A bronze glass wardrobe rarely arrives on site as the first trade to work in a bedroom. It arrives near the end of a fit-out, when flooring, paint, lighting and joinery have already taken their slots — which is exactly why late delivery turns into a project-wide problem. Glass panels cannot be trimmed on site, made-to-measure casings cannot be resized with hand tools, and a wardrobe sitting in crates on a finished floor blocks everyone else. The coordination work that prevents this happens months earlier, at specification and production stage.

This guide walks through how buyers, contractors and interior firms sequence delivery and installation for made-to-measure bronze glass wardrobes, from the first site dimension to final handover.

Why Glass Fronts Change the Delivery Sequence

With timber or laminate door fronts, a small dimensional error can sometimes be absorbed on site — a scribe cut, an adjusted filler panel, a re-hung door. Tinted glass behaves differently. Panels are cut to size, edged and tinted in the factory; once produced, a bronze glass front is what it is. If the finished opening turns out shorter than the height the panels were built to, the fix is a replacement set of fronts and a second shipment.

That single fact drives every decision below:

  • Dimensions must be final before production starts. Site dimensions are taken from finished surfaces — completed screed, finished floor level, finished ceiling or cornice line — not from structural draw-ups.
  • Other trades must clear the zone. Painters, electricians, flooring installers and air-conditioning ductwork all need to be complete or at least fixed in position before a wardrobe carcass is assembled against that wall.
  • Access matters as much as size. Long panels and full-height casings must travel through doorways, lifts, stairwells and corridors that exist on the day of delivery, not on the day of the design sketch.

Step 1: Lock the Specification Before You Lock the Programme

The most common scheduling failure is a construction programme written against an unfinished wardrobe specification. Buyers confirm the door style late, then expect production and freight to compress into the gap.

Settle these items first, because each one changes lead time as well as price:

DecisionWhy it affects delivery and installation
Glass type and tint — bronze, clear, frosted, smoked or ribbedTinted and textured panels are made to order; switching tints after production is booked restarts the clock.
Door operation — hinged, sliding or aluminium-framedSliding systems need track and clearance zones set out in the slab or head rail; hinged units need door swing clearance against other fittings.
Framed or framelessAn aluminium-framed bronze glass wardrobe arrives as frame sections plus panels, which changes packing, handling and the on-site assembly sequence.
Interior layout — hanging, drawers, shelving, lightingInternal components are usually installed before the glass fronts go on, so they must be in the same crate group.
Consolidation with other joineryWardrobes ordered alongside built-in cabinetry, vanities or kitchen cabinets can ship together, which removes one delivery window and one set of site preparation.
Practical rule: fix the wardrobe specification at the same time you fix door and architrave schedules. Both are trade-dependent, both are made to measure, and a change to one usually moves the other.

Step 2: Take Dimensions from Finished Conditions

Made-to-measure wardrobes are dimensioned off completed surfaces. Before releasing drawings for production, confirm and record:

  • Finished floor level at the wardrobe line, including any underlay, screed or flooring build-up
  • Finished ceiling or cornice line, and whether the unit runs full height or stops below it
  • Wall plumb and square across the full run — record the deviation rather than assuming a straight wall
  • Position of skirting, architraves and any projection that the carcass must scribe around
  • Location of power points, switches, downlights, air diffusers and thermostat controls relative to the casings
  • Clearance for handles, drawer pull-out and door swing against the bed, ensuite door and built-in seats

For sliding configurations, add the track zone: an overlapping glass sliding door wardrobe needs headroom for the track and a clear wall return for the second panel to travel. Confirm this on the drawing, not in conversation.

Where the design includes corner returns, bulkheads or a dressing-room footprint, request a set-out drawing showing the unit against the architectural plan. SANTERSON's project workflow includes design consultation and space planning before production, so use that stage to catch clashes rather than discovering them at handover.

Step 3: Build the Wardrobes into the Construction Programme

Work backwards from practical completion. A made-to-measure glass wardrobe run typically passes through four gates, and each gate has a predecessor:

GateMust be complete before this happens
Final site dimensions released to factoryWet trades finished in the room; screed and floor build-up set; ceiling line fixed
Production releasedDrawings signed off by buyer or designer; glass tint, frame colour and hardware confirmed
Delivery bookedSite access route verified; storage area prepared; other deliveries sequenced around it
Installation crew on siteFlooring laid and protected; paint touch-up zone available; power and lighting installed for on-site testing of integrated cabinet lighting

Two sequencing details cause the most rework. First, if integrated lighting is specified inside the wardrobe, electricians need the cable provisions in the wall before the carcass goes up — not after. Second, if the wardrobe sits on a finished timber or engineered floor, plan protective boarding along the delivery route and the assembly area; glass panels and heavy casings damage floor finishes quickly.

Step 4: Plan Freight, Packaging and Site Access Together

For international projects, the logistics stage is where a wardrobe order becomes a physical set of crates with a delivery date. When ordering from a China-based manufacturer, confirm in writing:

  • Packaging specification. Glass fronts need glazing crates or vertical A-frames with edge protection; carcass panels need corner protection and moisture barriers for ocean transit. Ask what packaging standard applies and photograph the packing before it closes.
  • Container loading plan. Full-height panels are long items. They load differently from cabinets, and mixed loads shift in transit if not braced.
  • Incoterms and delivery point. Door-to-door arrangements move goods to site; port or warehouse terms leave a local leg for the buyer to arrange. Both are workable — they just need naming early so the site diary reflects reality.
  • Customs documentation. Commercial invoices, packing lists and certificates of origin should match the crate marks, so clearance does not stall while the installation crew waits.
  • Crate numbering against room schedule. Every crate labelled to the room and unit it belongs to turns a two-day unpack into a half-day one.

