Stone and marble look simple on a mood board and complicated on a site programme. The slab is only the start: somebody has to approve the pattern, sign off the edge detail, accept the template for the basin cut-out and confirm that what arrives on the pallet matches what was initialled in the sample box. When SANTERSON supplies Santerson Stone & Marble Surfaces for bathroom works, or Santerson Stone & Marble Panels for wall systems, the specification conversation usually involves a designer, a builder, a procurement lead and an end client who may be several time zones away. Below is the approval routine we ask project teams to run, so that stone decisions are made once instead of three times. The same routine applies whether the scope is a handful of vanity tops or a wall-cladding package across several floors.
Start with one decision-maker per question
Before any sample leaves our facility, agree who owns each decision. Pattern and colour usually sit with the designer. Budget, substitution authority and variation sign-off sit with the client or their representative. Fabrication fit — cut-outs, joints, returns, threshold heights — sits with the builder's trades. When one name is attached to each question, comments come back as decisions rather than as a second round of opinions. If your team cannot name those three people yet, hold the stone enquiry and start with our interior design service, which begins with a project brief and space planning before finishes are specified. Our Stone & Marble Panels in the partitions and paneling range follow the same staged sign-off when wall cladding is involved.
Approve in four stages, not one
Our surfaces are made to measure, with material, finish and dimensions set per project. That flexibility is the reason approvals need staging:
- Stage 1 — Material and finish. Confirm the stone or marble family, the surface treatment and how the sample was lit when you viewed it. Approve a physical sample, not a screen image.
- Stage 2 — Layout and setting-out. Confirm panel sizes, joint positions, book-matching where required, and which wall or vanity elevation each piece belongs to. This is where slab yield and cost are settled.
- Stage 3 — Template and interface details. For countertops, confirm basin type and its position, tapware holes, splashback return, and the edge profile. Santerson's undermount, vessel and integrated basin options each cut a countertop differently, so the basin choice must be locked before Stage 3 is signed.
- Stage 4 — Production release. One signature combining the approved sample reference, the setting-out drawing and the template record authorises manufacture. Nothing enters production on verbal approval.
Put every approval in one written record
Keep a single approval sheet per surface type carrying: project name, room or elevation reference, product page reference from our catalogue, approved sample code and date, approved dimensions, drawing revision number, the name of the person who signed each stage, and the date. Photograph approved samples with the code visible. In our experience a stone dispute is usually a records dispute — an email thread where the layout was never closed. One sheet per surface removes that argument.
Say plainly what changes after approval
Tell your approvers which decisions are reversible and which are not. Change of edge profile or tapware hole position before Stage 3 is cheap. Change of slab family after the cutting list is issued normally means new material and a new lead time, because made-to-measure stone is cut for that job alone. Natural stone also varies between batches; approving a sample covers you for the approved range of variation, not for a uniform appearance across every panel. Where consistency across a long run matters more than natural veining, raise it at Stage 1 so the alternative can be quoted alongside the marble.
Close the loop on delivery and handover
Stone causes the most avoidable delay when it arrives before the substrate is ready, or after the trades who set it have moved on. Confirm the delivery window against the site programme, check each crate against the setting-out drawing on the day it lands, and record any damage immediately rather than at installation. Our team handles production coordination, freight arrangements and door-to-door delivery for projects abroad, with installation support and snag inspection after handover — but the person who signs Stage 4 should also be the person who accepts the delivery, so the reference numbers match.
If your next stone or marble package needs an approval routine rather than just a price, send us the elevations and the room list at our contact page. We will return a setting-out proposal you can circulate for signature.