A set of classic wooden hinged wardrobes rarely stalls on design. It stalls on sign-off. One raised panel profile, one stain sample or one drawer layout can travel between the designer, the homeowner, the builder and the factory, and every round trip costs days. The wardrobes themselves are made to measure, with material, finish and internal layout specified per project, so almost everything that gets approved is a decision about fit, look and use rather than a fixed catalogue item. Below is the approval sequence we run on bedroom joinery packages, and what each party should sign before production starts.
Who actually signs what
Before the first drawing goes out, name the approver for each decision. On residential and villa projects this usually splits four ways:
- Homeowner or end user — internal layout, storage mix, door count, hardware feel, anything they touch daily.
- Interior designer or architect — panel profile, timber species or grain, finish tone, how the elevations read against skirting, cornice and flooring.
- Builder or site contractor — wall openings, floor levels, ceiling heights, clearance for door swing, and what has to be set out before plasterboard closes.
- Supplier or factory — feasibility, panel spans, hinge loading, transport breaks and how the unit is assembled on site.
Write that split into one page at kickoff. Most of the delays we see come from a decision that two people believed the other owned — typically finish tone and internal layout.
Stage 1: site dimensions and constraints, signed by the builder
Nothing else can be approved until the opening is fixed. The builder confirms finished floor levels, finished wall faces, ceiling height, skirting detail, and the position of switches, downlights, air grilles and door openings that could clash with a hinged door swing. Hinged doors need clear swing space in front of the wardrobe; a bed, a doorway or a radiator in that arc changes the layout before any aesthetic decision matters.
For built-in joinery we work from site measurement rather than architectural drawings alone, because nominal dimensions and as-built dimensions differ on almost every site. The builder signs the measured dimension sheet. That signature is what lets a made-to-measure order proceed without re-measurement after production.
Stage 2: elevations and internal layout, signed by designer and user
The approval pack at this stage is a set of elevations plus an internal layout for each bay. What the pack should show clearly:
- Door count, door widths and hinge side for every door — hinge side changes what you see when you walk into the room.
- Panel construction: raised, recessed or flat profile, moulding depth, and the stile and rail widths on a classic paneled door. These proportions are the difference between a wardrobe that reads as joinery and one that reads as furniture.
- Internal zoning by user habit: hanging heights for short and long garments, drawer zones, shelf spacing, shoe and linen storage, and any lighting inside the carcass.
- Total height strategy — full-height to the ceiling with a top cupboard, or a cut-down unit with cornice above.
Two people sign this stage: the designer for proportion and profile, the end user for layout. Where they disagree, resolve it here, not after carcass panels are cut.
Stage 3: material and finish samples, signed physically
Wood tone is the single most contested item on a timber wardrobe package, and it cannot be approved from a screen. Send physical samples of the door panel, the moulding profile in the same finish, and the carcass edge band or interior board. View them on site, at the actual wall, against the flooring and the paint scheme, in both daylight and evening light.
Where the specification calls for a specific species — walnut solid wood wardrobes, oak, cherry or mahogany are common requests on residential projects — confirm the cut and grain match as well as the colour. Two boards of the same species can read very differently depending on cut, figure and how open the finish is left.
Record the approval on the sample itself: project name, date, position it applies to, initials. Keep one signed copy of every sample in the project file. That record settles disputes at handover without anyone re-finishing a door.
Stage 4: hardware and clearances, signed by builder and user together
Hinges, handles and soft-close fittings are usually specified early and approved late, which is the wrong order. At this stage confirm:
| Item | Who approves | What to check on site |
|---|---|---|
| Hinge type and load rating | Supplier, informed by door size and panel weight | Full-height solid paneled doors are heavy; the hinge set must match the door, not the catalogue default. |
| Handles or handleless pull detail | Designer and user | Handle projection against adjacent walls, bedside tables and traffic paths. |
| Door swing arc | Builder | Doors must clear the bed, the room door and any switch plate when fully open. |
| Soft close and damper spec | User | Decide which doors and drawers get it — a full set and a partial set price differently. |
Stage 5: production release, one signature only
Production should be released once, against a frozen pack: signed dimension sheet, signed elevations with profile and moulding dimensions, signed finish samples, confirmed hardware schedule. When that pack is complete, the factory order needs no further questions, and this is where procurement through interior design services earns its keep — drawings, production coordination and on-site guidance run as one chain instead of three separate contracts.
State explicitly in the release note what is now closed. Any change after this point moves the delivery date, and that consequence should be written down before someone asks for "just one small change to the drawer layout".
Stage 6: delivery, installation and snag sign-off
Book the install window against site readiness, not against the factory date. Timber joinery needs a dry, closed-in room with finished floor levels confirmed; installing into an open site is how panels get damaged and finishes get blamed on the supplier.
At handover walk the installation with the same people who signed the drawings. Check door alignment and gap consistency across the run, drawer runners, soft-close function, finish continuity at corners where units meet, and cleanliness of cut edges against skirting and architrave. Record snags on one list with an owner and a date for each item, then sign off once closed. Installation and after-sales support covers this inspection stage along with spare parts and maintenance, so the snag list is also the document that defines what falls inside the warranty conversation.
A short approval log worth keeping
Six lines, one per stage, is enough to keep a wardrobe package honest: dimension sheet signed by builder; elevations signed by designer and user; finish samples initialled and filed; hardware schedule confirmed; production release dated; snag list closed and handed over. When all six are dated, disputes about who approved what rarely survive contact with the file.