A materials schedule is the document that keeps a villa or hospitality fit-out honest. It records every finish, product and fitting room by room, so that what was drawn in the concept becomes what is ordered, delivered and installed. Wall panelling is easy to under-specify in that document: it appears on a single elevation, gets described as "feature wall panelling", and then three different trades interpret it three different ways during construction. This guide walks through how to place Santerson Textured Panels in a whole-project materials schedule, so the entry is complete enough to price, order and install without a second round of queries.
Why textured wall panels break schedules when they are under-specified
Textured finishes behave differently from flat ones in two ways that matter for procurement. First, texture changes with light: the same panel can read as a soft matte surface under diffuse ceiling lighting and as a strongly patterned surface under a wall light fixed close to the wall. Second, texture affects the joint detail. A flat lacquered panel can be butted tightly; a textured panel often needs an intentional shadow gap, a trim or a reveal, and that decision affects adjacent skirtings, architraves, cabinet edges and any Integrated Door & Paneling line that has to disappear into the same wall.
When those points are left out of the schedule, the panel is priced as a loose item rather than as part of a wall build-up. The result is change orders late in the job: extra substrate work, a different fixing method, or a finish sample approved on a small board that cannot be reproduced across a full wall height. Writing the detail into the schedule at specification stage costs nothing; discovering it on site costs time and margin.
Step 1 — Set the scope: which rooms carry panels, and where they stop
Start by listing every location that will carry a textured surface, and state the boundary of each one. A useful entry names the room, the wall, the start and end points, and the elements it meets. "Bedroom 3 feature wall" is not schedulable. "Bedroom 3, headboard wall, floor to soffit, with a return into both side reveals, terminating against plaster with a shadow gap at each edge" is.
- Continuous walls: state whether panels run uninterrupted behind built-in cabinets and bed heads, or stop short of them.
- Doors in the panelled field: if a door sits inside the panelled area, schedule it as integrated panelling so the leaf is finished to match the surrounding wall rather than being painted.
- Wet and humid areas: where panels appear in bathrooms or near spa areas, note the location explicitly so the material and finish selection can be confirmed for that environment.
- Transitions: record how the panel meets flooring, ceiling, skirting, architrave and any stone or timber element beside it.
Step 2 — Schedule the finish family, not one product name
A whole-project schedule usually carries more than one wall finish, and the entries need to sit in a consistent family so that alternatives can be compared at tender stage. In the Paneling Systems range, Santerson Textured Panels sits alongside Santerson Matte Lacquer Panels, Santerson Stone & Marble Panels and Wood Veneer Panels. Listing the family, then naming the specific selection per room, keeps the schedule readable for a quantity surveyor and gives you realistic substitutions if a finish is unavailable for your delivery window.
The same logic applies to operable walls. Where a partition or closet front needs to move, specify from the Sliding Panel Systems range so that the track, hardware and panel thickness are coordinated with the fixed panelling next to it — Santerson Textured Sliding Panels carries the same textured language as the fixed panels while being built around a moving leaf.
| Schedule field | What to record for a textured panel entry |
|---|---|
| Location / room code | Room number and the specific wall, matching the drawing references used elsewhere in the schedule. |
| Product reference | The named product from the range, plus the finish or texture selection for that room. |
| Dimensions | Panels are made to measure; give wall extents and heights as they will be verified on site, not as drawn nominal sizes. |
| Layout | Panel widths, joint positions, direction of run, and any set-out that has to align with a door, bed or light fitting. |
| Edge and junction detail | Shadow gaps, trims, reveals, and how edges terminate at plaster, stone, glass or built-in cabinets. |
| Fixing method and substrate | The required backing and fixing approach for the wall construction in that location. |
| Adjacent trades | Electrical outlets, lighting grazes, air grilles and skirtings that must be set out around the panel grid. |
| Sample status | Whether a physical sample has been approved, at what size, and by whom. |
Step 3 — Record made-to-measure sizing as a site verification, not a drawing number
Santerson wall panels are configured with made-to-measure sizing and material and finish options for each project. That means the dimension in your schedule is a target until the opening has been built and checked. Put a site-verification step in the schedule notes, and align it with your programme: panels should be released for manufacture after the substrate and first-fix services in that location are complete and the wall has been set out.
