A wall mounted open wardrobes submittal is the set of documents a contractor, designer or project owner reviews before production starts. For a made-to-measure piece that carries hanging loads on a wall rather than on a floor, the submittal is where dimensions, substrate conditions, fixings and finishes get agreed in writing. Below is the list we work to on our own wardrobe projects, item by item, so you can ask any supplier for the same set and compare offers on equal terms.
1. Drawings at three levels
Start with an elevation of each wall the unit sits on, a plan view showing how far the unit projects into the room, and a detail sheet for the parts that carry load: rail fixings, bracket positions, shelf-to-upright connections and edge trim. Elevations should show overall height, width and depth, plus the vertical spacing of every rail, shelf and drawer.
Plan views matter more here than they do for a wardrobe with doors. An open unit has no carcass to hide behind, so hanging garments, folded stacks and drawer fronts all project into the circulation space, and the plan is what proves a doorway or a bedside still clears. Ask for dimensioned drawings rather than renders: a render shows design intent, only a dimensioned drawing can be checked against site.
2. Wall and substrate confirmation
This is the section most often left out, and it is the one that causes rework on wall hung joinery. The submittal should state the finished wall construction — masonry, stud partition with plywood backing, timber frame, or an existing finished surface — and identify where the load path runs, because rails, uprights and brackets transfer weight into that structure rather than into a base plinth.
- Wall build-up, and the specific layer the fixings bite into
- Position of noggins, blocking or backing boards where loaded rails will sit
- Level and plumb tolerance of the finished wall face, and who corrects it if it is out
- Whether conduits, pipes or other services cross the fixing zone
If the wall condition is not known yet, the submittal should record that and schedule a site survey before release to production. A supplier who never asks about your wall is guessing.
3. Materials, finishes and samples
Name every material separately: panel substrate, edge treatment, decorative surface, metal components and any glass. Our metal frame open wardrobes and wood tone open wardrobes are specified the same way, because a line reading "grey wardrobe" on a bill of quantities does not survive contact with a site inspector.
Request physical samples of the exact surface rather than a colour card from another product family, and view them in the room's own light. Cross-reference the wardrobe finish against adjacent finishes — flooring, wall panelling, doors and ironmongery — on one finish schedule, so nothing clashes at handover.
4. Load ratings and hardware data
An open wardrobe is a storage system before it is a design feature, so ask for the working load of each rail, shelf and drawer, and how that figure was established: supplier test data, or published ratings from the hardware manufacturer. A full hanging rail over a metre of run loads a wall very differently from a folded-shelf bay.
- Rated load per rail, per shelf and per drawer, plus any stated deflection limit
- Fastener type, diameter and embedment depth for each wall condition listed in item 2
- Bracket and upright profile, with the maximum span between fixings
- Hardware make and model, so replacements can be sourced years later
Where a project requires an engineer to approve the fixings, name that responsibility in the submittal. Settling it on paper is cheaper than arguing about it after the first unit is on the wall.
5. Interior configuration driven by how the space is used
The layout sheet should follow the actual storage brief, not a generic template: long hanging for coats and dresses, double hang for shirts and trousers, shelf heights set to the depth of what is stored, drawers for folded knitwear, and lighting if the room is dim. On bedroom schemes we work from the same brief behind our minimalist open wardrobes range — what hangs, what folds, and what needs to stay out of sight.
Dust is the honest trade-off of open storage. If the client wants it in a bedroom, record that decision rather than working around it silently. Where a unit faces an entrance or works as a display wall, decide which bays stay open and which get a door or panel.
6. Tolerances and site sequencing
State the tolerance you will accept for floor level, wall flatness and ceiling height, and state who brings the substrate inside it. Then fix the sequence: which trades must complete the wall before delivery, whether flooring is laid first, and how the unit meets skirting, architrave and lighting. Made-to-measure joinery measured off an unfinished wall inherits every error that wall contains.
7. Packaging, delivery and installation
The packing list should read against the drawings: unit number, room, crate weight and dimensions, and a mark-up showing which crate belongs to which wall. Ask what edge and surface protection the panels get in transit, and confirm who unpacks, who positions the unit, and who makes the final adjustment on site.
8. Commercial terms and after-sales
- Quotation broken down by unit, so a change order touches one line instead of a whole room
- Lead time measured from drawing approval, not from enquiry
- What is covered after handover, how spares are ordered, and the replacement-panel lead time
- The revision rule: what happens if site dimensions change after drawings are signed off
Sign-off before production
A submittal is complete only when the drawings, wall condition, finish samples and load data have all been approved and dated, each with a named approver. That approval record is what protects the schedule later on. If you would like our team to review your wall elevations or price a wardrobe package alongside the rest of a project's joinery, contact us and send the drawings across.