Wood veneer hinged doors look simple on a schedule line: one door type, one finish, one quantity. They are the doors that most often come back as site problems, because the veneer, the core, the frame and the ironmongery all have to agree before production starts. If your procurement team is specifying Santerson Wood Veneer Hinged Doors for a villa, apartment or hospitality fit-out, the record you keep alongside the purchase order matters as much as the order itself. This article sets out what to write down, why each missing item turns into rework, and how to sign the doors off on site.
Why this door type needs a fuller documentation pack
Santerson Wood Veneer Hinged Doors sits in the Hinged Doors collection within the site's Windows & Doors range. The published product page describes it as made for residential door projects, with finish, layout and dimensions specified per space, plus made-to-measure sizing and material and finish options. That wording is deliberately open: there is no single fixed size, board material or veneer species on the page, and the same configurability applies to related items such as Santerson Flush Hinged Doors and Santerson Wood Veneer Pocket Doors.
For a procurement team, that means the door is defined by your documents, not by a catalogue line. Two identical openings can receive different doors if one room has a flush wall finish and the other does not, or if one schedule assumes a single leaf and the next a pair. Writing the decisions down at specification stage is what stops a batch arriving that no site condition matches.
The eleven items to record for every door opening
Work room by room, and give each opening a door number that stays the same from drawing through to handover. For each one, capture the following.
| Item to document | What good looks like on the sheet |
|---|---|
| Door number and location | One ID per opening, tied to a room name and the drawing revision it came from. |
| Leaf count and opening direction | Single or pair, left or right hand, inward or outward swing, checked against traffic flow and furniture layout. |
| Clear opening size and frame size | Finished floor level to head, plus the frame build-up, so the wall finish thickness is included rather than guessed. |
| Wall construction and finish | Block, stud or panelled background, and the wall finish that the door and architrave have to meet. |
| Veneer species, cut and grain direction | The veneer face you have approved, how it is cut, and whether the grain runs vertically or horizontally across the leaf. |
| Surface finish and sheen | The approved lacquer or oil system and its sheen level, with a signed physical sample rather than a screen image. |
| Edge and core build-up | Total door thickness, edge treatment on both long edges, and the core type you have agreed for acoustic or privacy duty. |
| Ironmongery schedule | Leaf size and weight against hinge positions, lock case backset, handle height, closers and any hold-open devices. |
| Veneer continuity with joinery | Where the door must match Wood Veneer Panels, wardrobes or cabinetry: same batch, same grain sequence, same sheen. |
| Threshold and floor interface | Floor covering build-up at the opening, undercuts, thresholds and any accessibility requirement. |
| Site conditions at delivery | Storage location, humidity exposure, and whether the opening is still wet-trade work when doors arrive. |
Keep the table in one file with the purchase order. When a query comes from production or from site, both sides are looking at the same numbers instead of trading emails about which drawing version was current.
Dimension and interface records that prevent rework
Most door snags on residential and hospitality projects are interface failures rather than product failures. Three records catch the majority of them.
1. A dimension sheet taken from the finished condition, not the structural shell
Record sizes against the completed wall and floor finishes, and state that on the sheet. Where an opening is still to be packed out or lined, note the tolerance you expect site to absorb and who owns it. Made-to-measure production cannot recover from a wall build-up of a few centimetres that nobody wrote down.
2. A hinge and ironmongery schedule that matches leaf weight
Tall and wide veneer leaves need hinge counts, positions and load ratings fixed before the cut. Note lock backset, handle height and any closer on the same sheet as the door size, so the machining is done in the factory rather than chased out on site.
3. A flush-detail decision per opening
Decide opening by opening whether you want a visible architrave or a flush, minimal-joint line. Flush and concealed details change the frame, the wall make-up and the decoration sequence. If some rooms need that treatment, list them separately and cross-reference Santerson Flush Interior Doors or the Integrated Door & Paneling option, so the wall build-up is designed together with the door instead of after it.
Veneer and finish records: how to keep the batch looking like one building
Veneer is a natural material, so variation between leaves is expected; unmanaged variation across a floor is what reads as a defect. Document four things.
- Approved sample reference. Number every physical sample you sign, keep one in your file, and put that number on the order line.
- Batch and sequence plan. Note which rooms are grouped in one production batch, so doors seen side by side come from matched material.
