A walnut wardrobe drawing rarely causes trouble on its own. The trouble starts where the drawing meets the room: a skirting board that was never measured, an out-of-plumb wall behind the built-in, a ceiling that drops 20 mm at one end, or a door swing that clashes with the handle detail. Our Walnut Solid Wood Wardrobes are made to measure for each project, which means the paperwork we receive has to be as accurate as the joinery we deliver. The checklist below is the one our production team works from on residential wardrobe packages, and it is the same sequence we follow on villa projects in Melbourne, Sydney and Perth.
1. Fix the scope before the drawings move
Half of all rework on custom wardrobes traces back to scope that was never written down. Before any detail drawing is issued, confirm in one document: which rooms are in scope; whether the carcass is solid wood or a Walnut Veneer Wardrobe with matching grain direction; which interior fittings each bay carries; and who signs off the final elevation set. If your project also covers Island Walk in Wardrobes or a dressing room, note the walkway widths at that stage, because an island changes circulation and therefore door geometry.
This is also where material substitution decisions belong. Walnut heartwood and sapwood differ noticeably in colour, so state on the drawing whether a run should be matched tightly, blended, or deliberately mixed. Making that call on paper avoids a dispute at handover.
2. Read the drawings the way production reads them
A furniture elevation and an architectural plan often disagree, and the disagreement is usually harmless until something is manufactured. Before release, check these items line by line:
- Datum and levels. Confirm which floor finish level the drawing assumes — finished or structural. A 25 mm difference in floor build-up changes every wardrobe height on the sheet.
- Wall conditions. Note where walls are not square, where pipes or boxes sit behind the carcass line, and whether the wall can carry a fixed unit or needs a freestanding one.
- Openings and services. Mark switches, sockets, air-conditioning grilles, lighting circuits and any skirting that must be removed or scribed around.
- Door type and clearance. Hinged doors need swing clearance and a clear run for handles; sliding doors need track depth and headroom. State which one the drawing shows on every elevation.
- Joint and shadow details. Show how the unit meets ceiling, side wall and floor: scribed filler, shadow gap, or cill return. Ambiguity here is the most common cause of an untidy installation.
Where our design team is engaged, this coordination sits inside Interior Design Services: space layout planning, furniture layouts with 3D renderings, then drawing and production coordination with on-site guidance. Where you supply your own drawings, we mark them up and return a shop-drawing set for your confirmation before cutting anything.
3. Verify the site, then re-verify it
Site requirements are not a single measurement. For each wardrobe position record, at minimum:
| What to check | Why it matters for a solid wood wardrobe |
|---|---|
| Height at three points (left, centre, right) | Ceiling levels vary; the carcass is built to the smallest clear height unless packing is designed in. |
| Width at top, middle and bottom | Out-of-square openings are common; filler widths are set from these figures. |
| Depth at both ends | Bowing walls reduce usable depth and affect door alignment. |
| Plumb and square of the back wall | Determines whether the unit is scribed, packed or built freestanding. |
| Floor finish level and threshold details | Sets the base detail and clearance under sliding doors. |
| Location of concealed services | Prevents fixing into pipes, conduits or underfloor heating runs. |
| Access route from lift, stair or entry | Decides whether the unit ships assembled or in knock-down sections. |
| Room humidity and heating pattern | Solid timber moves with the environment; the fitting detail should allow for it. |
Take these readings after wet trades, flooring and painting are complete, or at least after the final floor build-up is fixed on site. Re-measure if the programme slips, because a survey from an unfinished room is not a survey.
4. Match the finish to the room, not the sample photo
Walnut reads differently under warm bedside lighting and cool daylight from a north-facing window. Approve a physical finish board in the actual room before sign-off, alongside the ironmongery you intend to use. Then record the approved combination — species cut, stain or oil system, sheen level, handle model and hinge type — as one line item on the confirmed specification. If a matching finish is needed elsewhere in the same project, such as Oak Solid Wood Wardrobes in a second bedroom or cabinetry in the same corridor, request the boards together so the tones are compared side by side.
Our Custom & OEM Service covers bespoke finishes and textures, prototyping and material selection. For multi-unit work we recommend one prototype or first-article door be approved before the full run is produced.
5. Plan packaging and delivery around the opening size
A wardrobe that cannot reach the room cannot be installed. Confirm the tightest point on the route — stair width, lift door, corner turn, front gate — and design the packing around it. Long side panels and full-height doors are frequently the constraint, so decide early whether to deliver assembled, part-assembled or in knock-down sections with site assembly. For international projects this decision also affects container loading and freight; our Logistics & Door-to-Door Delivery team handles sea, air and rail freight, packaging and container loading, customs paperwork and shipment tracking, so the access route should be discussed before packing is fixed.
Agree the delivery window with the site programme as well. Built-in wardrobes belong after flooring, painting and ceiling work are complete, but before loose furniture and final dressing.
6. Install against the confirmed drawing, then close out with a snag list
At installation, three checks prevent most disputes: the unit is level and plumb in the opening as built; door gaps are even along the full height after the room has been used for a few days; and every drawer, hinge and slider is adjusted against the finished floor, not the subfloor. Where we support fitting on site, Installation & After-sales Support covers on-site installation, inspection and snags, plus spare parts and maintenance follow-up.
Close the package with a signed snag list held against the approved shop drawings. That document is what makes warranty claims and later spare-part orders straightforward, especially on projects with multiple identical wardrobes across several rooms.
A short pre-production sign-off sheet
- Elevations issued for every wardrobe position, with levels and datum stated.
- Site survey recorded after final floor build-up; measurements at multiple points.
- Carcass and door material, cut, finish and sheen approved on a physical board in situ.
- Ironmongery, interior fittings and soft-close specification confirmed as one line item.
- Delivery route measured; assembled or knock-down decision agreed.
- Installation sequence fixed against the site programme; snag list template agreed.