Step 4 — Coordinate the texture with the rest of the material palette
Textured panels rarely appear alone. In a villa or hotel guest room they sit next to engineered wood flooring, cabinet fronts, window treatments, stone surfaces and lighting. Schedule them as part of that palette so the comparison is made once, with all samples together, rather than in isolation.
- With built-in cabinets: where Custom Niche Paneling or built-in storage meets a textured wall, confirm whether the recess lines up with a panel joint or deliberately breaks the grid.
- With ceilings: a textured wall that runs up to Ceiling Panels or a plasterboard soffit needs the junction detailed, including any shadow gap continued into the ceiling line.
- With lighting: note every fitting that shines along the surface. Light fixed close to the wall makes texture more visible and shows up uneven joints, so its position should be settled before the set-out drawing is issued.
- With flooring: record whether panels stop at the skirting, run over it, or continue to the finished floor level.
Step 5 — Bring panelling into one procurement line with the rest of the envelope
Splitting wall finishes across several suppliers multiplies the coordination work: separate samples, separate delivery windows, separate claims if something arrives wrong. Because SANTERSON supplies furniture and building materials together, panelling can be scheduled in the same package as Wall Panels and Wall Cladding, Engineered Wood Flooring, ceiling panels, doors and Built-in Furniture, which keeps one accountable party for set-out, delivery sequencing and site coordination. The company's one-stop solution covers design consultation and space planning, material selection and product specification, manufacturing and quality control, project management and site coordination, through to installation and handover.
For teams sourcing from overseas, that single line also simplifies logistics: the site lists freight by sea, air or rail, customs paperwork, packaging and container loading, shipment tracking and door-to-door delivery as services, with installation and after-sales support following delivery. Confirm the commercial terms, insurance and delivery scope for your project individually rather than assuming published service descriptions apply unchanged.
Step 6 — Pre-issue checklist for the panelling entries
- Every textured surface has a room code, a wall reference and defined start and end points.
- The finish selection is named per room, not once for the whole project.
- Panel set-out drawings exist for each location, with joint positions coordinated to doors, outlets, lighting and headboards.
- Edge details are drawn at plaster, stone, glass, ceiling and floor junctions.
- Substrate and fixing method are stated for each wall construction type.
- A physical sample has been approved at a size representative of the texture before the entry is signed off.
- Made-to-measure dimensions are flagged as site-verified, with the verification milestone in the programme.
- Panelling, built-in cabinets, doors and flooring that meet each other are on the same procurement line, so set-out is coordinated by one party.
A worked example: one entry written properly
Compare these two lines from the same schedule. The first will generate queries; the second can be priced and ordered.
| Weak entry | Working entry |
|---|---|
| "Feature wall panelling to master bedroom — as per design intent." | "MB01 headboard wall: Santerson Textured Panels, with the approved finish sample reference recorded on the finish schedule; made-to-measure, dimensions verified on site after substrate sign-off; full height from finished floor to plasterboard soffit; shadow gap at both vertical edges and a continuous reveal at the ceiling line; set-out symmetrical about the bed centreline, with joints clear of wall lights and switched outlets; door to MB01 ensuite finished in matching panel; install after flooring and painting are complete." |
Nothing in the second entry is unusual. It simply answers, in advance, the questions that a manufacturer, a quantity surveyor and an installer would otherwise ask one at a time during construction.
Next step
If you are building out a materials schedule for a villa, hotel or office fit-out, send the room list and elevations with your enquiry and specify the panel family you want priced. The textured panels page shows the range entry, and Furniture and Building Materials Project Procurement explains how a single supplier handles specification, production and delivery for the whole package. Dimensions, finish selection and delivery scope are confirmed project by project.