A materials schedule that holds together is the difference between a fit-out that runs smoothly and one that stalls on substitutions. When doors are specified room by room, late, they arrive as an afterthought: wrong pocket depths, mismatched frames, finishes that no longer match the joinery. This guide shows how Santerson Glass Pocket Doors can be placed inside a whole-project materials schedule from the start, so the opening, the frame, the glass and the finish are all locked at the same time as the cabinetry, wall panels and flooring they sit next to.
Why pocket doors break schedules when they are scheduled late
Pocket doors are a built-in condition, not a loose item. The leaf slides into a cavity inside the wall, which means the wall has to be built around the door rather than the other way round. Once the framing, plasterboard and finishes are complete, changing a pocket door specification means opening up a finished wall.
Three things usually go wrong when doors are added late to a schedule:
- The structural opening is already framed to the wrong width or depth for the leaf and track that were finally chosen.
- The frame and architrave finish were picked after the wall paint and joinery veneer, so the tones clash under site lighting.
- Glass type, opacity and hardware were never reviewed with the bathroom and wardrobe specification, so sight lines and privacy expectations do not match what was sold.
Scheduling them with the other fixed elements removes all three problems at once.
What Santerson Glass Pocket Doors cover
The product page describes made-to-measure glass pocket doors for residential projects, where finish, layout and dimensions are specified for each space. The configuration lists made-to-measure sizing together with material and finish options, so each opening can be set out individually instead of forcing every room onto one standard size.
That per-opening approach is what makes the item schedule-friendly. Because the doors are made to the dimensions you submit rather than selected from a fixed size grid, the same drawing set that drives your wardrobes and wall panelling can drive the doors too. Exact glass specification, frame material, finish selection and pocket build-up should be confirmed for each project at quotation stage.
Where these doors earn their place in a villa or apartment plan
Glass pocket doors solve two problems at once: they remove the swing radius a hinged leaf needs, and they let light cross a plan that would otherwise be cut into dark corridors. In practice they work best in these situations:
- Study, media room or home office. The room can be closed for calls and opened to the living area afterwards, with no door leaf eating floor space when open.
- Ensuite and bathroom entries. A pocket leaf keeps a compact bathroom layout usable. Glass choice then decides how much light passes and how much privacy the room keeps.
- Pantry, laundry and utility stores. Opening stays clear when the doors are retracted, so access to shelves and appliances is not blocked by a swing.
- Dressing and walk-in robe entries. A glass leaf keeps daylight moving through the storage zone while the pocket keeps the room wall usable for cabinetry.
Reading the product line next to the rest of the door range
A materials schedule is easier to price and coordinate when similar items sit with one supplier. The same pocket-door grouping on the site also lists Classic Pocket Doors and Santerson Wood Veneer Pocket Doors. That gives a project a consistent pocket build-up and frame detail across rooms where glass is wanted and rooms where a solid or veneered leaf fits the joinery better, which reduces the number of different wall details your builder has to resolve.
Where an opening needs glazing but not a retracting leaf, Glass Sliding Doors are the alternative to compare. The decision is usually about wall build-up and how much clear opening you need, so it is worth settling both options in the same review rather than at separate times.
Building the schedule line by line
Treat each door as a row with the same fields as every other fixed item. A workable set of columns looks like this:
- Door tag and room. One tag per opening, tied to the room number used on the drawings.
- Clear opening width and height. Taken from the setting-out drawing, not from a nominal module size.
- Pocket depth and wall build-up. Confirmed against the framing method your builder is using for that wall.
- Leaf material, glass type and finish. Matched to the adjacent wardrobe fronts, panelling and paint schedule.
- Track, hardware and threshold detail. Including floor finish levels at the opening.
- Approval stage. Which drawing or sample sign-off releases production.
Fill those columns before the framing package is issued. Anything left blank at that point becomes a variation later.
Coordinating the doors with the rest of the fixed elements
A pocket door rarely stands alone on a wall. It sits between built-in storage, panelling and floor transitions, so those items should be reviewed in one pass. Wall Panel Systems and Custom Built-in Kitchen Cabinets are specified on the same setting-out drawings, which means one coordinated review can settle frame reveals, panel edges and floor levels together.
This is where a single supplier for several fixed categories pays for itself. One-stop Furniture and Building Materials Supplier arrangements mean the drawings, samples and production files for doors, cabinetry and surfaces come from one coordination cycle rather than three, so a change to a finish in one package can be checked against the others before it is committed.
Where custom and OEM support fits
Made-to-measure doors often need matching frames, architraves or reveals that are not stocked items. The Custom & OEM Service covers custom furniture design and prototyping, bespoke material finishes and textures, and OEM manufacturing with flexible minimum order quantities. For a project this means trims and matching joinery pieces can be produced to the same finish schedule as the doors instead of being sourced off-the-shelf and stained on site.
Confirm the specific finish, glass and hardware selections available for your project at quotation stage; the site describes these options generally rather than as a fixed list.
Production, delivery and installation sequencing
Glass pocket doors have to land on site after the framing and pocket build-up are complete but before floor finishes and wall decorations are finalised at the opening. That window is short, so lead time and packaging matter as much as the product itself.
The Logistics & Door-to-Door Delivery service covers global freight forwarding by sea, air and rail, customs paperwork, packaging and container loading, shipment tracking and door-to-door delivery. Import terms, duties, transit time and delivery scope should be agreed for each project individually.
The Installation & After-sales Support service lists on-site installation, inspection and snagging, warranty coverage, spare parts and replacement, and ongoing maintenance. Agree in writing which of these apply to your site, who carries the wall build-up work, and how snags at glazed openings are recorded at handover.
A practical checklist before you release production
- Every opening has a door tag that appears on both the door schedule and the setting-out drawings.
- Pocket depth, framing method and wall build-up are confirmed for each wall, not assumed from one detail.
- Glass type and opacity are approved against the privacy requirement of each room.
- Frame and hardware finishes are checked against the joinery, panelling and paint schedule under site lighting conditions.
- Floor finish levels at each threshold are fixed before the track detail is released.
- Delivery window is agreed against the framing programme, with storage available on site.
- Inspection and snag responsibilities at glazed openings are named in the handover documentation.
Bringing it together
Glass pocket doors fail on schedule, not on quality. Put them into the materials schedule with the same fields as your cabinetry and surfaces, settle the pocket build-up before framing is issued, and review finishes for every opening in one pass alongside the joinery they sit next to. Scheduling Santerson Glass Pocket Doors through the same coordination cycle as the rest of the fixed elements keeps the wall detail, the finish and the delivery date aligned.