- Grain and matching instruction. State whether leaves should be book-matched, mirror-matched or run in a single direction, especially for pairs and for doors set into panelled walls.
- Sheen and finish system. Record the approved topcoat and sheen. A matched veneer under a different sheen still looks wrong under lobby lighting.
Where doors sit next to other veneer work, order them together with the joinery. Santerson's Wood Veneer Panels and wardrobe ranges are specified the same way: made-to-measure sizing with material and finish options. That makes a single specification pack covering doors, panelling and cabinetry the simplest way to keep one floor consistent. The company's Custom & OEM Service covers bespoke finishes and textures alongside standard production, which is where a project-specific veneer requirement should be raised: before drawings are issued for production, not after.
Commercial and logistics records for an imported door package
Doors are a schedule-critical delivery, so the commercial file needs the same discipline as the technical one.
| Record | Why it earns its place in the file |
|---|---|
| Approved shop drawings with revision dates | The single reference both factory and site work from; undated revisions are how two versions of one door get built. |
| Order lines matched to door numbers | Makes delivery checking a tick-list exercise instead of an argument at the hoarding. |
| Packaging and pallet marking list | Each leaf marked with its door number and room, so crates can go straight to the right floor. |
| Delivery terms and shipping documents | Santerson's logistics service covers freight forwarding by sea, air and rail, customs paperwork, packaging and container loading, shipment tracking and door-to-door delivery. Keep your Incoterms, commercial invoice and packing list aligned with the door numbers. |
| Delivery window and storage plan | Veneer doors need a dry, acclimatised store; note where they land and who protects them until hanging. |
| Inspection and snag sheet per leaf | Sign each door on arrival for finish damage and correct size, before the packaging leaves the site. |
| Warranty and spare-parts record | The company's installation and after-sales pages list warranty coverage plus spares and replacement; keep your claim route, photos and door numbers together so a replacement order can be placed without re-specifying. |
Confirm import terms, duties and delivery scope for your own project rather than assuming published service descriptions apply to your site. Door packages are where an unclear delivery term becomes a costly delay, because the trades behind it cannot start.
Sign-off checklist before you release production
- Every opening has a unique door number that appears on drawings, schedule and order lines.
- Leaf count, handing and swing direction confirmed against furniture and traffic layout.
- Sizes recorded against finished wall and floor levels, with tolerances assigned to a named party.
- Veneer species, cut, grain direction and matching rule written on each order line.
- Signed physical finish sample referenced by number on the purchase order.
- Ironmongery schedule reconciled with leaf size, weight and hinge positions.
- Flush versus architrave decision made per opening and reflected in the wall schedule.
- Doors batched together with matching veneer panelling and joinery where they meet.
- Pallet marking list issued so leaves can be delivered to their rooms without re-handling.
- Inspection sheet prepared for arrival, with photos logged against door numbers.
Santerson has operated as a China-based furniture and building materials manufacturer since 2008, and positions itself as a one-stop furniture and building materials supplier covering design coordination, custom/OEM production, door-to-door logistics, installation and after-sales support. Published Australian project references include villa work in Sydney, Melbourne, Perth, Willoughby and North Turramurra. For a door package that means one supplier holding the joinery, panelling and finish decisions together, provided your documentation gives them the same information you would expect from a local subcontractor.
If you want a second pair of eyes on your door schedule before it goes into production, send your opening list and finish references to the SANTERSON team through the contact page, and ask for shop drawings that carry your door numbers.
Frequently asked questions
Do I need a separate dimension sheet for each opening?
Yes. Made-to-measure doors are produced from per-opening sizes, so one row per door number with width, height, wall finish build-up and floor level is the minimum workable record.
What documentation carries the veneer decision?
A numbered physical sample plus a written note of species, cut, grain direction and sheen. Screen images are not a specification for a natural veneer face.
Should doors be ordered with the joinery package?
Where veneer doors meet veneer panelling or cabinetry, ordering them in one batch keeps material, grain sequence and sheen consistent. That is also the practical point to raise any project-specific finish requirement.
What should site check when the doors arrive?
Leaf identity against door numbers, size against the schedule, finish condition under raking light, and matching of leaves that will be seen together. Record it with photos before the packaging is removed from site.