Two-tone grey cabinetry is easy to specify on a mood board and difficult to sign off on a shop drawing. The palette itself rarely causes rework; what causes rework is the list of details that never made it into the purchase order. If you are specifying light & dark grey modern kitchen cabinets for a villa, apartment or boutique hotel fit-out, here is what we ask buyers to lock down before production starts.
1. Which grey, on which surface, under whose lighting
Grey is not one colour. The same panel reads cool and flat under 4000K site lighting and warm under the 2700–3000K LED strips used inside glass display cabinets. In our grey modern kitchen cabinets with an LED glass wine cabinet, the light grey uppers and dark grey lowers are deliberately separated by the worktop so the two tones do not bleed into each other visually.
Before approval, confirm: the exact panel sample for both tones; whether the carcass interior matches the door colour or is a standard neutral; and whether your lighting designer has specified the colour temperature of the under-cabinet strip. A tone approved on a backlit sample card can look different once it is installed opposite a window.
2. Door style and edge profile
Flat panel doors carry this look, but the edge detail changes everything at close range. Tell us whether you want a square-edged slab, a handleless rail or groove pull, or a touch-to-open mechanism with no visible hardware at all — our handleless minimalist kitchen cabinets are built for that fully flush appearance. Also confirm the door thickness and whether the same profile continues on tall pantry units, where a slab can look thin against a 2,400 mm floor-to-ceiling elevation.
3. Appliance schedule — the most common source of delay
Integrated appliances must be fixed before carcasses are cut, not after. For each built-in unit we need the make, model and dimension drawing: refrigerator, oven or stacked double ovens, microwave, wine cooler, dishwasher. The tall housing for stacked ovens has to be engineered around the appliance's ventilation requirement, and the run of the under-counter units depends on where the dishwasher sits in the working triangle.
If appliances are still undecided, tell us which sizes you are considering so we can build a reserved housing with adjustable fillers rather than a fixed opening. That single decision saves a site visit later.
4. Glass cabinets and the lighting that goes inside them
Glass display sections need their own confirmation sheet: glazing type (clear, frosted or smoked), frame finish, shelf spacing for the tableware you actually intend to display, and whether the warm LED is top-mounted, vertical, or sensor-switched. A display cabinet specified without its lighting detail arrives as a dark box, and retrofitting cable routes into a finished cabinet is not clean work.
5. Internal layout, not just the front elevation
Clients review elevations and forget interiors. Confirm the drawer-to-door ratio in the base run, the number of pantry shelves, corner solutions (pull-out or lazy Susan), cutlery organisation, bin housings and any charging drawer. We customise internal partitions, panel colours and surface finishes per project, but only when the interior schedule is signed alongside the elevation.
6. Worktop, splashback and the junction with neighbouring trades
Stone worktops and splashbacks are usually supplied separately, so the interface must be agreed in writing: the thickness of the stone, whether the splashback sits on or behind the worktop, the scribe detail at the wall, and which party installs which element. A marble-pattern stone splashback specified as a panel behind the counter needs the cabinet run dimensioned to receive it.
7. Substrate, finish and site conditions
Confirm the board substrate and surface system for each zone — matte, gloss, acrylic, lacquer, melamine, PVC or wood veneer all behave differently near a sink, an oven housing or a coastal environment. For apartments and hotels we also confirm floor levels and wall plumb at handover; uneven slabs are normal on site, and the toe-kick and scribe allowance should be set to absorb them rather than discovered during installation.
8. Hardware specification in writing
Hinges, soft-close dampers, drawer slide rails, support legs and connecting brackets are part of the specification, not accessories. Confirm the brand or grade, the load rating for wide drawer fronts, and whether soft close applies to all doors or only the ones in daily use. Hardware specified late tends to be substituted on site.
9. Quantities, packaging and delivery sequence
For multi-unit projects, confirm the unit-by-unit schedule and whether identical layouts should be produced as repeat sets or adjusted per apartment. Confirm container loading sequence so kitchens arrive in installation order, plus labelling by room of destination. Our custom built-in kitchen cabinets are supplied as interior fixtures for hotel and apartment projects, where a staged delivery plan matters more than a single bulk drop.
10. Approval documents and the inspection reference
Before cutting, we ask buyers to sign off three things: approved panel samples for both grey tones, signed dimension drawings with appliance positions, and a finish schedule naming substrate, surface and hardware. Those signed documents then become the reference for packing-list checks and for any snag inspection on site. If your project has an internal consultant or a head contractor reviewing shop drawings, add them to that approval chain before production is released, not during it.
A short pre-production checklist
- Signed panel samples for light grey and dark grey, viewed under the project's lighting temperature
- Door profile, edge detail and handle or touch-to-open decision
- Appliance schedule with model numbers and dimension drawings
- Glass cabinet glazing, shelf spacing and internal LED specification
- Internal storage schedule for base units, tall units and pantry
- Worktop and splashback interface, with the installer of each element named
- Hardware grade and soft-close scope listed on the order
- Site levels confirmed; scribe and toe-kick tolerances set
- Unit-by-unit quantities, labelling and container loading sequence
- Named approval chain for drawings before production release
If you send us the elevations and the appliance schedule, we can return shop drawings with these items already resolved. As a one-stop furniture and building materials supplier, we also supply the flooring, wall panelling, lighting and joinery that sit around the kitchen, so the interfaces are coordinated by one team rather than argued between several.