A door schedule tells a site team what to buy. A product submittal is what lets them approve it before anything goes into production. For Classic Panel Hinged Doors, which are made to the dimensions, finish and layout of each project rather than picked from a stock list, the submittal is where those choices get written down, drawn out and signed off. Get it right and the door package moves through approval in one pass; get it wrong and you discover at handover that the opening heights were never reconciled with the floor build-up.
Below is the package we ask project teams to assemble for this collection, item by item, along with what each part is actually used for during review.
Start with the door schedule, not the product sheet
The product page describes a range: made-to-measure sizing, material and finish options, and a layout tailored to the project. What it cannot do is tell you which of those applies to room 204 on level three. That is the job of the door schedule, and it should be the first sheet in the submittal.
- A unique tag for every door, matching the tag used on the architectural joinery drawings, so nobody reconciles two different numbering systems during installation.
- Clear opening width and height, plus wall thickness, recorded from site measurement rather than from setting-out drawings alone.
- Leaf type and panel configuration for each tag — how many raised or recessed panels, their proportion, and the moulding profile where a classic panel detail is being matched to existing joinery.
- Hinge hand and swing direction per opening, checked against furniture layout and circulation, not assumed from the drawing.
- Finish specification by tag: base material, stain or paint system, sheen level, and the reference sample the finish was approved against.
Where a project mixes door styles across zones — for example panel hinged doors in bedrooms alongside Standard Interior Hinged Doors in service areas, or Santerson Decorative Concealed Doors where the wall finish continues unbroken — the schedule is also what stops a single blended line item hiding three different build-ups behind one description.
Dimensional information that survives construction
Most door package disputes start with a dimension nobody confirmed in writing. Include, for each tag:
- Finished floor level and the intended floor build-up on both sides of the opening. A 20 mm difference between corridor screed and bedroom flooring changes every leaf height in the schedule.
- Frame and lining sizes, plus how the frame relates to the wall finish — whether it is flush, rebated or set back, and who supplies the architrave or whether the door is intended to sit without one.
- Threshold and undercut dimensions where acoustic, privacy or ventilation expectations exist for the room.
- Clear opening allowance for ironmongery: hinge positions, lock case backset, strike plate location, and any door coordinator or closers carried over from another package.
A practical rule for review: if a dimension appears only in a note on a drawing and not in the submittal schedule, treat it as unconfirmed. Our production team works from the approved submittal, so anything left out is decided on site instead.
Materials, finishes and the samples behind them
Classic panel doors are read at close range, so the finish specification carries more weight than in most joinery. For each door tag, the submittal should state the core and substrate construction, the face material, and the applied finish system with its approved reference. Where a project specifies a wood-grain appearance, include the species or veneer description and the direction of the grain on stiles and rails — an inconsistency here is visible immediately once several doors are hung in one corridor.
Attach physical evidence rather than descriptions alone:
- A signed-off finish sample board for each colour or stain, dated and initialled by the party who approved it.
- A panel profile detail at 1:5 or 1:2 showing moulding radii and panel recess depth, which is where a "classic" reference either matches the surrounding joinery or does not.
- Written confirmation of the sheen level and any gloss difference between painted frames and painted wall panels supplied from separate packages.
Material and finish selection is handled as part of our Custom & OEM Service, which covers bespoke finishes, prototyping and specification review before production starts. Where a project needs a mock-up door for sign-off — common on hospitality work where the same detail repeats across many rooms — that is agreed at this stage rather than after the full order is released.
Hardware coordination
The door package and the ironmongery schedule are usually prepared by different parties, which is exactly why they need to be reviewed together. Confirm in the submittal:
- Hinge type, quantity and leaf thickness compatibility, including whether hinges are mortised or surface-applied.
- Lock, handle and escutcheon positions with lever height agreed across the project, so a single dimension drives every opening.
- Whether handles are required at all — a handleless or concealed detail changes the leaf edge preparation and must be fixed before machining.
- Closing devices, door stops and any access-control preparation, including what is routed into the leaf and by whom.
Scope, sequence and site interface
A submittal that only describes the product still leaves the commercial question open. State plainly which items are included in the door package and which sit with other trades: frames and linings, architraves, ironmongery, glass or glazed panels, thresholds, and site-made packing to finished floors.
Then record the sequence that the programme depends on: when final opening dimensions are taken from site, the cut-off date after which dimensions cannot change, production lead time from approved submittal, and delivery method to the building. For projects supplied internationally, our Logistics & Door-to-Door Delivery service covers freight arrangements, packaging and container loading planning, shipment tracking and delivery to the site address, with documentation prepared for import clearance.
Close the submittal with the interface list: who prepares the opening, who carries the wall finish up to the frame, who touches up after other trades have finished, and who signs off the hung leaves before handover. Those four questions cause most of the snags on door packages, and answering them on paper costs nothing.
Approval checklist
- Every door tag in the schedule appears once, with no unnumbered openings left to be resolved later.
- Dimensions are site-verified and reference finished floor levels on both sides of each opening.
- Panel configuration, moulding profile and grain direction are drawn, not described in words only.
- A dated, signed finish sample exists for every finish named in the schedule.
- Ironmongery positions and hinge type are cross-checked against the ironmongery schedule.
- Inclusions and exclusions are listed per door tag, not per project.
- The dimension freeze date, production lead time and delivery sequence are written down and accepted by the site team.
If your team would rather have this package assembled from drawings and site measurement than compiled internally, our project design coordination service covers specification, drawing review and production follow-up through Turnkey Solutions, with installation support and inspection at handover.
Send your door schedule, opening dimensions and finish references to PHILLIP on +86-13928214007 (phone / WhatsApp) or santerson@qq.com, and we will return a submittal package for review before any production release.