A mirrored hinged wardrobe rarely fails because of the mirror. It fails on the paperwork: a door swing that clashes with the bed, a carcass depth that never matched the hanging space, or three rooms measured by three different people at three different times. If you are ordering mirrored hinged wardrobes for a villa, an apartment block or a hotel floor, the quantity plan and the coordination plan have to be settled before production starts. Here is how we work through both with project buyers.

Start from the opening, not the catalogue

Our hinged-door wardrobe line is made to measure: sizing, material and finish, and internal layout are all specified per project. That means a quantity list cannot be copied from another job. For every bedroom, record four numbers before anything else:

  • Clear wall length between the finished wall faces, including skirting and any architrave that will stay in place.
  • Floor to ceiling height at three points — left, middle, right. Slab levels on site vary more than drawings suggest.
  • Obstructions — switch plates, air-conditioning returns, curtain boxes, skirting depth, and the swing arc of the room door.
  • Finished floor level as built, not as drawn, plus the thickness of the wall finish still to be applied.

Take these from the same survey for every unit in the building. One surveyor, one datum line, one set of notes — that is what keeps a repeated floor plan from producing twelve slightly different wardrobes.

Count doors before you count metres

Quantity for a hinged wardrobe is driven by door count and door geometry, not by total running metres. Two identical rooms can need different door splits if one has a column on the left return.

ItemWhat to record per roomWhy it drives quantity
Door leavesNumber, width, mirror face and hinge sideSets hinge hardware, glass area and the swing clearance you need in front of the unit
Carcass baysWidth, depth, height per bayDetermines panel cut lists and how many bays ship per room
Internal fittingsShelves, drawers, hanging rails, lightingOrdered as loose items; easy to leave off a purchase order and discover on site
Mirror glassArea per door, plus sparesGlass is the component least likely to be replaced quickly at destination
Spare hardwareHinges, handles, shelf pins per unit typeA small spares holding on site avoids a stoppage over one missing part

For multi-unit projects, group the rooms by a repeatable unit code — Type A bedroom, Type B bedroom — and issue one specification per code rather than one per room number. Identical codes can then be produced together, packed together and installed in sequence.

Coordinate the wardrobe with the rest of the fit-out

A mirrored hinged door needs a clear arc in front of it. That arc is where most coordination problems appear, because the bed, the door into the room and the curtain line were all decided by other trades.

  • Against the room door: confirm the door opens away from the wardrobe, or that the wardrobe starts beyond the door's swing arc. Where space is tight, that one room may suit a sliding option such as mirror sliding door wardrobes while the rest of the building stays on hinged.
  • Against flooring: decide whether the wardrobe sits on the finished floor or is scribed to it. This changes both the height you order and who trims the skirting.
  • Against lighting: if internal lighting is specified, the driver position and cable route must be agreed before the carcass panels are drilled, and the electrician needs to know which wall the supply arrives on.
  • Against adjacent joinery: where wardrobes meet built-in furniture such as a window seat, a desk return or a whole house custom cabinetry and built-in storage project, one party must own the interface detail — which unit is packed out and which one is scribed.
  • Against wall finishes: plaster, wallpaper and paint all add millimetres. Order to the finished dimension and state that on the drawing.

We hold one coordination meeting per project type with the drawings open: wardrobe, bed layout, door swing, lighting and flooring on the same sheet. That meeting removes most of the change orders that would otherwise follow.

Set the order schedule around production and freight

Made-to-measure joinery and glass arrive in better condition when they are released in stages rather than ordered all at once. A sequence we use on villa and apartment packages:

  • First release: one representative room of each unit type, installed and signed off, so every dimension is confirmed against a real wall before the rest is committed.
  • Second release: the repeat batch for approved types, produced together so finishes come from the same material lot.
  • Third release: exceptions — rooms with columns, sloping ceilings or a different door layout — after site re-measurement.
  • Last release: loose internal fittings and spare hardware, shipped with the final consignment so they are not lost between deliveries.

Split shipments this way and each container arrives with a packing list that matches an installation week. Our logistics and door-to-door delivery service covers freight forwarding, packaging and container loading, customs paperwork and shipment tracking, so the delivery dates above are ones you can build a site programme around.

Check the specification sheet before you sign it

Before production, read back the confirmation drawing for each unit code and check six lines. If any one is missing, send it back:

  • Overall width, height and depth at the finished faces, with the datum stated.
  • Door count, hinge side and which face of each door carries the mirror.
  • Internal layout diagram with shelf heights and drawer positions dimensioned.
  • Finish reference for carcass exterior, interior and edges — a material and finish code, not a colour name alone.
  • Interface notes: skirting, flooring, lighting supply point, adjoining units.
  • Packing schedule by room code, so the installation crew knows which crate belongs to which bedroom.

For finishes that need to match existing joinery on site, request samples through our custom and OEM service before the batch is cut. Veneer, lacquer, melamine, glass and aluminium frames read very differently once they are fixed beside a window.

Common quantity mistakes we see on site

  • Ordering by room count instead of measured opening, then trimming units on site and arguing about who owns the damaged finish.
  • Forgetting that a mirror adds thickness to the door face, which changes the clearance needed at a nearby wall or bed side table.
  • Buying one set of internal fittings for the average room when two room types need different hanging heights.
  • No spare hardware held on site, so one missing hinge set stops work in a whole bedroom group.
  • Re-measuring late: by the time exception rooms are surveyed, the production slot has moved and the batch waits.

Send the drawings and we will build the quantity list with you

If you have room-by-room plans for a villa, apartment or hotel project, send them with your target installation dates. We return a unit-coded wardrobe schedule, door splits, mirror areas and a release plan that matches your site programme, then confirm every dimension against a survey before anything is cut. Our turnkey interior project solutions cover design coordination, production, delivery and installation support for wardrobe and joinery packages. Contact PHILLIP at santerson@qq.com or on WhatsApp +86-13928214007 to start the schedule.

Product dimensions, finishes and internal layouts are specified per project; confirm all dimensions and selected specifications for each order.