A wardrobe that arrives on site without a complete submittal package is a wardrobe nobody can sign off. For villa and apartment fit-outs, the Combination Modular Wardrobes usually mixes two or more module types in one run — hanging sections, drawer units, shelving and a finish change halfway along. That mix is exactly where submittal packages go wrong: one drawing set, several interfaces. The package below is the sequence we prepare for made-to-measure joinery so approvals come back with comments instead of questions.

1. Scope statement and module schedule

Start with a one-page scope that names every room, elevation and module in the order, plus anything explicitly excluded — internal accessories not in our supply, on-site electrical work, or finishes supplied by others. Then attach a module schedule: reference code, width, height, depth, door type, and interior configuration for each unit. A schedule written this way lets the site team match a delivery crate to an elevation without opening drawings.

For combination runs we list modules by function rather than by appearance, so a Hanging Modular Wardrobes section and an Open Modular Wardrobes bay sitting side by side in the same elevation are shown as separate line items with their own fixings and tolerances.

2. Dimensioned elevations, sections and setting-out

Elevations carry overall dimensions plus module widths; sections show depth, plinth or floor clearance, and the top condition against the ceiling line. Setting-out drawings come next: finished floor levels, wall alignment, skirting treatment, and the position of switches, sockets and air-conditioning grilles that the carcass has to work around. Where a run meets a sloping or out-of-plumb wall, show the scribe allowance rather than assuming a square box.

Send these drawings as PDF with dimension text selectable, not scanned images. Image-only drawings cost a round trip before any comment can be returned, and they cannot be marked up on site.

3. Materials, finishes and hardware schedule

List carcass and door substrates, the surface treatment for each — laminate, lacquer, veneer or glass — and the direction of grain where it matters. Note the edge treatment on visible edges, and record which finish appears on which elevation so a sample can be checked against the right face.

Hardware gets its own table: hinges, slides, handles, soft-close devices, integrated lighting where specified, and load-bearing items such as rails and trouser drawers. For projects that specify their own ironmongery, state clearly whether we supply it, fit it, or receive it on site for our installers to fit.

4. Samples and approval record

Physical samples beat printed swatches for anything with grain or sheen. We send labelled samples carrying the project reference, the finish code, and the elevation they belong to, and we log the signed return so production starts against an approved reference rather than a verbal confirmation.

Keep one approval sheet that records who signed which decision and when — finish, door style, interior layout, handle choice. When someone on site asks three months later why a drawer bank sits on the left, that sheet ends the argument.

5. Manufacturing and quality checkpoints

The submittal should say what gets inspected before packing: dimension check against approved drawings, finish and edge condition, hardware function test, and door alignment on a dry assembly where the run is complex. State how panels are protected and numbered, because crate labelling that matches the module schedule is what makes an unload on a finished floor safe.

Our Custom & OEM Service covers bespoke finishes and prototyping when a project needs a mock-up before the full order — worth requesting early on villa work, where one wardrobe often sets the finish standard for the rest of the joinery package.

6. Delivery, access and installation plan

Include container or crate dimensions against the delivery vehicle, the route from kerb to floor, lift sizes, stair widths and any turning restrictions. Wardrobe panels are long; a submittal that ignores the lift will be rejected by the building manager regardless of how good the drawings are.

Then set out installation sequence, protection of completed finishes, fixing method to each wall type, and the site conditions we need — power, lighting, clean and dry storage. Our Installation & After-sales Support service covers on-site fitting and snag inspection, so the same team that reads your drawings is the team asking for clarification on site.

7. Commercial terms and document control

Quote basis, currency, inclusions and exclusions, packaging and freight scope, and the Incoterms applied to delivery should all sit in the package, not in an email chain. Version every drawing with a revision number and date, and state which revision production will build to. Revisions that circulate without numbers are how two different door heights end up in one shipment.

Common gaps we see

  • Elevations with no setting-out against services, so installers find a switch centre of a door.
  • Finishes approved from a catalogue image with no signed physical sample.
  • Hardware shown on drawings but absent from the supply schedule.
  • No crate list tied to module references, causing unloading delays on upper floors.
  • Tolerances and scribe details left to be solved on site, with tools that are not there to solve them.

Putting the package together

Send the seven items in one file set, indexed, and ask for a single consolidated return of comments. As a SANTERSON furniture and building materials partner working on villa and apartment fit-outs, we would rather receive your submittal template than write our own — it saves the reconciliation stage that delays joinery orders most often.

If you are assembling a package now, start with the module schedule and setting-out drawings; those two drive everything else. Send them to us with your room list and we will return a quotation built on the same references your site team will be working from.