A flush wall aligned door is one of the smallest line items on a villa or hotel schedule and one of the most expensive to get wrong. The leaf, frame and surrounding cladding have to arrive from different suppliers with the same finish level, the same opening dimension and the same idea of what "flush" means. When procurement documentation stops at a door size and a finish name, the correction happens on site, in front of a finished wall, and it is billed as a variation.
The practical answer is that a flush concealed door needs the same documentation discipline as fixed joinery. Below are the records we ask project teams to confirm before an order is released, based on how these doors are actually made and installed.
1. The opening, recorded from the wall that will be built
Record the clear opening width, height and finished floor level from the setting-out drawing that shows the completed wall build-up — not from a door schedule drafted before the partition design was fixed. Flush doors are made to measure against those confirmed dimensions, so the document has to show what the wall will be when the frame goes in: stud line, insulation or backing board, plasterboard thickness, and any service runs behind the leaf.
Where a door sits in a clad wall rather than a plasterboard partition — timber veneer panelling, stone, laminate — say so explicitly. The fixing detail and the reveal depend on that build-up, and it is the single most common reason a concealed frame arrives without the right packing arrangement.
2. Which flush detail the project actually wants
"Concealed" covers several different outcomes, and each one needs a different record. For our own ranges we ask buyers to name the type in the enquiry:
- Handleless concealed doors — no visible handle or hardware, so the document must state how the leaf is opened and which face carries the push detail.
- Decorative concealed doors — the leaf carries a deliberate pattern or moulding, so the drawing has to show how that pattern lines up with the panelling either side.
- Flush interior doors and flush hinged doors — the leaf sits in a visible or minimally revealed frame; record the reveal width you expect.
- Flush sliding doors — record the pocket depth, track position and the wall thickness that has to house the gear.
If a project mixes types across room types — handleless in the bedrooms, decorative in the lobby corridor — put that in one table rather than leaving it to be discovered room by room.
3. Finish continuity with the wall
A flush door only reads as a wall if its surface is specified at the same level of detail as the wall next to it. For painted leaves, record the paint system and sheen, not just a colour name; for wood veneer or lacquered leaves, record grain direction, the veneer cut, and whether the leaf is to be matched against an adjacent panel run. Where the wall is clad in integrated door and panelling, specify the two together as one item so the finish is produced in one batch.
Ask for a physical sample of the leaf surface, signed off against the wall sample. A colour code on a spreadsheet does not survive the difference between a painted timber surface and a plasterboard surface under the same lighting.
4. Hardware, movement and clearance
Record hinge type and load rating against the leaf size and core, the number of hinges, and whether the leaf is single or double acting. Then record the swing path: distance to the nearest return wall, any floor finish build-up in the threshold, and the clearance needed for handles where they are used. In hospitality work this is also where acoustic and privacy expectations belong — state the requirement, then confirm the specification that meets it rather than assuming a concealed frame delivers it by default.
5. Room-by-room schedule and responsibility
Give every door an ID that matches the room number on the architectural drawings, and keep one row per opening with: type, clear opening size, wall build-up, finish, hardware set, and the supplier responsible for the frame versus the wall maker. The point of the schedule is to make the interface visible. When the door supplier, the panelling supplier and the site builder are three different parties, an unassigned interface becomes a variation order.
6. Site conditions before production release
Record the wet trades that sit ahead of installation — plastering, screed, stone fixing — and the date each will be complete in the areas where doors are to be fitted. Made-to-measure joinery should be released after those levels are confirmed on site, not at tender stage. For projects shipped from our factory under door-to-door delivery, note the delivery sequence too: concealed frames need to arrive before wall closure, and finished leaves after it.
7. Handover record
Keep a signed set of as-built dimensions, finish references and hardware schedules for each door type, plus the adjustment and spare-parts route for installation and after-sales support. Concealed doors get adjusted more often than visible ones precisely because nothing gives a clue to the operating mechanism. The handover file is what stops that adjustment from becoming a replacement.
How we take these orders
Our windows and doors range is made to measure, with material and finish options selected per project, so the enquiry documents above are the same ones we need in order to quote accurately. Where a flush door forms part of a wider fit-out, it is usually better procured as part of turnkey interior project solutions, with doors, panelling and joinery produced against one coordinated set of drawings.