A set of high gloss PVC cabinets is one of the most finish-sensitive items in a kitchen fit-out. The panels carry a reflective surface that shows every scratch, every pressure mark and every shift in tone, and they are made to measure for a specific plan. That combination - visual sensitivity plus custom sizing - is exactly why an international order can fail long before the container reaches the site. The problems are rarely the cabinets themselves; they are the handovers between design, production, freight and installation.

The sequence below follows the workflow we work to on project orders: custom and OEM production, then logistics and door-to-door delivery, then installation and after-sales support. Each stage has decisions you need to close before the next one starts.

Before production: what has to be fixed on paper

Made-to-measure cabinetry cannot be corrected in transit. Every dimension, door swing and appliance recess needs to come from a drawing that the buyer and the factory have both signed off, because a panel cut to a superseded revision is scrap, not a delay. The practical minimum before a production slot is booked:

  • A coordinated set of final drawings - elevations with overall and finished dimensions, floor levels, skirting treatment, and the position of services that cabinets have to clear.
  • One written finish schedule - the exact PVC wrap or lacquer reference for every door and carcass, plus edge banding, handle specification and hardware brand. High gloss shows batch differences more readily than a matte texture does.
  • A named layout for each room - corner units, tall units, glass-front sections and integrated appliances listed unit by unit, so the packing list can be read against the drawing.
  • Confirmation of what is excluded - worktops, sinks, taps, appliances and any site-built returns are usually supplied locally, and their dimensions still affect the cabinet carcass.

If the same design repeats across apartments or villas, ask for one prototype set to be built, photographed and approved before the balance is cut. That single step removes most of the disputes that surface at handover.

Choosing the shipping terms decides who owns each risk

Incoterms are not a price comparison; they define where your responsibility begins. A door-to-door arrangement covers the whole movement of goods from production to delivery at site, which is what our project services describe as part of the workflow. Keeping one party accountable for factory to port, ocean or rail, import clearance and final transport matters most on cabinetry orders, where a delay is not just late goods but an idle site.

  • Door-to-door - supplier handles freight, documentation and inland delivery; you receive the goods at site and arrange unloading labour.
  • Port-to-port with your own forwarder - more control over carrier and routing, but you carry the customs clearance and any detention costs if paperwork is short.
  • Sea, air or rail - sea is normal for full container cabinetry loads; air freight only makes sense for a small number of replacement panels, and even then the panel dimensions often rule it out.

Ask your supplier which documents they issue and check them against your own customs broker's requirements before the goods sail: commercial invoice, packing list, certificate of origin, and any import permit or declaration your country requires for timber-based board products. Mismatched HS codes and undervalued invoices are the two most common causes of containers sitting at a port.

Packing and loading are where high gloss finishes get damaged

Reflective PVC surfaces need protection on three fronts: abrasion between panels, impact at the edges, and moisture inside the container. Specify the packing method in the purchase order rather than accepting whatever the factory normally uses.

  • Face-to-face protection - gloss doors packed with a protective interleaf between finished faces, never stacked gloss against gloss dry.
  • Edge and corner protection - corner guards on every door panel; the corners are where chips become visible under raking light.
  • Rigid outer cases - plywood or heavy cardboard crates with strapping, doors standing rather than flat where crate height allows.
  • Moisture control - desiccants and container liners for ocean passages, plus a requirement that panels reach ambient temperature before unwrapping on arrival.
  • Marking that matches the drawings - each crate labelled with the room, unit code and sequence number used on the layout, not just "Kitchen 1 of 4".

Loading order is as important as packing. Cabinets that install first should be loaded last so they come off the container first, and heavy stone or glass items must never ride above door panels. Ask for a loading plan with photographs taken at container stuffing - those photos are what you refer to if a claim has to be raised.

Sequencing delivery against the site programme

Cabinetry arrives into a room that must already be ready: screed and plaster dry, services first-fix complete and signed off, flooring either protected or laid, and a secure, dry storage area. A container of made-to-measure cabinets delivered to a wet, shared site is an expensive problem twice over - the panels can be damaged, and the room they belong to may not exist yet.

Work backwards from your installation date rather than forwards from production. Confirm the production slot, allow the transit time quoted by the forwarder for the actual routing, then add a clear margin for customs inspection and inland transport. Where a project has several bathroom or kitchen types, splitting the shipment so that one complete type arrives together is usually better than one large mixed load: installers can finish and hand over one area at a time.

Receiving, inspecting and closing out

Inspection happens at the container, not after the crates are spread across floors. Check crate counts against the packing list first, then open the panels in sequence and look at each finished face under raking light for scratches, edge chips and tone variation. Photograph any damage on the spot with the crate marking visible, and note it on the delivery paperwork before signing.

Replacement panels take time to produce and ship, so report shortages or damage the same day rather than at the end of installation. Our after-sales support service lists spare parts and replacement for project orders, but the practical answer is always faster when the request arrives with the crate marking, unit code and photographs.

A final note on scope: a kitchen order rarely travels alone. Projects that also source interior fixtures, vanities, wardrobes or flooring from the same supplier can consolidate shipments and share one set of customs documents, which cuts handling and reduces the number of separate arrivals to coordinate on site.