A set of smoked glass aluminum frame wardrobes looks simple on a rendering: aluminium profiles, tinted glass panels, made-to-measure heights. On the receiving end of an international order it is anything but simple. Glass panels travel in crates, aluminium frames pick up edge damage in transit, and a single missing handle set or an unconfirmed dimension can stall handover. If you are ordering built-in wardrobes for a villa, apartment or hospitality project from overseas, the delivery plan deserves as much attention as the design itself.

Start with the specification, not the shipping date

Our built-in furniture is made to measure, so the delivery clock only starts once dimensions, layout and finishes are signed off. For wardrobes in this family, that means confirming:

  • Room-by-room opening dimensions, including skirting, cornices, uneven floors and anything above the wardrobe line such as air-conditioning ducts or bulkheads.
  • Layout per unit: hanging zones, drawers, shelves, lighting provisions and how adjacent units meet at corners.
  • Glass type and tint for each elevation. Within our Glass & Aluminum Frame Wardrobes collection the same profile can carry smoked, clear or frosted glass, and mixing tints across rooms is a decision worth making once, in writing.
  • Frame colour and finish, for example the darker profiles used in our Minimalist Black Frame Wardrobes, matched against the joinery and door finishes elsewhere in the project.
  • Hardware: hinge brand, soft-close specification, drawer runners, integrated handles and any lock provision.

Every change after production starts resets more than the order date. It changes packaging, crate sizes and container loading, which is why we treat detail confirmation as a separate step between the quotation and production in our turnkey project workflow.

Choose an incoterm you can actually manage

Most wardrobe orders move by sea. Where your team stops managing the shipment depends on the term you buy:

  • FOB or CIF suits buyers with a freight forwarder they trust at the destination port. You handle customs clearance, inland transport to site and the last leg yourself.
  • DAP / door-to-door keeps one party responsible all the way to the delivery address. For project orders split across several unit types — wardrobes together with one-stop furniture and building materials such as flooring, wall panelling and vanity units — this usually reduces finger-pointing when a crate arrives short.

Our furniture logistics and door-to-door delivery service covers freight forwarding by sea, air and rail, customs paperwork, packaging and container loading, shipment tracking and delivery to site. Ask us for commercial invoices, packing lists and certificates of origin in the format your clearing agent expects — mismatched paperwork is a common and entirely avoidable cause of demurrage.

Plan packaging and container loading around the glass

Smoked glass panels are the fragile element; aluminium frames are heavy but forgiving. Before booking space, confirm with the factory:

  • Crate construction and internal bracing for glazed doors, and whether panels ship assembled in the frame or loose and glazed on site.
  • Glass thickness and tint per crate marking, so the site team can sort panels by room without opening everything.
  • Separation of hardware, mirrors and light profiles from glazed crates, since small parts are the items most often reported missing on arrival.
  • Loading sequence against your site programme — the first crates unloaded should be the ones the installation crew needs first.

For multi-unit orders we can consolidate wardrobes with other fit-out items into shared containers. Consolidation saves freight cost, but it only works if the packing list is itemised per room and every crate carries a unit reference that matches the shop drawings.

Sequence delivery against the site programme

Built-in wardrobes are installed after wet trades, flooring and electrical first fix are complete, but before final decoration and loose furniture. Work backwards from your installation window:

  1. Site survey and drawing sign-off.
  2. Production, with a pre-shipment check of frame squareness, glass tint consistency and hardware count against the schedule.
  3. Booking vessel space — confirm the cut-off, not just the sailing date.
  4. Customs clearance at destination; allow contingency for inspection holds.
  5. Delivery to site or to a staging warehouse if the building is not yet ready to receive crates.

Storage at the destination port is expensive, and crates left standing in an open yard are an avoidable risk. If your site cannot receive the shipment, arrange covered storage before the vessel arrives rather than after.

Close out with inspection and support

On arrival, check each crate against the packing list before the carrier leaves, photograph any damage on the crate itself and on the contents, and record crate numbers rather than generic counts. Replacement glass cut to a confirmed dimension is straightforward; replacement glass cut to an assumed one means another shipment and another wait.

Our installation and after-sales support covers on-site installation, inspection and snags, spare parts and maintenance. Where your own crew installs, we supply marked shop drawings and hardware schedules so the fixing sequence is clear before the first crate is opened.

A short checklist before you place the order

  • Dimensions verified on site, not from architectural drawings alone.
  • Glass tint and frame finish confirmed against physical samples for every room.
  • Incoterm, insured value and delivery address agreed in writing.
  • Packing list format agreed with your clearing agent.
  • Storage plan ready if the site cannot receive the shipment.
  • Snag and spare-parts route agreed before installation starts.