A request for quote for made-to-measure joinery only becomes comparable once every supplier is pricing the same thing. With mirror sliding door wardrobes, the variables are unusually wide: overall envelope, mirror specification, track and hardware set, internal layout, and the delivery arrangement agreed for site. Send an incomplete enquiry and you receive three different prices for three different products. The checklist below is what we need on a quotation request so that the number returned can actually be compared with other offers.
1. The opening, not just the front elevation
Sliding doors travel in front of an opening; they do not seal it the way a hinged door does. Provide the width and height of the finished opening, plus the clear wall length available on at least one side for the panels to stack against. Then state the ceiling condition: slab, suspended ceiling, or a bulkhead above. A wardrobe built to a room height that changes between corners will not sit level on its track, so give heights measured at several points if the floor or ceiling is not flat.
Tell us whether the unit is a freestanding carcass or built-in between structural walls, and whether the sides are exposed in the room. Built-in units fix to the structure rather than to their own case, which changes both the build method and what you are being charged for.
2. Mirror and panel make-up
"Mirrored doors" is not a specification. For each door face, confirm:
- Mirror type and colour — clear, bronze, grey or tinted, and whether the mirror is polished-edge or framed.
- Substrate behind the mirror — mirror laminated or bonded to a board panel, and the total door thickness you expect.
- Safety treatment — whether a shatter-resistant backing film is required for the doors.
- Mixed materials — some projects pair mirrored panels with glass sliding door wardrobes or timber-front panels in the same run. State which bays get which face.
- Edge and frame detail — bare mirror edge, aluminium channel, or a solid frame around each panel.
Finish samples are worth requesting at this stage. A bronze mirror against a warm timber carcass reads very differently under bedroom lighting than on a drawing.
3. Track, hardware and door count
State how many panels you expect and how they should stack — two panels over one opening, three panels with a centre meeting, or a multi-panel run for a wide wall. Then ask the supplier to name the track system being quoted: top-hung or bottom-rolling, single or double track, and the hardware brand or series. Frameless mirror-on-board panels and framed aluminium-channel panels hang differently and carry different load limits, so the same door size can require different fittings.
Ask what is included in the quoted price: tracks, guides, bumpers, handles or edge pulls, plinth, and any closing or soft-stop components. Hardware left out of a quotation is the most common reason two prices for the "same" wardrobe differ.
4. Internal layout and carcass specification
Send the internal arrangement you want, bay by bay: hanging lengths at full and short height, shelf runs, drawer banks, and any provisions for an ironing column, safe or lighting. Drawer positions matter because drawers must clear the door travel to open. If you do not have a layout yet, say so and ask for one — our design service covers space planning, internal layouts and 3D renderings before production is quoted.
For the carcass, specify board type, edge treatment, and interior finish colour, and confirm load expectations for shelf spans. See our custom minimalist bedroom wardrobe page for the kind of handleless, layout-driven detail we work to when a project calls for a clean front.
5. Site conditions and access
Include floor finish and floor level at the wardrobe line, skirting details, position of sockets and switches that must remain reachable, and any wall that cannot be fixed into. For apartments and hotels, note lift dimensions, stair width and whether panels can be delivered in sections and assembled on site. Large mirror panels are limited by what physically fits in a service lift — this affects panel count and joint positions more often than buyers expect.
6. Quantities, programme and delivery terms
Give the number of rooms or units, not just one typical wardrobe. Repeat types let us fix one specification and price the set consistently; a villa with bespoke wardrobes in every bedroom should be quoted room by room. State the required site date and work backwards: production, then freight, then your own on-site preparation. Tell us which arrangement you want priced — ex-factory, FOB, CIF to a named port, or door-to-door delivery to site — because our logistics service covers freight forwarding, export paperwork, container loading and tracked delivery, and each option carries different cost and risk responsibility.
For multi-unit projects, ask whether units ship together or in phases, and how cartons are labelled against room numbers. Labelling decided after shipment is far harder to fix.
7. What we need from you, and what you should expect back
A usable enquiry pack is short: drawings or measured dimensions with levels, a room-by-room schedule of quantities, the mirror and finish selection, the internal layout, site access notes, required dates and the delivery term. Attach photographs of the space where drawings do not exist.
In return you should receive an itemised quotation showing carcass, doors, hardware and any extras separately, a confirmed specification sheet for signature before production, and a production plus freight schedule. Ask us to flag anything we have assumed — mirror size, track type, or who prepares the floor level — so assumptions become line items rather than surprises at handover.
8. The short pre-quote checklist
- Opening width and height, stacking wall length, heights at multiple points.
- Built-in or freestanding; exposed sides identified.
- Mirror colour, thickness, backing, edge detail, safety film yes or no.
- Panel count and stacking pattern; track system and hardware named in the quote.
- Internal layout per bay, including drawer clearance against door travel.
- Carcass board, edge banding and interior colour.
- Lift, stair and doorway dimensions for delivery in one piece or in sections.
- Quantities per room, required site date, chosen Incoterm.
Send a complete specification and compare quotes on equal terms
Mirror sliding door wardrobes sit at the awkward end of joinery procurement: glass-fronted, heavy, made to size and installed late in a programme. The buyers who get clean comparisons are the ones who send the full envelope above on day one. If you have drawings or even just measured dimensions and photographs, send them over and we will price the set against our wardrobe and built-in furniture range, with the specification confirmed before anything goes into production.