Then check the last 30 metres. Measure the narrowest point on the route from vehicle to bedroom: gate, lift car, stair turn, corridor corner, bedroom door. A full-height glass panel that clears a lift car with only a few millimetres to spare is workable; one that has to be craned through a window is a different cost and a different programme.

Where the project includes several made-to-measure items — wardrobes, vanities, kitchen cabinets, wall panelling — consolidating them into one shipment reduces delivery windows and gives you a single logistics coordinator to track. That is how SANTERSON handles villa and hospitality fit-outs where multiple joinery packages come from one factory.

Step 5: Prepare the Room Before the Crew Arrives

Installation day should be assembly, not discovery. Hand the crew a prepared space:

  • Room swept, dry and finished — no wet trades scheduled in that room for the following days
  • Floor protection laid from the delivery entry point to the wardrobe line
  • A clear staging area roughly the footprint of the run, for unpacking and laying out components
  • Power available at the room for saws, drills and testing of internal lighting
  • Level and plumb recorded at the wall line, with packing material on site where walls deviate
  • Any site-supplied fixings, anchors or structural blocking installed as agreed on the drawing

Confirm who supplies what before the crew mobilises. Some installations assume the builder provides wall blocking for heavy casings, floor protection and post-installation touch-up paint. Getting that in writing avoids an unfinished handover.

Step 6: Sequence the Installation Itself

A typical order of work for a made-to-measure glass wardrobe:

  • 1. Inventory and inspect on arrival. Open glazing crates in daylight, check each panel for edge chips and tint consistency, and photograph any damage the same day while the freight claim window is open.
  • 2. Dry-fit carcasses. Stand casings in position, check level across the run and confirm the scribe allowance at ceiling and floor.
  • 3. Fix and align the carcass block. Fix to wall and floor per the fixing detail, pack out deviations, then check the whole run is square before anything else goes on.
  • 4. Install internals. Shelves, drawers, hanging rails and any integrated lighting, with wiring tested before fronts close it in.
  • 5. Fit frames and tracks. For framed or sliding configurations, fit head and bottom tracks and confirm door travel is smooth and unobstructed.
  • 6. Fit glass fronts last. Panels go on at the end, after heavy work in the room is done, then hinges, handles and soft-close hardware are adjusted.
  • 7. Adjust and clean. Door alignment, gap consistency across the run, sliding action, and a final wipe-down of glass with the correct cleaner for tinted panels.

Keep spare panels where a project has a long run of matching fronts. For multi-unit developments, ordering one spare set of fronts to the same tint and batch avoids a colour mismatch if a panel is broken during the works.

Step 7: Hand Over with a Snag List, Not a Handshake

Close out by walking the run against a written inspection agreed with the client or builder before the crew mobilises. Cover:

  • Glass panels free of chips, scratches and tint variation across the run
  • Door gaps consistent from top to bottom; no rubbing on adjacent panels
  • Sliding doors running quietly through full travel with no lift-off from track
  • Drawers and soft-close mechanisms operating smoothly under load
  • Integrated lighting switched, dimmed and tested at the intended control point
  • Carcass scribed neatly to floor, ceiling and side walls; silicone and trim finished
  • Hardware spares, keys and care instructions handed to the client or facilities manager

Record the model, finish code and glass tint alongside the room schedule. Six months later, when a replacement panel or matching piece of joinery is needed, that record makes the order straightforward rather than a colour-matching exercise.

Common Failure Points Worth Designing Out

FailureWhere it actually originates
Panels do not fit the openingDimensions taken before finished floor and ceiling levels were set
Delivery cannot reach the roomAccess route never measured; lift car or stair turn assumed adequate
Glass damaged on siteFronts fitted early, then other trades worked in the room around them
Wardrobe blocks flooring handoverTwo trades booked into the same room in the wrong order
Internal lighting cannot be connectedCable provisions omitted from first-fix electrical
Tint mismatch between batchesOrder split across production runs without a single confirmed tint reference

How a Single-Supplier Fit-Out Simplifies This

When wardrobes, vanities, kitchen cabinetry and wall panelling come from separate factories, each carries its own production clock, packaging standard, freight forwarder and installation crew. Coordination becomes a matrix of dates that nobody owns.

Sourcing those items through one built-in furniture and fit-out supplier collapses that matrix: one set of shop drawings, one production schedule, one consolidated shipment, one point of contact for snags. SANTERSON operates as a China-based manufacturer and one-stop supplier covering design consultation, custom and OEM production, freight and door-to-door delivery, installation support and after-sales service — the sequence described above is how that workflow runs on villa and hospitality projects in markets including Australia.

For buyers, the practical benefit is narrow but real: fewer interfaces to manage means fewer places for a made-to-measure item to go wrong.

Checklist: Delivery and Installation Readiness

  • Glass tint, frame finish, door operation and internal layout confirmed in writing
  • Shop drawings signed off against finished floor and ceiling levels
  • Wall deviations recorded; scribe and packing allowances shown on drawing
  • Electrical first-fix provisions for internal lighting installed
  • Packaging standard for glass agreed and confirmed before crating
  • Incoterms, delivery point and customs documents agreed
  • Last-30-metres access route measured and cleared
  • Room prepared: dry, finished, protected floor, staging area, power on site
  • Builder-supplied items (blocking, protection, touch-up paint) assigned in writing
  • Snag list format agreed before the crew mobilises

Planning a wardrobe package for a villa or hotel project?

Send us the room schedule and target handover date. We will confirm the specification options, production window and delivery sequence for bronze glass wardrobes alongside your other built-in joinery.

Contact SANTERSON — Phone / WhatsApp: +86-13928214007 (PHILLIP) · Email: santerson@qq.com