit-out, the coordination work happens before the first panel is cut. Below is the sequence we use to take these systems from drawing to installed wall.
Start with what the product page actually promises
Santerson Metal Frame Modular Systems belongs to the Modular Shelving Systems collection and is made to measure: layout, dimensions, materials and finish options are specified per project rather than chosen from a fixed size chart. That single fact drives everything downstream. There is no standard module to repeat blindly across a wall, and there is no catalogue width to design around — the system is built to the opening you confirm.
It also means the specification sheet you sign off has to be complete. The same configurable logic runs through the rest of the collection, so if your scheme mixes systems, keep one coordination method for all of them: Santerson Floating Modular Shelves and Santerson Floor to Ceiling Systems are confirmed the same way, dimension by dimension, finish by finish.
Step 1 — Reconcile the drawing set before you measure anything
Send us the full drawing package, not a single elevation. What we need to see:
- Floor and ceiling levels. Where the finished floor level is defined, and whether the ceiling is a true slab or a bulkhead or grid that the system will meet.
- Wall build-up. Substrate, plasterboard or masonry, any insulation or cladding behind the run — this decides fixing method and load path.
- Adjacent trades. Skirting, architraves, cornices, doors, radiators, curtains and blinds that will abut or overlap the system.
- Services. Sockets, switches, data points, sprinkler heads, air diffusers and light circuits shown on the same drawing the shelving is drawn on.
The most common conflict we see is a service drawn on one discipline only. An elevation may show a lit niche while the electrical drawing puts a socket in the same square metre. Catching that on paper costs nothing; catching it during installation means re-cutting a panel on site.
Step 2 — Take site dimensions against the finished condition
Made-to-measure only works if the measurement describes the wall as it will be when the system arrives. Record width and height at several points along the run, plus depth, and note out-of-plumb or out-of-square conditions rather than averaging them away. Then confirm:
- The floor finish that will sit under the system, including its build-up thickness.
- Whether skirting is removed, scribed around, or carried through behind the frame.
- Doors, architraves and reveals that reduce the clear opening.
- Obstructions above the ceiling line — ducts, beams, cable trays — if uprights run to structural soffit.
For a floor-to-ceiling run in particular, the difference between slab soffit and a set-down ceiling changes the whole vertical module. Measure both and tell us which one the system is meeting. Where an existing wall is being reused, re-measure after plastering and painting, not before.
Step 3 — Lock the layout, then lock the finish
With confirmed openings, we set out the layout: upright positions, shelf heights, open versus closed compartments, and where the display niches sit. Review this setting-out drawing the way you would review a joinery detail — with the client's actual use in mind. Shelf depths for books differ from those for display objects; a run used daily needs different clearances than one used for staging.
Only then fix the finish. Sample the exact board, veneer or lacquer and the metal frame colour together, because a system reads as two materials meeting, not one. Check samples in the room's own light at day and night before signing off. If the run sits next to kitchen cabinetry, wardrobes or wall panelling from the same package, order those samples at the same time so tones are compared side by side.
Step 4 — Coordinate integrated lighting early, not at handover
Lighting inside a modular system is not an accessory you add later. Where the scheme includes lit shelves or back panels — as in Santerson Integrated Lighting Systems — the driver location, cable route, switching point and dimming method must appear on both the furniture drawing and the electrical drawing. Confirm the electrical specification and compatibility for the chosen configuration before production starts, so the wall is wired once.
Practical checks at this stage: which circuit feeds the drivers, whether a transformer or driver stays accessible for maintenance, whether switching is at the run, at the room entry, or on a control system, and whether the dimming protocol matches the rest of the room's lighting. The same discipline applies to lit cabinetry elsewhere in the project — see Santerson Integrated Cabinet Lighting for bathroom and kitchen joinery.
Step 5 — Sequence the order against site trades
Modular wall systems sit in a narrow window in the programme. Typical sequence:
- Drawing review and setting-out confirmation.
- Site re-measure after wet trades, flooring and painting are complete.
- First-article or sample approval of finish and hardware.
- Production, with the electrical specification already issued to site.
- Delivery once the room is locked, clean and dry.
- Installation and inspection against the approved setting-out drawing.
Two rules prevent most site problems. Nothing installs before the floor finish and final wall decoration are done, and nothing measures before those finishes are fixed in specification. If the programme forces an early delivery, protect the panels in a dry storage area and keep them off the floor until the room is handed over.
Step 6 — Sign off with a documented specification
Before production, one document should carry: confirmed dimensions per run; frame profile and colour; shelf material and edge detail; load expectations for anything heavy; glass or door elements if used; lighting specification with driver and control details; and the finish reference actually approved. Keep that document through to handover — it is what your site team installs from, and what any later extension of the run is matched against.
How our project services fit this workflow
Coordination of drawings, production details and on-site guidance is part of Interior Design Services, covering space planning, furniture layouts and 3D renderings through to production coordination. Where a system is built to a project-specific detail rather than our standard configuration, Custom & OEM Service covers bespoke design, prototyping and material or finish selection. For whole-apartment or villa packages, Turnkey Solutions keeps shelving, cabinetry, lighting and finishes under one procurement and coordination process, with logistics and door-to-door delivery and installation and after-sales support arranged around the site programme.
Send us the drawing set, the room's finished levels and the service layout, and we will return a setting-out drawing you can put in front of the site team. That is where a metal-frame modular system stops being a product purchase and starts being a built element of the project.