Flush wall aligned doors look simple on a drawing: one clean plane, no visible frame, no casing breaking up the wall. That simplicity is exactly why they fail so often on site. The door either sits proud of the finished wall, shows a shadow gap that was never designed in, or arrives to find an opening that cannot accept the frame build-up. Before a project team signs off a door approval, the following confirmations should be closed out one by one.

1. Confirm which wall finish the alignment refers to

A flush door is only flush against something. On most villa and hospitality jobs, the wall receives its final layer — plasterboard jointing, paint, stone veneer, timber panelling or a decorative wall panel — long after the frame goes in. Ask the design team to state explicitly which finished surface the door face must sit level with, and confirm that the build-up on both sides of the opening matches that assumption.

  • Total thickness of the wall finish on the room side and the corridor side, measured from the structural opening face.
  • Whether the leaf is specified as single-sided flush in a single-leaf wall or double-sided flush in a partition.
  • Where the frame sits relative to the structural opening once the concealed frame build-up is added.

Fix this detail early wherever the door meets another finish. Integrated door and panelling packages set the leaf and the surrounding panel into one line, so the wall build-up has to be agreed before either item is manufactured.

2. Confirm opening sizes against made-to-measure dimensions, not nominal ones

Concealed-frame doors are supplied to project-specific sizes, and a nominal architectural dimension is not an order dimension. Before approval, the site team should re-measure the structural openings and return confirmed figures for width, height and wall thickness at each door position, together with the finished floor level at the threshold.

  • A door schedule that shows the finished opening size for each position, not one repeated typical size.
  • Threshold and floor build-up levels, including any screed or underfloor heating still to come.
  • Which side each leaf hangs on and its swing direction, checked against the furniture layout for that room.

Our Flush Wall Aligned Doors are made to measure with selectable materials, finishes and layout, so the confirmed dimension sheet is what governs production. Anything still marked "to be advised" on that sheet should hold up the approval.

3. Confirm hardware and leaf load before the frame is closed in

Concealed hinges and hidden frames carry their own constraints. Hinge positions, the number of hinges, the weight the set is rated for, and the lock or latch case all sit inside a frame that will be covered by the wall finish, so they cannot be adjusted once plasterboard tape goes on.

  • Leaf size and weight against a hinge set rated for it, especially for full-height leaves in tall openings.
  • Lock case, strike plate and handle or push-plate style — a handleless detail needs different edge preparation.
  • Whether an acoustic or privacy requirement changes the seal, drop-bottom and leaf construction.

Where the schedule calls for a handleless concealed door, confirm how the leaf is opened and how it is held open during handover. Where the design wants the door to read as part of the decoration, decorative concealed doors should be approved with their finish sample alongside the wall finish sample, not separately.

4. Decide the perimeter gap and edge detail in writing

Two details separate a well-executed flush door from a poor one: the size of the perimeter gap, and whether that gap was intended. A generic gap taken off a typical detail may not suit a tall leaf, a dark painted finish or a wall that moves with the seasons.

Detail to confirmWhat the approval should record
Perimeter gap widthThe agreed dimension, its tolerance, and whether it is consistent on all four sides
Shadow reveal or flush abutmentThe profile of the reveal, its colour, and which trade forms it — door supplier, plasterer or finish trade
Leaf-to-wall surface planeWhich trade is responsible for bringing the wall finish to the agreed plane
Paint and finish continuityWhether the leaf is painted on site or finished in the factory, and the sheen level

Record these decisions on the door approval sheet with a marked-up section drawing. Where the same detail repeats across a villa floor or a hotel corridor, one agreed section stops each trade from interpreting the gap differently.

5. Confirm sequence, protection and site access

Concealed frames belong to the first-fix stage; leaves and finishes come much later. A door package approved without a sequence will either sit exposed through the wet trades or be blocked by services routed through the opening afterwards.

  • Frame installation date against the plasterboard, screed, tiling and painting programme.
  • Who protects installed frames and leaves while other trades work in the same zone.
  • The delivery route inside the building — full-height leaves need a clear path and vertical storage.
  • Which items ship together, so frames, leaves and ironmongery arrive on the same visit.

For projects sourced from China, coordinating these stages is easier when one supplier holds the whole package. As a one-stop furniture and building materials supplier, SANTERSON manufactures doors alongside the joinery, panelling and finishes that surround them, and supports projects through production, freight and door-to-door delivery.

6. Confirm who signs off the mock-up

The most reliable approval step is a physical one. Install one complete door — frame, leaf, ironmongery and finished wall on both sides — at a representative position, then review it in the light the room will actually have.

  • Agree the mock-up location before production starts on the rest of the door schedule.
  • Check sight lines from corridors and main living spaces, where grazing light exposes uneven planes.
  • Operate every leaf several times, including any hold-open or soft-close element.
  • Minute the agreed result and photograph it as the reference for the remaining positions.

A signed mock-up turns a subjective detail into an agreed standard, and gives the site team something concrete to inspect against when the rest of the doors are installed.

7. Confirm what happens after handover

Flush doors stay with a building for years, and adjustment access is limited once everything is closed up. Before approval, establish how the package will be maintained.

  • Spare ironmongery and any replaceable leaf ordered with the original package.
  • The adjustment method for the hinges and the operative responsible for carrying it out.
  • Warranty terms and exclusions, particularly where an on-site finish is applied over a factory-finished leaf.

SANTERSON works on villa, hospitality and office projects with project-specific dimensions and finishes, covering design coordination, custom manufacturing and installation support. Our Flush Wall Aligned Doors sit within a wider flush and concealed door range that can be specified together with the surrounding panelling and built-in furniture as one package.

Approval checklist before you release production

Reference each door position on the drawings. Confirm the finished wall plane and build-up on both sides. Re-measure structural openings and return confirmed sizes for every leaf, including threshold levels. Fix hinge set, lock case and ironmongery against leaf weight and size. Record the perimeter gap and reveal detail on a marked-up section. Agree the mock-up location and who signs it off. Confirm delivery sequence, protection and spares.

If those seven items are closed out, the door is unlikely to appear on the snag list at handover. If any one of them is still open, the approval should wait — it costs far less to resolve on paper than in plasterboard and paint.