Classic French double doors usually arrive on site late in a villa or hospitality fit-out, and that timing is exactly why they cause trouble. By the time the door schedule reaches production, wall openings have been set out, floor levels have been poured and the finishes package has been signed off. A single undocumented item — an arch head radius nobody recorded, a swing direction assumed rather than drawn — turns into a rework order, a second container or a hold point at handover. The documentation below is what we ask procurement teams to lock down before an order for Classic French Double Doors is released, and it applies equally to the arched and slim-frame variations in the same collection.

Why double doors need a heavier file than single leaves

A single hinged leaf fails quietly: it binds, it is adjusted, it is forgotten. A pair of meeting stiles is different. Two leaves must meet at the same height, in the same plane, with the same reveal either side, or one leaf will always look wrong no matter how well it was made. Because our doors are made-to-measure — sizing, material and finish are all specified per project rather than picked from a stock list — the drawing package is what carries that accuracy across an ocean and into a site opening.

For projects where the whole joinery scope comes from one one-stop furniture and building materials supplier, this file also protects consistency. The same wall that carries French doors often carries wardrobes, panelling and concealed doors in matching veneer or lacquer. If the door schedule and the cabinetry schedule are written to different finish references, the mismatch is discovered on site, not in the factory.

The opening record: what must be on the drawing before order release

Send the measured opening, not a nominal architectural dimension. Every number below should come from site measurement or a coordinated construction drawing, with the datum stated.

Item to documentWhy it matters for double leaves
Rough opening width and height, plus finished floor levelDetermines frame build and the clearance each leaf needs above the floor finish.
Which face the measurement is taken fromReveal widths differ once plasters, panelling or stone returns are accounted for.
Head condition: square, arched, or soffit-reducedAn arched head is a different product build; state the radius and springing point.
Wall build-up and total thicknessFrame depth must match the completed wall, including any acoustic layers.
Squareness and plumb of both jambsMade-to-measure frames follow the drawing; an out-of-plumb opening needs to be recorded, not absorbed.
Floor finish thickness at the thresholdDetermines undercut and whether a threshold or saddle is required.
Adjacent finishes on both sides of the wallArchitrave, flush reveal or shadow gap must be agreed for each face separately.

Where a project uses an arched opening, do not assume the standard square-head build will be adjusted on site. Santerson Arched French Doors is a distinct configuration in the same collection, and it needs the radius, springing height and leaf division drawn explicitly.

The door schedule line: fields to fill in, not leave blank

A one-line schedule entry is where most procurement files fall short. For each opening, the following should be written out rather than inferred from a symbol on a plan.

  • Leaf count and active/passive designation. Which leaf carries the hardware, which is fixed or bolted, and whether the passive leaf is reversible.
  • Glass configuration where glazed. Pane count, glazing type and any obscure or laminated requirement per face.
  • Moulding and panel profile. Raised, recessed or flat panel; state the profile reference and show it on a detail, not in words alone.
  • Frame and architrave profile. Square, shaker or slim — and whether a Santerson Modern Slim Frame French Doors build has been specified instead of the classic profile.
  • Finish system and reference. Veneer species and cut, lacquer sheen, paint colour standard, and which side of the door each finish applies to.
  • Ironmongery package. Hinge type and count, meeting bolt, flush bolt, handle set, lock case backset and strike — with the cutouts shown on the shop drawing.
  • Hardware handedness per opening. Stated as push/pull and hinge-hand from a named side, so it does not depend on who reads the plan.
  • Acoustic or performance intent. If the wall is specified for sound separation, say so at enquiry; door build and seals follow from it. Where separation is critical, an acoustic panel system may be part of the same wall assembly.
  • Sign-off party and date. Who approved the schedule line, and when. Undated approvals are a common cause of late changes.
A practical test before release: hand the schedule line to someone who has never seen the project. If they cannot tell which leaf opens, which way it swings and what the finished edge looks like on both faces, the line is not ready for production.

Compatibility checks procurement teams should run before ordering

Doors are specified in isolation and installed in an assembly. Three checks catch most conflicts early.

  • Swing path against fixed work. Wardrobes, vanities, island edges and skirting all sit in the arc. Confirm the swing against the layout drawing for both leaves.
  • Wall alignment detail. If the design calls for a wall-flushed finish, that decision changes the frame and the wall build-up; it is documented with Flush Wall Aligned Doors detailing rather than assumed.
  • Alternative operation. Where the swing path cannot be cleared, a pocket or sliding arrangement may replace the hinged pair. Record that decision on the schedule so pricing and openings change together — see Classic Pocket Doors.
  • Consistency across the joinery package. Where doors, wardrobes and panelling come from one production run, confirm the veneer lot, lacquer batch and sheen reference are shared across schedules.

Commercial and logistics fields that belong in the same file

For an overseas order, the technical schedule alone is not enough. Procurement should keep these commercial fields alongside each opening code so nothing has to be chased after production starts.

  • Pack list mapped to opening codes, so every crate can be traced to a room on site.
  • Container loading sequence matched to the installation order, not just to packing efficiency.
  • Delivery term and destination, with the receiving party named for each consignment.
  • Spare and replacement allowance — matching architrave lengths, one extra hinge set per door type.
  • Storage plan on site. Made-to-measure doors arriving before the building is dry and enclosed is a frequent cause of damage claims.
  • The named approver for the shop drawing at each stage: enquiry, pre-production and shipment release.

SANTERSON describes its project workflow as running from design consultation and specification through production, quality control, logistics coordination and installation handover — so the documentation you produce at enquiry is what the factory works from months later. For a villa or hospitality package where doors sit alongside interior fixtures, cabinetry and finishes, that single coordinated file is worth more than any individual product detail.

Common documentation gaps we see on door schedules

  • Nominal instead of measured openings. Architectural dimensions are not site measurements; state which one you are sending.
  • "As per sample" with no signed sample reference. Name the sample, its date and who holds it.
  • Hinge count left to the manufacturer. Hinge count follows leaf weight and height — record the leaf dimensions so the choice is auditable.
  • One finish listed for a door between two different rooms. Guest-facing and back-of-house faces are often specified differently.
  • No threshold detail. The saddle, or its absence, decides acoustic performance, weather separation at a terrace door, and floor transition.
  • Approval trail in email rather than on the drawing. Revisions should be numbered on the sheet, not reconstructed from correspondence.

A short pre-production checklist

  • Measured opening recorded for every code, with datum and finished floor level.
  • Head condition confirmed as square or arched, with radius where relevant.
  • Active/passive leaf, swing direction and hinge hand stated per opening.
  • Moulding profile, frame profile and finish reference written on the line.
  • Ironmongery package listed with cutout details on the shop drawing.
  • Wall build-up and flush or reveal detail agreed for both faces.
  • Pack list mapped to opening codes; storage plan confirmed for site.
  • Named approver and revision number on every released drawing.

Documenting a classic French double door properly is not paperwork for its own sake. It is the difference between a pair of leaves that meet cleanly at first fitting and a hold point at handover. If you are assembling a doors-and-joinery package for a villa, apartment or hospitality project, send us the schedule and the measured openings and we will confirm what each line requires before production begins.