A project order that pairs an aluminum and teak-look slat outdoor dining set with an adjustable sun lounger usually arrives on one pallet plan and has to be unpacked, assembled and placed on a finished deck or pool surround. The furniture itself is the easy half of the job. The part that decides whether your site team is happy is how well you planned the freight, the packaging breakdown and the handover before the containers were even booked.
Start with the specification, not the shipping date
The product page for this collection lists customisable frame colours and table dimensions for hospitality projects. Every one of those choices changes what gets shipped, so lock them down before you ask for a freight quote:
- Table length and width, because they drive the carton footprint and whether the tabletop ships flat or assembled.
- Frame finish, since a custom powder-coat colour is produced in its own batch and cannot be mixed freely with standard finishes on the same line.
- Lounger configuration — this range is offered as a slatted lounger with multiple recline angles. If your pool deck also needs sling loungers, that is a separate product family; see the aluminium sling sun lounger collection, which comes in sled-base, wheeled and folding versions and stacks differently in a container.
- Quantity per zone. Dining sets for a restaurant terrace and loungers for a pool deck are delivered to different areas on different days, and the packing list should mirror that split.
Getting these decisions in writing at order stage is what custom furniture design and prototyping support is for. A confirmation sheet signed by the specifier, the contractor and the factory removes most of the arguments that appear six weeks later on site.
Choose the Incoterm you can actually manage
SANTERSON describes global freight forwarding by sea, air and rail together with customs paperwork, packaging and container loading, shipment tracking and door-to-door delivery. That gives you two practical routes:
- Door-to-door. The supplier arranges the main carriage and the final leg to your gate. Fewer hands, one point of contact, but you still need to know who clears customs in your country and who pays duty.
- Port or terminal delivery. You appoint your own broker and on-carrier. More control over the last mile, more coordination for your team.
Whichever you choose, get the commercial invoice, packing list and certificate of origin in the format your broker expects, and confirm early who handles any import permit. Ask these questions in the same email that confirms the order — paperwork surprises are the most common cause of a container sitting at the terminal while the deck opening date slips.
Plan the container around site storage
Aluminium slat furniture is comparatively light, and slatted tops and sled-base chairs pack efficiently. That is an advantage when you are thinking about how much to order in one shipment, but a full container of outdoor furniture is still a handling problem on a finished site.
- Split the order into delivery blocks that match your installation programme: dining sets first for the terrace, loungers second for the pool deck.
- Agree a stacking and storage area before the truck arrives. Aluminium frames scratch against each other if loose cartons are moved with forklift tines.
- Keep the packing list keyed to your drawings. Label cartons by zone — "Level 2 East Terrace, Set 4 of 11" — so the crew does not open everything at once.
If the project is a villa or resort where indoor joinery and loose furniture are being installed at the same time, coordinate the outdoor order with the rest of the package rather than treating it as an afterthought. Turnkey project furnishing covers that coordination across indoor and outdoor scopes.
Build the inspection into the delivery day
Aluminium with a teak-look finish is chosen for exactly this reason: no oiling, no cracking the way real timber behaves outdoors, and slatted surfaces that drain rainwater quickly. That low-maintenance profile only pays off if the frames arrive straight and the coatings are intact.
- Photograph any damaged carton before signing for it, and open the affected cartons in front of the driver where your local practice allows.
- Check recline mechanisms on every lounger, not a sample. Adjustment hardware is the item most likely to bind after transit.
- Assemble one full dining set and place it on the finished surface before unpacking the rest — floor protection stays down until you have confirmed leg levelling works on your paving.
SANTERSON lists on-site installation, inspection and snags, spare parts and replacement among its after-sales services. Confirm in writing which of those apply to your project and who raises a snag report before the container is opened.
A short checklist before you place the order
- Frame colour, table dimensions and lounger configuration confirmed and signed off.
- Incoterm, customs broker and duty responsibility agreed.
- Carton labelling mapped to your zone drawings.
- Delivery blocks aligned with the installation programme and site storage capacity.
- Inspection and snag process agreed, with named contacts on both sides.
Plan those five items and the international leg of your outdoor furniture order stops being a risk. Send your drawings, quantities and target site to SANTERSON and we will confirm the packing breakdown, carton dimensions and freight options for your project before production starts.