A made-to-measure kitchen package looks simple on a drawing: an aluminium frame, smoked glass fronts, a run of wall and base units. On site it is one of the tightest schedules in the fit-out, because the cabinetry has to arrive after the walls and services are finished but before trades leave the building. Smoked Glass Aluminum Cabinets are built to project-specific dimensions, so every measurement, glazing choice and hardware set is fixed at order confirmation. That single fact shapes the whole delivery and installation plan, and it is where most kitchen packages go wrong when they are ordered late and shipped without a schedule attached.

Start with the site conditions, not the product page

Before any drawing is signed off, collect what the room actually gives you. On villa and apartment kitchens — including projects we have worked on in Melbourne, Willoughby and Perth — the same checklist applies:

  • Finished floor level and finished wall faces — recorded after plastering and tiling, not from the structural drawing.
  • Positions of water supply, waste, gas and electrical outlets, with distances from both datum lines.
  • Ceiling height at several points, plus the depth of any bulkhead that an overhead unit has to clear.
  • Door and window openings, opening direction, and the clearance a glass front needs to swing or slide freely.
  • Lift dimensions, stair widths and corridor turning radii in apartments, which decide whether a tall unit travels as one piece or is split.

Aluminium-frame cabinetry is forgiving about humidity and easy to wipe down, but it is not forgiving about out-of-square walls. Where the wall deviates, we plan a scribe or filler panel on the drawing instead of leaving the installer to cut it on site.

Freeze the specification before production begins

Our Custom & OEM Service covers bespoke finishes, textures and material choices, and that flexibility is exactly why the specification has to be closed out in one pass. For a smoked glass kitchen we ask the buyer to confirm, in writing:

  • Frame profile and finish, and whether the frame edge is exposed or recessed into the carcass.
  • Ask the specifier whether tempered safety glass is required for the fronts and record the answer on the drawing.
  • Handle style or handleless reveal, hinge brand and soft-close package, drawer runner load rating.
  • Appliance schedule with cut-out dimensions, ventilation gap and door-relief direction for ovens, dishwashers and fridges.
  • Countertop material and thickness, which sets the back-splash rebate and the sink support frame.
  • Integrated lighting: transformer position, cable routes and where the driver stays accessible after installation.

Once these are confirmed we produce shop drawings for signature. Anything changed after that point reopens production, and a glass panel that has already been cut to size cannot be trimmed down to fit a revised opening.

Sequence production with the rest of the package

Kitchens are rarely ordered alone. A villa or hospitality project normally puts cabinetry, wardrobes, vanities, flooring, wall panelling and lighting into one purchase so that the same team coordinates them — see our One-stop Solution. Two scheduling decisions save weeks:

  • Order glazing and hardware at the same time as the carcasses — split shipments tend to land after the installers have moved on.
  • Group items that share a wall — cabinetry plus panelling plus concealed doors — so their setting-out dimensions are drawn from one common datum.

We also stage production by zone. Wall units, base units and tall packs are labelled per room and per elevation, which turns an unloading day into a straightforward sort rather than a search through mixed cartons.

Plan freight around the glass

Smoked glass fronts change how a kitchen ships. Our Logistics & Door-to-Door Delivery service covers freight forwarding by sea, air and rail, customs paperwork such as commercial invoices, packing lists and certificates of origin, packaging and container loading, shipment tracking and delivery to the site. For glazed cabinetry we plan a few extras on top:

  • Glazed fronts packed vertically with edge protection and interleaved padding, crated separately from carcasses so a heavy frame cannot shift onto a panel in transit.
  • Spare glass allowance for long sea legs, agreed with the buyer before shipment — cheaper than re-cutting one panel after a breakage on arrival.
  • A container mix that keeps tall units and short units apart during loading, decided at the packing list stage rather than at the factory door.
  • Delivery booked against site access: apartment towers need a lift booking and often a weekday window; villas usually allow a direct truck drop.

Tell us the delivery address early. A kerbside drop on a suburban block and a booked lift run in a multi-storey building are different jobs with different labour, and both need to be priced before the container is dispatched.

Install in the right order and sign it off properly

Our Installation & After-sales Support service includes on-site installation, inspection and snag resolution, spare parts and ongoing maintenance. On site we follow a fixed order of work:

  • Check the room against the shop drawings before opening crates — levels, services positions, and clearances for appliances.
  • Level and fix base runs first, then set tall units, then hang wall units to the finished wall line.
  • Fit worktops and sinks, connect appliances, and only then hang glass fronts and adjust hinges so every gap is uniform.
  • Test all drawers, doors and soft-close mechanisms, clean the glass, and walk the snags with the site supervisor on the same day.

Photograph the completed run at handover. That record supports warranty claims and makes it far easier to supply a matching replacement panel if a front is damaged later in the project.

A practical timeline to work back from

Rather than quoting delivery promises we cannot control, build the schedule backwards from your completion date and leave slack at the three points where custom work is always exposed: site survey sign-off, shop-drawing signature, and container arrival. Confirm with us at enquiry stage which dates matter to you, and we will tell you honestly which items can be made to measure in that window and which cannot.

Before you enquire, have ready: the finished-level floor plan of the kitchen, the appliance schedule, your preferred glass tone and frame finish, and the delivery address with site access notes. With those four items we can price the package and set a realistic production and shipping sequence in one pass.

SANTERSON is a China-based furniture and building materials manufacturer supplying kitchen, wardrobe and interior fit-out packages to villa, hospitality and office projects worldwide. Send us your drawings and we will return shop drawings, a packed shipment plan and an installation checklist for the same package.