An arched French door pair is one of the few openings in a villa or hotel scheme that carries both the daylight plan and the style statement of the room. Because it sits at the junction of structure, joinery and glazing, approval usually stalls on a handful of practical questions rather than on aesthetics. The list below follows the order our project teams work through when a client brings us Santerson Arched French Doors for sign-off, so that what gets approved on paper is what can actually be built, delivered and hung on site.

1. The opening itself: spring line, clear width and reveal depth

Arched doors are made to the opening, not the other way round, so the first confirmation is a survey of the finished opening rather than the structural one. Before drawings are released, project teams should confirm:

  • the height at which the arch begins to curve — the spring line — measured from the finished floor level, not the slab;
  • clear opening width and height after plaster, skirting, flooring and any wall finishes are installed;
  • wall build-up and reveal depth, which decides frame profile and how the arch head is closed off internally;
  • floor threshold level and the door's clearance to the finished floor on both sides of the opening.

These figures drive everything downstream: frame section, glass sizes, hardware positions and how the arch relates to ceiling lines. When a survey cannot yet be trusted — for example in an early-stage villa where partitions are still being set out — we produce the doors against agreed dimensions and re-confirm them before production starts.

2. Operation: which leaves move, and how they meet the arch

A pair of arched French doors can be detailed in several ways, and the choice changes both cost and the look of the elevation. Confirm before approval whether both leaves hinge and open, or one leaf is fixed to hold the glazed pattern; whether the meeting stile sits centred or off-centre; and how the transom arc is divided across the leaves so the glazing bars read as a continuous curve when the doors are closed. Active leaf width also has practical limits — a wide active leaf needs hardware rated for its weight, and it changes the swing path into the room.

Also settle how the doors relate to the floor finish: threshold type, whether a sill is required at all on internal applications, and the swing clearance against skirting, drapery recesses and any adjacent joinery. These are small drawings but expensive to change once frames have been machined.

3. Material and finish: matching doors to surrounding joinery

Our Windows and Doors range is specified per project, with material and finish options rather than a fixed catalogue colour. For arched doors that usually means agreeing the substrate, the surface treatment and — if the doors face other timber work — how closely the grain and tone will be matched to the cabinetry and panelling in the same space. Colour chips and physical samples are worth requesting early, because a warm wood tone that reads well on a small sample can look very different across a full-height glazed leaf.

Where the doors sit inside a wider joinery package, we produce them alongside it so frames, architraves and reveals share one material palette and one production run. If you are also specifying Santerson Modern Slim Frame French Doors elsewhere in the same building, confirm at approval stage that the two profiles are intended to differ, and record which rooms take which detail.

Practical note: arched heads cannot be corrected on site the way a square frame can. Any dimension or finish changed after production release normally means remaking the leaf, so approval should wait until the survey, the swing layout and the finish sample are all settled.

4. Glazing pattern and glass build

The curve is what makes this door type distinctive, so it deserves its own line on the drawing. Confirm the number of glazing bars in the arch, their spacing, whether the bars are structural or decorative, and how the curved top light is framed. Glass build follows from that layout: thickness, whether the panes are clear or textured, and how each piece is cut to follow the arc. Curved-top panes and shaped bars add lead time compared with a straight rectangular leaf, which matters when doors must arrive before a plastering or flooring sequence.

5. Hardware: handles, hinges and locking

Hardware on arched doors is specified, not assumed. Agree handle type and height — the curve often pushes handles away from a standard centre line — hinge grade against leaf weight, and whether the pair uses a keeps shutter, an astragal bolt or a single-point lock. Finish should be written down explicitly so it can be matched to ironmongery elsewhere in the project rather than substituted later.

6. Scope of supply: frames, architraves and coordination with others

Be explicit about what is included in the order. Frames and leaves travel together as standard; architraves, extension reveals, sills, glass, ironmongery and any arch-head infill should be listed item by item on the approval sheet. Then confirm who prepares the opening: setting-out, the lintel or head support above an arched opening, and making good around the frame are usually site trades, and a gap in that handover is the most common cause of delay at installation.

7. Logistics sequence and installation window

Doors are heavy, glazed and easily damaged, so they should not be the first items shipped. Confirm that wet trades around the opening are complete before dispatch, agree a delivery window that matches the site's installation programme, and confirm packaging and container loading plan for glazed leaves. Under our Turnkey Interior Project Solutions, doors normally arrive with the joinery package so one crew can hang the leaves, fit architraves and adjust the arch head in a single visit, followed by an inspection against the approved drawings before handover.

Approval checklist — sign off these eight items

  • Surveyed finished-opening width, height, spring line and reveal depth, taken after floor and wall finishes
  • Leaf layout: active and fixed leaves, meeting stile position, swing direction and clearance
  • Frame material, surface treatment and approved finish sample
  • Arch glazing pattern with bar spacing and glass build recorded on the drawing
  • Handle, hinge and lock specification with finishes named
  • Itemised scope of supply, including architraves, reveals and ironmongery
  • Site responsibilities for opening preparation, head support and making good
  • Delivery window tied to the installation programme, not to production completion

When those eight points are documented, an arched French door stops being a risky feature item and becomes a routine line on the schedule. Send us the opening drawings and the surrounding joinery specification, and we will return shop drawings for your review before anything goes into production.