Wardrobes rarely decide a project on their own. They become a problem when they arrive late, out of sequence with the floors and wall finishes they sit against, or specified to dimensions that no longer match the completed shell. Wooden sliding door wardrobes are one of the more schedule-sensitive items in a villa or apartment fit-out, because their panels travel across an opening that has to be square, level and finished before hardware can be adjusted. This guide shows how to place them inside a whole-project materials schedule rather than treating them as a late joinery afterthought.
Why the wardrobe belongs in the master schedule, not a trade sub-list
A made-to-measure sliding wardrobe is fixed to the structure. Its tracks, panel heights and reveal against the ceiling all reference finished floor levels and finished wall faces. When the item sits only on a joinery contractor's list, three things tend to go wrong at once: the flooring is laid after the opening was measured, the wall finish changes thickness, and the wardrobe delivery date is set without checking when the room becomes dust-free.
Putting the wardrobes into the same schedule as engineered wood flooring, wall panel systems and bathroom fixtures gives you one document where dependencies are visible. That is the practical difference between a wardrobe that installs in a day and one that sits in a corridor for three weeks while someone resolves a level discrepancy.
Step 1: Group wardrobes with the other built-in elements by room
Schedule by room first, then by trade. For each bedroom, list every element that touches the same openings and finishes:
- Sliding door wardrobe, including panel material, finish and door layout
- Flooring type and thickness at the wardrobe line, plus any transition detail
- Wall finishes on both side returns and above the head of the opening
- Ceiling set-down or cornice that the top track may pass behind
- Lighting and switch positions that fall within or beside the opening
- Adjacent joinery such as custom built-in kitchen cabinets in open-plan layouts, which share the same finish palette
Grouping this way exposes clashes while drawings are still cheap to change. A track that needs a structural packer, or a cornice that has to be set down before installation, is a line item on a schedule at that stage and an unplanned site variation later.
Step 2: Write specification fields you can actually check off
Vague wardrobe lines cause the most rework. Each line in the schedule should carry fields that a site manager can verify on delivery:
| Schedule field | What to record |
|---|---|
| Opening reference | Room code, wall line and drawing number for the opening the unit fits |
| Finished dimensions | Width, height and depth measured to finished surfaces, with the measurement date noted |
| Door system | Sliding panel count, overlap, track type and whether the track is surface or recess mounted |
| Panel material and finish | Board substrate, surface finish and colour reference, matched to the finish schedule |
| Interior layout | Hanging zones, shelves, drawers and any integrated lighting |
| Interface conditions | Floor covering at the track line, skirting treatment, ceiling reveal, wall return thickness |
| Sequencing note | Which finishes must be complete before installation is allowed on site |
| Approval status | Shop drawing approved, production released, shipped, received, installed, inspected |
SANTERSON's sliding door wardrobe range is specified per project rather than ordered from a fixed size grid: sizing is made to measure, material and finish options are selected for the job, and the interior layout is tailored to the space. The same approach applies across built-in furniture, so a project can carry one finish language from bedroom storage through to kitchen and media walls. Confirm dimensions and selected specifications for each project before production is released.
Step 3: Set the measurement gate, then protect it
Made-to-measure joinery only works if the measurement happens after the conditions it depends on are fixed. Before releasing wardrobe dimensions for production, require confirmation that:
- Flooring in the room is laid, or its build-up thickness is documented and locked
- Wall finishes to the wardrobe line are complete, including any wood veneer panels that add thickness at the returns
- Ceiling set-downs, cornices and any recessed track pockets are formed to drawing
- Levels across the opening have been checked and recorded, not assumed
- Services in the wall and floor are located, so fixings do not cut into them
Record that gate as a dated milestone in the schedule. If any of those conditions move afterwards, the wardrobe line is re-measured or the variation is raised immediately, instead of being discovered by the fitter on the day.
Step 4: Sequence delivery around the room's other finishes
Wardrobes are bulky, and panels marked or swollen by site moisture are a common claim. In the schedule, place wardrobe delivery after wet trades have dried and after flooring is laid and protected, but before loose furniture arrives so that panels can be manoeuvred into the room without blocking access. Where a project sources furniture logistics and door-to-door delivery from the same supplier as joinery, flooring and fixtures, consolidation is usually possible: fewer consignments, one packing list to reconcile, and one point of contact when a line item needs re-ordering.
Add a receiving step that checks each consignment against the schedule line — room code, panel count, finish reference, hardware set — while packaging is still on site. A shortage found at receipt costs days; a shortage found after the fitter opens the crate costs weeks.
Step 5: Make installation and snagging part of the same line item
Close each wardrobe line with a defined handover rather than an install date. The items worth inspecting are quick to check and cheap to fix while the room is still open:
- Panels glide freely across the full opening, with no binding at the track joints
- Panel reveal is consistent top to bottom and between adjacent panels
- Track fixings secure, with no movement when a panel is pushed hard into the stop
- Finish intact on visible faces, edges protected, no site damage to accept or reject
- Doors align with skirting, architraves and any adjacent panelling
- Interior layout matches the approved shop drawing
Where installation is supported through installation and after-sales support, agree in advance which party provides the fitter, who signs off the snag list, and how replacement panels or hardware are ordered. Confirm the actual scope for your project rather than assuming a standard arrangement.
Step 6: Keep one schedule across the whole fit-out
The real efficiency gain is not in the wardrobe itself. It is that the same document governs wardrobes, cabinetry, flooring, wall finishes, lighting and sanitary fixtures, so a change in one room shows up as an impact on the others. Coordinating that scope with a one-stop furniture and building materials supplier removes the reconciliation work between multiple vendors' order confirmations, which is where most fit-out programmes quietly lose time.
For projects in Australia, SANTERSON's turnkey solutions cover villa, hospitality and office work, with project references including villas in Sydney, Melbourne, Willoughby, North Turramurra and Perth. Scope, dates and local requirements for any specific project should be confirmed directly with the project team.