Open display units rarely cause problems at quotation stage. They cause problems later, when the joinery arrives on site and nobody has agreed what it will sit against, how deep it is allowed to be, or who supplies the lighting inside it. If you are specifying Santerson open display units for a villa, apartment or hospitality fit-out, the quality of your procurement brief decides whether the units read as built-in architecture or as furniture that arrived by accident.
Because these units are made to measure, the brief below covers the decisions a buyer or project manager needs to lock down before a quotation is requested. Each item maps to something you can write into a schedule today.
Start with the wall, not the unit
Open display units are almost never standalone. In most residential and hospitality projects they sit inside a wider wall composition — joinery panels, closed storage, media units, feature shelving. Before you specify the open section, record what it connects to.
- Which adjacent systems share the wall: closed cabinets, media walls, paneling or a plain finished wall.
- Whether the unit is recessed into a niche, flush with surrounding panels, or proud of the wall face.
- The finished floor and ceiling levels at that point in the drawings, including any skirting, cornice or shadow gap you expect the unit to return around.
- Whether the surrounding finishes are also being ordered from the same package, so material and colour batches match.
If the open display is meant to read as one composition with the rest of the wall, say so in the brief. A schedule that lists each item separately invites separate deliveries, separate fixings and visible joins.
Fix the dimensions you control, and flag the ones you do not
Made-to-measure sizing means the unit follows your drawings, but it also means errors travel with it. For each unit in the schedule, give:
| Dimension | What to state |
| Overall width and height | Finished dimensions from the setting-out drawing, with tolerance expectations where other trades work to the same line. |
| Depth | Clear depth required for what will be displayed, plus how the unit resolves against the wall build-up. |
| Bay and shelf spacing | Which bays are fixed and which need adjustable shelving; note any bay sized around a specific object or appliance. |
| Floor-to-unit interface | Plinth, recessed base, or floor-fixed — this affects both cleaning access and how the unit survives site traffic. |
Where a dimension depends on another trade's work — a plaster return, a stone reveal, a raised floor — mark it as pending rather than guessing. Confirming dimensions against site conditions before production is normal practice; confirming them after production is a variation.
Specify the finish system by name
Finish and material options are part of the configuration, so the brief should name what you want rather than describe a mood. Practical wording includes:
- The substrate and surface treatment you expect (veneer, lacquer, laminate or other finish families in the range), with the reference sample you approved.
- Whether shelf backs are the same material as the carcass, a contrast material, or a feature surface such as stone.
- Edge treatment on visible shelf fronts and returns — square, eased or bull-nosed matters in high-traffic and child-facing settings.
- Sheen level. A high-gloss display shelf shows fingerprints and light banding in a lobby; a matte surface behaves differently under the same lighting.
Ask for a physical finish sample of the exact combination you specified, not a generic colour card. Veneer figure and lacquer sheen are hard to judge from a printed swatch, and approvals made on paper are the most common source of late disputes.
Decide early who owns lighting and services
Open display shelving usually carries light. Either the unit is supplied with integrated lighting, or your electrical contractor runs cable and fittings separately. Both approaches work; the failure mode is neither party taking ownership.
- State whether recessed or surface-mounted lighting is to be built into the shelves, and where drivers, transformers and switches will sit.
- Agree who supplies the light source, the control gear and the wiring to the unit — manufacturer, main contractor or your lighting designer.
- Record cable routes and access points on the setting-out drawings before first fix.
- If a lit display cabinet appears elsewhere in the same package, keep the fitting type and colour temperature consistent across both.
For rooms where shelving is one part of a larger built-in composition, the same brief should also cover closed elements in the storage units range, so the whole wall is quoted and delivered as one package.
Say what will be displayed
This sounds obvious and is nearly always left out. Shelf depth, shelf span and fixing method all depend on the load. A display of books behaves differently from ceramics, sculpture or a decanter collection, and a hospitality display that guests can touch needs different edge detailing from one behind a barrier.
Include in the brief: the category of items to be displayed, whether items are project-supplied or fixed by others, and whether any single object needs an unusual bay size, load path or lighting angle. If a specific piece must be shown on site before sign-off, request that bay as part of the sample stage.
Cover delivery, handling and installation in the same document
Built-in joinery is where procurement documents are usually thinnest, and it is where cost overruns appear. Your brief should state:
- Delivery address, access constraints, lift or stair dimensions, and whether units arrive assembled or flat-packed for site assembly.
- Storage arrangements on site — joinery left in a damp or trafficked area is the most avoidable damage there is.
- Which party carries out installation, and the sequence relative to painting, flooring and final cleaning.
- The snag and rectification route for anything damaged after handover, with named contacts on both sides.
SANTERSON's project services cover design coordination, custom/OEM production, logistics and door-to-door delivery, installation and after-sales support, so a single brief can travel through the whole chain instead of being rewritten at each stage. That is the practical argument for writing one procurement document rather than three.
A short pre-quotation checklist
- Setting-out drawings with finished levels, wall interfaces and pending dimensions marked.
- Named finish system with approved physical sample reference.
- Bay layout, shelf adjustability and load description for each unit.
- Lighting scope with a named owner for cable, fittings and control gear.
- Delivery access, storage, installation sequence and snag route.