A pocket door disappears into the wall, so nothing swings into the room and nothing sticks out along it. That is exactly why the decision deserves more attention than a standard hinged door: once the panel, frame and hardware are inside the wall lining, changes become demolition work. Before you place an order for classic pocket doors on a villa, apartment or hospitality project, here is the question list we would take into a supplier conversation.
1. What is the wall able to accept?
The first question is not about the door at all. A pocket needs a cavity deep enough to swallow the panel plus the frame and track, and it must be able to carry that opening without disturbing what the wall already does. Ask your design team to confirm, room by room:
- Wall build-up and finished thickness. The clear cavity depth has to match the pocket frame you intend to buy, not the other way round. Finish build-up — plasterboard, render, tiles, panelling — eats into that depth.
- What is inside or behind the wall. Pipework, ducting, switch cables, structural studs and insulation all have to be relocated or routed around the pocket before the frame goes in.
- Whether the wall can be opened at all. On a renovation or an occupied building, opening one side of a party wall or a tiled bathroom wall changes the scope of works far beyond the door itself.
If the existing wall cannot take a cavity, say so early. It is cheaper to change the door type on paper than to change a wall on site.
2. Single pocket, double pocket, or a different sliding detail?
Classic pocket doors are commonly specified as a single panel that slides into a single pocket. Two panels can share one pocket or use two, which suits a wide opening between a living room and a study, or a bedroom and its ensuite. Where the wall cannot be opened, an exposed sliding track is the alternative: wooden sliding doors travel on a visible track in front of the wall instead of inside it, and are made to measure in the same way. Where you want the opening to close off completely when in use, classic folding doors fold along a tracked opening and need far less wall depth.
Glass is another branch. A glazed pocket panel keeps daylight moving between rooms and reads lighter in a narrow corridor; the glass pocket doors in the same collection are specified to suit each space, on made-to-measure sizing with material and finish options.
3. Who is measuring, and against which dimension?
Never order from a drawing scale or a nominal opening. Ask the supplier to work from site-measured dimensions taken at the finished floor and finished wall level, after the floor screed, waterproofing and wall finishes are accounted for. Our pocket doors are supplied made-to-measure, with the layout, material and finish specified per project, so the measurement sheet is the document that decides everything downstream.
On multi-unit work, ask this explicitly: is one dimension repeated across every unit, or has each opening been measured individually? Small variations between units are normal in a building under construction, and they are the most common cause of doors that arrive and do not fit.
4. Which hardware set, and who supplies it?
The panel is only part of the order. Before you confirm, get in writing:
- The pocket frame, track and hanger set rated for the weight of the panel you have chosen — a solid core or glazed panel is heavier than a hollow one.
- Soft-close or plain close, floor guide or no floor guide, and whether the threshold detail has to sit flush for accessibility or a wheelchair route.
- Handles and edge pulls on both faces, plus the privacy catch if the door serves a bathroom or ensuite.
- Stopping position and architrave or skirting returns, so the joinery team knows where the lining ends and the decoration begins.
Ask whether hardware ships with the frame or is ordered separately, and whether spares are available later. Hardware inside a wall is easy to fit and awkward to replace, so a matching spare hanger set on site is worth specifying at order stage.
5. What finish, and does it match the rest of the joinery?
On a project where wardrobes, vanities, panelling and doors come from different sources, the door is the item that gets judged against everything next to it. Specify the species or veneer, the grain direction, the sheen level and the lacquer system, then ask for a physical sample rather than a printed card. Wood veneer pocket doors are offered with material and finish options specified per project, which is what allows a door to sit alongside matching cabinetry in the same room.
Ask how the finish will be protected in transit and whether both faces are finished to the same standard — a pocket panel shows one face to the room and one face to the pocket, and both should still look correct years later.
6. How does the door arrive, and when?
Pocket frames have to be installed before wall lining closes, which puts them earlier in the programme than most people expect. Work backwards from your lining date, not your handover date, and confirm:
- Production lead time for made-to-measure doors, and whether frames and panels ship together or in separate consignments.
- Packaging and crate labelling by room or unit number, so the trade on site knows which frame belongs to which opening.
- Delivery terms to site, and who handles customs clearance and inland transport. The services we list cover sea, air and rail freight forwarding with the shipping paperwork, packaging and door-to-door delivery — logistics and door-to-door delivery — so confirm the terms for your own port and site before ordering.
7. Who installs, and what happens if something is wrong?
Ask whether the supplier provides installation guidance or on-site support, and get the fixing sequence in writing for your own installer: frame alignment, packing, lining, architrave, then hardware adjustment and final hang. A pocket door that is out of plumb in the frame will drag for the rest of its life, and no amount of adjustment at the hanger fixes a frame that was set badly.
Then close out the practical detail people forget: what is covered after handover, how a damaged panel or worn hanger is replaced, and how long it takes to get that part to site. The support we list for installed projects covers on-site fitting, inspection and snags, warranty work and spare parts — installation and after-sales support. Ask which of those apply to your project and in what scope.
8. Can one supplier carry the door with the joinery around it?
Pocket doors rarely stand alone in a project schedule. They sit beside wardrobes, panelling, vanities and kitchen cabinetry, and every separate supplier means another set of dimensions to reconcile and another party to chase when something does not line up. Sourcing the openings and the built-in joinery together keeps one measurement standard across the job — see our built-in furniture range, and turnkey interior project solutions for villa, hospitality and office work.
If the specification is still open, ask the supplier to review your drawings before you order. Space planning, material selection and product specification are part of our interior design services, and a door type changed at drawing stage costs nothing.
A short pre-order checklist
- Cavity depth confirmed against the frame, with finish build-up included.
- Services relocated before the frame is set; opening signed off before lining.
- Site-measured dimensions per opening, not a repeated nominal size.
- Hardware set, weight rating, floor guide and spares listed on one order.
- Physical finish sample approved against adjacent joinery.
- Delivery date working backwards from the wall-lining date.
- Fixing sequence, warranty terms and spare-part route agreed in writing.
Answer those questions and a classic pocket door is a straightforward order. Skip them and the cost lands later, inside the wall. Send us your drawings and opening dimensions and we will specify the frames, panels and hardware against them.