A walnut solid wood wardrobe is one of the last items to be manufactured and one of the first things a client notices when they walk into a finished bedroom. That timing makes it unusually sensitive to logistics and site readiness. This guide walks through how we plan the journey from our factory in Foshan, China, to a hung, level and adjusted wardrobe on site — and what we need from the builder, designer or project manager at each stage.
Our role covers design coordination, manufacturing, freight, customs paperwork, delivery and installation support. Site conditions — flooring levels, wall alignment, services, trade sequencing — sit with the local contractor. Getting those two halves to meet on the right day is where a joinery package either lands cleanly or turns into a variation.
Before production: what has to be fixed first
Delivery and installation problems are usually decided months earlier, in the drawing review. Walnut Solid Wood Wardrobes are made to measure for each project, with the layout, finish and dimensions specified per space, so the measurement set we produce from is the one that governs everything downstream.
Three decisions need to be closed before we release a wardrobe to production:
- Final room dimensions, taken off the finished build. Rough-in dimensions drift. Skirting, plaster thickness, floor finishes and ceiling set-downs all change the opening. We work from as-built or near-as-built dimensions, and where a room is not yet finished we record what still has to move.
- Door type and clearance envelope. Hinged doors need swing clearance in front of the wardrobe; sliding doors need clear run along the face and enough depth for the track. A layout that works on a plan can fail once the bed, ensuite doorway or a pendant drop is added.
- Fixing conditions. What the wardrobe bears against — stud wall, masonry, a framed bulkhead, a floating floor — determines the fixing detail and whether any blocking needs to be built in by others before the walls are closed.
Where the bedroom is part of a wider joinery package, we coordinate it with the rest of the timber work so the walnut doors, wall panelling and any vanity or sideboard are produced together, from the same batch logic and to the same site dimensions. Splitting those items across suppliers and production windows is the most common cause of finish mismatch on handover.
Choosing a pack size that fits the opening it has to travel through
Solid wood wardrobe carcasses are bulky, and the constraint is rarely the truck — it is the last twenty metres. Before we finalise packaging we ask for the access route on site:
- Stair well width and turning landings, for apartments and villas with upper-level bedrooms
- Lift car dimensions and door openings, including whether a service lift is available and its booking window
- Corridor widths, corner radii, and any door that has to be removed to pass a panel
- Crane or hoist access where a panel will not fit the stair at all
A wardrobe can be built as a single tall carcass or broken into sections with a site joint, and that choice is made on the access route, not on aesthetics. If a full-height side has to be split, we detail the joining so the seam falls at a planned line and the walnut grain still reads correctly across it. Panels are packed with edge protection and corner guards, and each item is labelled against the room drawing it belongs to, so the crew on site is not sorting an unlabelled stack of boards in a hallway.
Freight: how the shipment is arranged
We arrange freight forwarding by sea, air or rail, together with the commercial paperwork that moves with the goods — commercial invoice, packing list and certificate of origin. Wardrobes normally travel in a shared container alongside other joinery and building materials for the same project, which is where consolidated shipping pays for itself.
Two points matter more than people expect:
- Consolidation has to be planned around installation order, not just container space. If the wardrobes are loaded behind a batch of flooring that is needed three weeks earlier, they arrive late even though the vessel was on time. We load so that the sequence at the far end of the container matches the sequence on site.
- Customs clearance is a real duration, not a formality. Import terms, duties and any permit requirements are confirmed for the specific destination before the goods are booked. We do not promise a transit day count in writing until the routing and clearance path are fixed for that shipment.
For projects where a bedroom is needed early — a display suite, a staged villa, a hotel floor being signed off room by room — we can split the joinery into two shipments rather than hold everything for one container. That costs more in freight and saves more in program delay.
