A storage and display wall looks like a small, low-stakes item on a project schedule. It is one joinery line among dozens of finishes, and it rarely gets the same scrutiny as kitchen cabinetry or bathroom fit-out. That is exactly where problems start. The Santerson Storage & Display Combo sits in the Media & TV Walls collection and is a configurable built-in system: finish, layout and dimensions are set per project rather than chosen from a fixed catalogue size. Every variable you leave open at order stage becomes a variation, a delay or a snag at handover.
The risks below are the ones procurement teams should close out before a purchase order is raised, not after the drawings have gone to production.
1. Treating a configurable system as a standard product
Configurable systems are quoted against a specification, not a part number. Two projects can order the same named item and receive completely different assemblies, because the layout, dimensions and finish were specified differently each time. If your requisition simply names the product without an accompanying dimension schedule, storage configuration and finish reference, the supplier is quoting on assumptions.
- Attach a dimensioned elevation to the requisition, not just a product name and quantity.
- State which sections are closed storage, which are open display, and where services or equipment sit behind panels.
- Name the finish by reference, with the substrate and edge treatment noted in writing.
2. Ordering before the site condition is confirmed
Built-in wall systems depend on the wall they are fixed to. Floor-to-floor height, floor level, skirting, plaster tolerance and the position of power and data all change what can be manufactured. A unit measured off a drawing set rather than a completed site will usually need field adjustment.
- Take site-verified dimensions after wet trades and floor finishes are complete, or write the tolerance into the order explicitly.
- Confirm what the wall substrate is and whether it can carry the load of the assembled unit.
- Record outlet, switch and data positions on the elevation before production release.
Rule of thumb: if a supplier can produce the item without asking you a single question about your site, the specification is not detailed enough to build from.
3. Assuming finishes match across trades
Media walls rarely stand alone. They sit next to wardrobes, sideboards, shelving and paneling that may come from different line items or different suppliers. Veneer tone, lacquer sheen and hardware finish drift between batches and between manufacturers, and the mismatch only becomes visible once installed under site lighting.
- Order finish samples for the exact materials, not catalogue images, and keep signed-off physical samples on site.
- Where adjacent joinery comes from the same factory, request it under one production batch so veneer and lacquer are drawn from the same run.
- Check adjoining items in the range before specifying — full height media walls, floating TV units and integrated TV panels sit in the same collection, so aligning them early avoids duplicated framing.
4. Splitting one wall across several suppliers
When the carcass, doors, lighting and panels come from separate vendors, no single party owns the interface gap. That is where cost leaks: duplicated framing, mismatched reveal depths, and site disputes over who carries the correction.
- Keep integrated cabinet lighting and panel systems on the same order wherever possible, so wiring routes are resolved in design rather than on site.
- If you do split the scope, define the interface in writing: who supplies infill panels, who makes good around services, who signs off the final alignment.
- Confirm which party is responsible for protection of installed units until practical completion.
5. Freight and packaging on oversized built-ins
Full-height panels travel badly and are easily damaged in transit. For projects sourced from overseas factories — SANTERSON is a China-based furniture and building materials manufacturer supplying villa, hospitality and office projects internationally — the packaging specification and container loading plan matter as much as the manufacturing date.
- Ask how oversized panels are crated, whether they are flat-packed or assembled, and what replacement terms apply to transit damage.
- Sequence the delivery so the wall system arrives after the room is enclosed, sealed and dry, not with the first container.
- Build a realistic re-manufacture contingency into the programme for any panel that arrives damaged.
6. What to have signed off before you raise the order
| Item to close out | Evidence required before production release |
|---|---|
| Dimensions | Site-verified elevation signed by the site lead, with tolerance stated |
| Storage configuration | Shelf, drawer and closed-section layout confirmed against the client brief |
| Finish | Physical sample approved and retained; batch reference recorded |
| Services | Power, data and lighting routes shown on the drawing and agreed with the electrical contractor |
| Scope boundary | Written split between supplier, builder and any second joinery vendor |
| Delivery window | Agreed delivery sequence plus damage and replacement terms |
| Handover | Inspection and snag process agreed, with named parties on both sides |
Where a single supplier reduces the exposure
The clearest way to control these risks is to consolidate the wall system with the joinery around it. A custom and OEM service covers bespoke dimensions, finishes and textures, which removes most of the guesswork from a configurable item like the Storage & Display Combo. Pairing that with coordinated logistics and on-site installation keeps responsibility in one place from drawing to handover.
For projects already running several interior packages, this also means fewer separate drawings to reconcile — media walls, wardrobes and paneling can be detailed against one set of levels and one finish schedule.
The practical next step
Send the elevation, the room's completed dimensions and your preferred finish reference with the enquiry, and ask for a production drawing back before you commit the order. If that drawing comes back with questions about your wall substrate or service routes, that is a good sign — it means the specification is being read, not assumed.