Flush sliding doors look simple on a drawing: a panel that disappears into a pocket and leaves a clean wall face. In practice they are one of the few door types where the finished result depends as much on what the buyer wrote down before production as on the panel itself. Pocket depth, track support, wall build-up, finish schedule and handover sequence all sit in the procurement record. This guide lists what a procurement team should capture when specifying Santerson Flush Sliding Doors for a villa, hotel or apartment package, so that the quotation, the production drawing and the site installation all describe the same door.
Start with the opening, not the door
Santerson's sliding door range is made to measure: sizing, layout, material and finish are specified per project rather than chosen from a fixed catalogue size. That shifts responsibility onto the buyer to supply verified openings. Record for each opening the clear width and height at three points, the finished floor level, the wall build-up on both sides, and whether the surrounding structure is load bearing or a partition. Note the tolerance you are allowing, because a flush detail only works when the frame can be aligned to a true plane.
Number every opening and keep that number in every subsequent document: enquiry, quotation, drawing revision, packing list, delivery note and snag list. A single consistent reference is what stops one door being manufactured to an earlier dimension while another room waits for it.
Document the pocket and the wall build-up
A flush sliding door needs somewhere for the panel to travel. Document the pocket depth required for the panel thickness, the position of the track and its support, and how the pocket is closed and finished once the door is fitted. State which trade builds the pocket and which trade closes it, so that nobody assumes the door supplier covers structural work outside their scope.
Record the wall make-up on both faces as well: substrate, any lining, the finish material and its thickness. Finish thickness decides how much frame is left exposed and whether the reveal reads as intended. If a related detail in the same package uses Flush Wall Aligned Doors, document that pair together, because the two must share one wall plane and one finish schedule to look coherent.
Fix the finish and material schedule in writing
Material and finish options are part of the configuration, so the record needs a named finish for every leaf, frame and any associated panelling, together with who approved it and when. Sample references alone are not enough; add the room or opening each sample was approved against, since the same finish reads differently in a lobby than in a bedroom corridor.
Also record what is excluded from the door supply: glass specification where glazed leaves are involved, ironmongering if it is being sourced separately, and any wall finishes around the opening. Exclusions written at quotation stage prevent two parties arriving on site assuming the other one is fitting the track.
Capture the interface with joinery and panelling
Flush sliding doors are frequently specified next to custom cabinetry or wall panelling, where a shared reveal line or a mismatched edge detail becomes visible immediately. Document which supplier owns each interface, and issue one combined setting-out drawing rather than separate trade drawings. If the wider package is being coordinated as a whole-space fit-out through Interior Design Services, keep the door schedule inside that same drawing set so the door, panelling and joinery revisions stay aligned.
Keep one specification sheet per opening through production
Before releasing to production, confirm on paper that each opening's sheet carries the final dimensions, the approved finish, the pocket detail, the track type and the handover sequence. Log every change with a date and a reason; an unrecorded verbal change is the most common cause of a correctly manufactured door that no longer fits.
For freight, the same reference numbers should appear on packing and delivery documentation, which matters most when doors travel alongside other fit-out items under Logistics and Door-to-door Delivery. A door labelled with its opening number can be routed straight to the right floor; a door labelled "3 of 12" cannot.
Close out with a site verification record
At handover, walk each opening and record operation, alignment to the wall face, finish condition and any adjustment needed. Photograph the installed door closed and fully open, and file those images against the opening number. Where installation support is arranged through Installation and After-sales Support, this record is what makes a follow-up request specific rather than descriptive.
Keep the final as-built sheet for each opening after handover. It is the document a facilities team needs when a track needs servicing years later, and it is the fastest way to reorder a matching panel without re-measuring an occupied room.
To specify a flush sliding door package for your project, send SANTERSON your numbered opening schedule together with the wall build-up and finish selections, and ask for a production drawing per opening before release: contact SANTERSON directly.