Installation planning: the site conditions we need on the day
A wardrobe install crew that arrives to a wet screed, an unpainted room or an unresolved floor level loses the day. Before we commit an installation date we confirm the following with the contractor:
| Condition | What must be true before install |
|---|---|
| Floor finish | Flooring laid, level checked and protected. Wardrobe carcasses are set on the finished floor; an unknown floor build-up changes the height of everything above it. |
| Walls | Plaster complete and dry, with the required blocking or noggins in place at fixing lines. Straightness is checked against the wardrobe face — a bowed wall is corrected on site, not by bending the panel. |
| Ceiling | Set-down level confirmed and any bulkhead or cornice resolved, so a scribe detail is cut to the actual ceiling line rather than the drawing line. |
| Services | Electrical outlets, switches and lighting — including any interior wardrobe lighting — positioned and energised for test. Downlights and pendants confirmed against door swing. |
| Environment | Building closed in, services running, space dry and clean. Solid timber should not be installed into a wet, unconditioned shell. |
| Access and storage | A dry, secure staging area near the bedrooms, plus lift or hoist booked for the delivery window. |
| Trade sequencing | Paint and floor finishing complete behind the wardrobe footprint; wardrobes installed before soft furnishing and before final cleaning of the level. |
We also agree an inspection point. Wardrobe doors are adjusted after hanging, and a level that is still being walked through by other trades will knock an alignment out again. Door adjustment therefore sits at the end of the room's trade sequence, with a snag list closed out before handover.
A practical timeline to work back from
Rather than quoting fixed durations, use this as a dependency chain and set the handover date first, then work backwards:
- Enquiry and layout review. Drawings, room dimensions, finish selection and door type. Open questions here are cheaper than variations later.
- Detail confirmation and order. Dimensions signed off against the build stage actually reached; fixing details issued to the contractor so blocking is installed before walls close.
- Manufacturing. Production with quality checks on carcass squareness, panel flatness, finish consistency and hardware.
- Packing and booking. Pack sized to the site access route; freight booked against the installation window, not simply when the goods are ready.
- Transit and clearance. Shipment tracked, paperwork ahead of the goods, delivery slot confirmed with the site.
- Delivery and install. Goods staged by room, carcasses set and levelled, doors hung and adjusted.
- Snag and handover. Inspection with the client or head contractor, punch list closed, spare parts and hardware documented for later maintenance.
The single most effective change to this chain is moving the final measurement as late as the drawing freeze allows, and confirming floor levels before we cut. Every other risk in delivery planning becomes manageable once those two inputs are correct.
Related walnut wardrobe options
Where a project wants the walnut look with a different construction or budget, Walnut Veneer Wardrobes are made to measure on the same basis, and sit alongside other built-in ranges such as Oak Solid Wood Wardrobes. Mixing solid timber carcasses with veneer doors in the same room is possible, but grain and tone have to be reviewed together before order — not after delivery.
Questions we are asked most often
When should the wardrobe be measured?
After floor finishes and wall set-outs are fixed, and before other joinery is ordered if it has to match. If that point is too late for the program, we measure at the closest controlled stage and record the outstanding tolerances on the drawing.
Can wardrobes be delivered before the bedroom is finished?
Only if there is dry, secure staging and the delivery does not block other trades. We would rather hold goods at a controlled point and install once in one visit than deliver into an active wet trade area.
Who installs on site?
Installation and after-sales support are part of our service scope, with inspection and snagging before handover. The exact arrangement — crew dispatched for the project or supervision of a local contractor — is confirmed per project, along with what is covered afterwards and which spare parts we hold.
What if a wall or floor is out on site?
Scribes, packers and adjusted sash details handle normal variation. Anything beyond that gets raised as an item for the head contractor with a proposed fix, priced before work proceeds — not corrected silently at the wall.
Planning a bedroom joinery package and want the delivery and installation sequence mapped against your program? Send us the room drawings and build stage, and we will return a make-up, access route and install plan for review. Contact SANTERSON — furniture and building materials manufacturer and one-stop project supplier, operating since 2008.