A mixed open and closed storage wall looks simple on a drawing: some shelves, some doors, one continuous finish. On site it is one of the less forgiving elements in a joinery package, because it combines made-to-measure cabinetry, wall tolerances, services behind the wall and a finish that has to read as one plane across several different functions. Most problems are not caused by the unit itself but by delivery and installation being planned as an afterthought. This guide walks through how we plan that sequence for Santerson Mixed Open & Closed Storage on villa, apartment and hospitality projects, and what we need from the site team at each stage.
Why this product type needs its own delivery slot
Mixed open and closed storage is a wall system rather than a piece of loose furniture. Open bays, closed cabinets and any open display niches in the same run share one set of vertical standards and one shadow line, so the units are manufactured to a fixed order and can only be assembled in that order on site. Nothing can be swapped or re-cut on the day without breaking the reveal.
Because it is made-to-measure, the dimensions come from a site survey of the actual opening, not from architectural dimensions on a plan. Plasterboard, skirting, architraves, cornices, power points and data outlets all change what the unit can occupy. A storage wall ordered against drawing dimensions before those elements are fixed is a frequent cause of re-order.
Stage 1: survey and dimensional sign-off
Before production starts, we ask for a confirmed wall setting-out. The items below must be final, because each one is built into the panel size:
- Finished floor and finished wall lines, including floor build-up height at the wall.
- Skirting and cornice details — whether they are removed, scribed around or carried through the run.
- Positions of power points, switches, data outlets and any integrated lighting feed, with as-built coordinates.
- Wall construction and fixing substrate: stud layout, noggins or reinforcement behind heavy open bays and wall-mounted sections.
- Adjacent door and window reveals, and the access route from the lift, stair or entry door to the room.
For runs that also carry a screen or TV position, we treat it as integrated media storage and confirm cable routes and ventilation behind closed cabinets at this stage, not at installation. Where a run reaches the ceiling, we size it against the same rules as full height storage walls, since floor-to-ceiling fixing depends on the slab level and cornice detail being resolved first.
Stage 2: production and finish confirmation
Once dimensions are signed off, the remaining decisions are material and finish. Doors, carcasses, open bay interiors and shelf fronts can be specified in different finishes, and a project often mixes lacquer, melamine and veneer across one elevation. We ask for one approved finish schedule per elevation, with the sample reference recorded, because open bays show the carcass colour from the front and a mismatch is visible immediately.
Where the storage wall sits within a wider turnkey villa furnishing package, we produce it together with the cabinetry and other built-in joinery from the same batch. Panels cut at different times can show a slight variation in wood figure or sheen even within one specified finish, so grouping them protects consistency across the apartment.
Stage 3: packing, freight and container sequence
Storage walls travel as flat packs with numbered sub-assemblies. We pack by elevation and mark each bundle with the room, wall reference and assembly order, so the fitter on site never has to guess which panel starts a run. Doors and glass-front elements are crated separately from carcasses, and open bay frames are protected at the front edge, which is the part most easily chipped in transit.
Our furniture logistics and door-to-door delivery service covers freight booking, packing lists, commercial invoices and the customs paperwork that goes with a joinery shipment. Two practical points matter more than the route chosen:
- Sequence the container so the first room to be fitted is unloaded first. A storage wall blocked behind another project's crates sits in the depot while the site waits.
- Check the delivery access before the truck arrives — lift dimensions, stair widths, turning radii at corners and whether panels can be carried horizontally. Long full-height panels are often the largest single item in a shipment.
Import terms, duties and clearance requirements vary by country and by consignment. We confirm Incoterms, insurance and documentation for each project individually rather than applying a blanket assumption from a previous order.
Stage 4: site readiness before the fitters arrive
A costly delay on a storage wall installation is arriving at a room that is not ready. Before we schedule installation, the following should be complete:
| Site item | Required condition |
| Wet trades | Plastering, tiling, painting and floor finishes complete and dry, so levels are final and the finish will not be damaged by later works. |
| Services | First-fix electrical and data in as-built positions; any integrated lighting feed tested and left accessible. |
| Substrate | Reinforcement or noggins in place behind the fixing line where heavy closed cabinets or wall-mounted sections are scheduled. |
| Storage on site | A dry, lockable holding area for flat packs, with crates kept upright and off the floor until fitting begins. |
| Environment | The space enclosed and, where available, conditioned, so panels acclimatise to the room before fixing. This matters most for veneer and lacquered fronts. |
| Other trades | No flooring, curtain or painting crews scheduled in the same room during installation. |
We normally ask for a short pre-installation walk with the site team and record it. A brief check against the setting-out drawing at this point prevents rework that a full day of fitting cannot undo.
Stage 5: installation sequence and handover
Our furniture installation and after-sales support covers on-site fitting, inspection and the snag list that follows. For a mixed open and closed wall the practical sequence is:
- Set out the run on the wall and establish the datum line; the first vertical sets everything after it.
- Fix base or wall-mounted carcasses, checking level and plumb along the whole line before tightening.
- Add open bays and niches, then shelves, so the reveal between open and closed sections is consistent.
- Hang doors and adjust hinges last, after the carcass line is fixed, then fit handles and integrated lighting.
- Inspect against the approved finish schedule, protect the fronts, and record snags with photographs before the crew leaves.
Handover should include the finish references used, the layout drawing as built, and a list of any spare panels or doors shipped with the order. Keeping that pack on file makes a later replacement or an extension of the run straightforward instead of a matching exercise.
A simple timeline to plan against
| Milestone | Who owns it |
| Layout and finish schedule agreed | Design team with supplier |
| Site survey and dimensional sign-off | Site team, after wet trades |
| Production and finish sampling | Supplier |
| Freight booking and documentation | Supplier with clearing agent |
| Site readiness check | Site team, before the crew is scheduled |
| Installation, snagging and handover | Supplier's fitters with site supervision |
Working backwards from the practical completion date is what makes this hold. If installation falls in the last week of a programme, there is no room to absorb a survey error or a delayed container.
What to send us to start
To quote and plan a storage wall accurately, send the elevation drawing with room and wall references, the finish schedule, the intended mix of open bays, closed cabinets and niches, and the programme date you want the units installed against. We will confirm what can be manufactured to those dimensions and where a survey is still needed.
As a one-stop furniture and building materials supplier, we handle joinery production, packing, freight documentation and installation for these wall systems under one coordination team, which keeps the survey, shipment and fitting sequence in the same set of hands. Send your drawings through our contact page and we will return a delivery and installation plan for the run.