Open modular shelves look simple on a drawing: a run of verticals, a stack of horizontals, some display niches. On site they fail in two predictable ways — the quantity is wrong, or the shelving arrives as pieces that do not line up with the joinery, lighting and wall finishes around it. Both problems are decided before production starts, in the take-off sheet and in the coordination notes attached to it. Below is how we build both for villa and apartment projects, using our Open Modular Shelves as the reference product.
Start from elevations, not floor plans
A floor plan tells you where a wall is. It does not tell you what sits in front of it. For every shelving run, request or produce a dimensioned elevation of each wall face, and mark on it the fixed conditions that will interrupt the module grid:
- Switch plates, sockets, thermostat panels and data points, with their heights from the finished floor.
- Bedside pendants, wall sconces and any integrated lighting positions that have to fall inside a bay rather than across a vertical.
- Door openings, curtain lines and the travel of any glass sliding door that closes over the shelving.
- Skirting, cornice and floor build-up — a unit measured against a structural slab will not fit once the finish is laid.
- Adjacent cabinetry such as wardrobe carcasses, kitchen cabinets and vanities, whose reveal or shadow gap has to match the shelving face.
Our Open Modular Shelves are made to measure, with material and finish options and a layout set per project, so the marked-up elevation is what becomes the order. Send elevations rather than a room schedule; a room schedule cannot resolve a 40 mm conflict.
Break the run into modules before you count it
Counting linear metres is not a quantity. Count modules, and count them by type:
- Standard bays. The repeating unit that sets the grid. Fix one bay width for the whole run and keep it; alternating widths read as an error on site.
- Closure panels. End trims, scribes and infill to walls that are out of plumb. These let a fixed module grid survive a building that is not square.
- Display niches. Recessed or framed openings for objects, often lit. List them separately so the niche depth and its lighting driver are ordered together — the same detail used in open display niches within storage walls.
- Closed elements. Drawers, doors and closed boxes inside the same grid. Where a run has to hold clutter as well as display, mixed open and closed systems keep one module language across both.
- Tall variations. A waist-height run in a study, a floating modular band above a desk and a floor to ceiling system in a hallway are three different fixing details even when the bay width is identical.
For multi-unit work, take off from a typical detail first. Get the repeating bedroom or study shelving type approved once, then multiply by unit count and only then handle exceptions — the apartments with different wall lengths, the duplex stairwell. That order keeps one approval cycle instead of thirty.
Quantities that survive site conditions
- Re-measure after the finishes. Final dimensions come from the completed wall face and floor level, not from architectural drawings. For made-to-measure shelving this re-measure is a production gate, not a courtesy.
- Order accessories with the frame. Brackets, rails, shelf pins, trims and other shelving accessories sit on separate take-off lines and then arrive in a second shipment. Put them on the same purchase line as the modules.
- Hold a small spares allowance. Field-cut end panels and chipped display shelves get replaced during installation. A short run of spare horizontals plus one closure set costs far less than an order placed after the site has been cleared.
Coordination: four interfaces that decide the result
Lighting. An LED strip inside a shelf bay needs a driver location, a cable route and service access before the carcass is closed. Confirm the electrical specification and compatibility of the chosen configuration with your electrician at the same meeting where the joinery is signed off — not when the shelving is already on the truck.
Wall and ceiling finishes. Where shelving meets a clad wall, decide which element trims which. Our wall panel systems and open shelving can be coordinated in one drawing, so profiles, reveals and shadow gaps match instead of being reconciled with sealant on site.
Storage walls and wardrobes. Open shelving that stops against a wardrobe door line has to share the same plane. Set the reveal width once across both product families and record it in one detail.
Fixing substrate. Floating and floor-to-ceiling runs need backing that carries the load at the real site condition. Establish whether the wall is block, stud or clad, and settle who supplies the substrate — this is a common reason a shelving order gets reopened.
Before you release a shelving package for production, check four things: the module grid is fixed on every elevation, accessories are on the same purchase line, the electrical specification is confirmed by name, and the substrate supplier is named. If any of those is blank, the quantity is not finished.
How we run it as one package
Because shelving, joinery, panelling and finishes can be ordered from one furniture and building materials manufacturer, a project can be specified through a single coordination loop: design consultation and space planning, material selection and product specification, manufacturing with quality control, then site coordination and installation. Our published project cases include villa work in Willoughby, Perth, North Turramurra, Melbourne and Sydney; on projects of that type one set of module dimensions is shared between shelving, cabinetry and wall finishes instead of three trades each guessing the gap.
If you are assembling a take-off for an open modular shelving package, send us the elevations, the module grid you want fixed and the interface conditions above. We will return a module-by-module breakdown, the accessory list and the finish schedule for your confirmation before anything enters production.