A door schedule rarely looks risky on paper. The elevations show the panel layout, the finish note says "to match joinery", and approval moves on. The problems appear later, when a frame arrives that does not suit the opening, or when a classic panel profile clashes with the skirting the site team has already installed. Before you sign off Classic Panel Hinged Doors for a villa or hotel package, put six confirmations in writing.

1. The opening, measured on site, not off the drawing

Panel doors are usually supplied made-to-measure, so the numbers you send become the product you receive. Confirm finished floor levels and finished wall finishes first, because a 15 mm change in screed or plaster moves the clear opening height as much as the door allowance itself. Then confirm the width at head, middle and sill, the wall thickness at each opening, and whether the opening is plumb and square.

Record which party produces those measurements and who signs them off. On a project where doors arrive after the wet trades have finished, an unverified dimension turns into a site rectification, not a factory correction.

2. Swing direction, clearance and traffic flow

A hinged door needs the floor area it swings into. Check the leaf against wardrobes, vanities, furniture layouts and any glazed screens beside the opening, and check the arc against skirting, radiators and door stops. For accessible or hospitality guest rooms, confirm the clear opening width after the frame and leaf are installed rather than the structural opening.

Where a room cannot give up that floor area, compare the alternative operating types in the same finish family before approval — Classic Folding Doors and Classic Pocket Doors free the swing zone, but they change the wall build-up and the hardware you have to coordinate.

3. Panel profile, finish and what "matching" actually means

Classic panel doors are specified for their moulding: number of panels, raised or recessed, mould depth, and the stiles and rails around them. A drawing that says only "panel door to match joinery" invites variation. Confirm the profile against a physical sample, and confirm the finish system — veneer species and cut, paint colour with sheen level, or laminate decor — on a board, not on a screen.

If the door has to match cabinetry or wall panelling, state which element is the master reference and who signs the matching sample. Timber-based finishes from different batches can read differently even in the same species, so an approved physical reference protects you at handover.

4. Hardware set and load

Hinged doors are only as good as what holds them. Confirm hinges by grade and quantity for the leaf size and weight, the latch and lock case format, handle design and backset, plus closers, keep plates, door stops and any hold-open devices. For a project package, decide which of these items you supply locally and which come with the door set; mismatched local hardware is one of the most common reasons installation stalls.

Fire-rated, acoustic or moisture-controlled leaves are separate specifications and must be requested as such — they change the core, the frame, the seals and the ironmongery schedule. Do not assume a decorative panel door in the same visual style carries those performance duties.

5. Interface with flooring, skirting and wall finishes

Thresholds and transitions are where a specification quietly fails. Confirm the floor build-up at each opening, the threshold profile between rooms of different materials such as engineered wood flooring and stone or tile, and the door frame detail at skirting and architrave. Where the design calls for a flush or wall-aligned look, that decision belongs with the frame and wall build-up from the start — see Flush Hinged Doors if the intent is a near-invisible line rather than a moulded architrave.

6. Lead time, packaging and sequence of installation

Confirm production lead time against the site programme, then confirm how the doors travel and where they are stored on site. Solid panel leaves and frames need flat, dry storage and protection at the edges; damage discovered after delivery is far more expensive than a corrected packing note agreed in advance. For international packages, agree the packing list format, container loading sequence and receiving responsibility before the order is released.

Sequence matters as much as date. Doors usually install after wet trades, flooring and finishes are complete, so schedule them with the joinery and windows and doors package rather than treating them as a late trade item.

How SANTERSON handles door approval on project packages

SANTERSON is a China-based manufacturer and one-stop supplier of furniture and building materials, operating since 2008, with project work across villas, hospitality and offices. Interior doors sit inside the same package as cabinetry, wardrobes, flooring, wall finishes and loose furniture, which is exactly where door coordination gets easier: opening sizes, finishes and thresholds are resolved once, against one drawing set and one production schedule.

For each project we work through design consultation and space planning, material selection and product specification, manufacturing with quality control, project management and site coordination, then delivery and installation support. Under the Turnkey Interior Project Solutions route, doors are specified alongside the rest of the fit-out rather than procured as a late substitute.

Approval checklist before you release the order

  • On-site dimensions signed off against finished floor and wall levels, at head, middle and sill.
  • Swing direction checked against furniture, fittings, skirting and required clear opening width.
  • Panel profile and finish approved from a physical sample, with the master reference named.
  • Ironmongery schedule agreed, including who supplies hinges, locks, handles and stops.
  • Thresholds, transitions and architrave or flush detail resolved with the flooring package.
  • Lead time, packing list, storage location and installation sequence confirmed in writing.

Send us your door schedule, drawings and finish references and we will confirm what can be produced to those dimensions and finishes for your project, together with the rest of the fitted furniture package.