An outdoor swim spa rarely fails because of the shell. It fails at the handover point, where the design intent drawn by the design team never quite matches what the procurement package asked the factory to build. The Outdoor Swim Spa WS-PC06ST-L sits in that gap more often than most project teams expect, because it is a configurable product: the catalog gives you a footprint and a feature list, while the actual build depends on which options you confirm and who signs them off.
If the designer and the buyer are not working from the same confirmed document set, the spa arrives correct and the site around it is wrong. Below is the alignment checklist we recommend before a purchase order is raised.
1. Agree on the exact model designation first
The most common avoidable error is a loose model reference in the specification. Within this range, the catalog lists closely related models that share the same width and depth but differ in length: WS-PC06ST-L at 6390 × 2400 × 1470 mm and WS-PC06ST at 5900 × 2400 × 1470 mm. A drawing that simply says "6m swim spa, Santerson range" does not distinguish them.
Ask the buyer to state the full model code in three places: the schedule of finishes, the purchase requisition and the foundation/structural setting-out drawing. Ask the designer to confirm that the longer shell still clears the deck, the access route for delivery, and any overhead structure. Roughly half a metre of length changes the pool deck layout far more than it changes the water.
2. Lock the dimensions into the civil works, not the other way round
The catalog dimensions for this model are 6390 mm long, 2400 mm wide and 1470 mm deep. Those numbers should be transferred to the structural and landscape drawings before any concrete is poured, together with the working space the installation team needs around the shell.
| Catalog length | 6390 mm |
|---|---|
| Catalog width | 2400 mm |
| Catalog depth | 1470 mm |
| Total power shown | 6.55 kW |
| Jet total shown | 6 pcs |
| LED lights shown | 4 |
| Filter pump shown | 1 pc |
| Control system shown | 1 set |
| Swim training system shown | 1 set |
These figures are the values recorded in the product listing. Treat them as the starting point for coordination, and re-confirm them against the signed configuration sheet for your order.
3. Decide what is included and what is an option
The features shown for this model are water jets, LED lighting, ozone and a swim training system. Beyond that, the catalog lists options such as control systems, UV sterilisation, water pumps, heat pumps, sand filtration, insulation and steps. Availability and compatibility vary by model.
Two points matter here. First, a heat pump is not a line item you can add casually after order confirmation — it changes the electrical load, sometimes the plant space, and often the insulation package you need for overnight heat retention in a cooler climate. Second, the captured specification for this model does not list a water pump. If your design relies on a specific jet performance or a particular circulation arrangement, get that written into the configuration rather than assuming it is standard.
The practical rule: the buyer sends the option list, the designer marks which options their drawings already assume, and anything the two lists disagree on gets resolved before the order, not during installation.
4. Electrical coordination is where handovers break down
The listing shows a total power figure of 6.55 kW for this configuration. That number is only useful to the MEP consultant if it is confirmed for the exact option set you are buying, because adding a heat pump or upgrading pumps moves it.
- Cable size, breaker rating and run length should be designed from the confirmed configuration, not from the catalog figure.
- Isolation location, RCD protection and bonding arrangement need to appear on the electrical drawings before first fix.
- The supply authority or local electrician must approve the installation. Local electrical requirements are set by the site, not by the product listing.
- Where the spa sits relative to plant access and the control system should be shown on the layout, since service visits need reach.
A buyer who orders on catalog figures alone will get a compliant shell. A designer whose drawings were never updated for the real configuration is the one who ends up chasing an electrician on site.
5. Specify the swim function as a use case, not a feature name
"Swim training system: 1 set" tells procurement that hardware exists. It does not tell the design team how the space will be used. In a villa or resort context, the questions worth putting in writing are different: is this unit intended for daily laps by residents, for hydrotherapy and low-impact rehabilitation, or for evening relaxation with jets running? The answer drives jet layout, water temperature targets, lighting scenes and even how the surrounding deck furniture is arranged.
Where a project needs something beyond the standard catalog geometry — an oval, curved or otherwise customised footprint set into a terrace or garden wall — that should be raised at design stage rather than solved on site. Santerson's range includes customized shape outdoor spa options for exactly that situation, which is a design decision and not a late variation.
6. Put the rest of the outdoor package on the same schedule
A swim spa rarely arrives alone. In most villa and resort packages it lands alongside loungers, shade structures and poolside seating that have to match in finish and tolerate the same exposure. Coordinating those items with the same supplier avoids two different interpretations of "weather-resistant" across one deck.
The Swimming Pools and Swim Spas category covers the wider swim spa range, and outdoor furniture for villas and resorts covers what usually surrounds it. For a project buying shell, seating, shading and interior fixtures together, turnkey villa furnishing keeps the whole scope under one coordination process instead of several unrelated purchase orders.
7. Fix the responsibility split before the order
The clearest projects are the ones where the split is written down early: who supplies the shell and equipment, who prepares the base and surrounds, who runs the supply and bonding, who commissions the system, and who maintains it after handover. Ambiguity here costs more time than any product question.
Santerson's stated scope covers design coordination, custom/OEM production, door-to-door logistics, installation support and after-sales service. Site preparation, local electrical work and statutory approvals remain with the local contractor and their engineer. Both sides should be able to point at the same document when a question arises on site.
Before you raise the purchase order
- Full model code WS-PC06ST-L written into the schedule, the requisition and the setting-out drawing.
- Confirmed option list signed by the designer, with heat pump, insulation, filtration and steps resolved one way or the other.
- Electrical design based on the confirmed configuration, reviewed by the local electrical contractor.
- Access route, crane or lift path and working clearance around the shell checked against the delivered dimensions.
- Written responsibility split for base preparation, connections, commissioning and warranty response.
When those five items agree, this model specifies cleanly. When they do not, the spa is fine and the project is late. Send us the drawings and the option list you are working from, and we will confirm the configuration against them before anything goes into production.