A smoked glass wardrobe looks simple on a drawing: tinted glass, a slim frame, an interior layout. On site it is one of the most coordination-heavy items in a bedroom fit-out, because glass dimensions cannot be trimmed, tracks must be level, and the wall, floor and ceiling rarely behave the way the detail expects. An installation plan written before production starts is what keeps the joinery team, the glazing supplier and the site crew reading from the same sheet.

Below is the working checklist we use on residential wardrobe projects, organized by the decisions that have to be closed out at each stage.

1. Site data: what has to be measured before anything is drawn

Made-to-measure wardrobe work fails on incomplete site data, not on the glass itself. Record all of the following for every wall the run touches:

  • Width, height and depth at three points along the run — floor to ceiling at the start, middle and end of the wall — because slab and plasterboard levels move.
  • Floor finish build-up and where the finished floor level stops relative to the wardrobe line: the base sits on the finished floor, not the screed.
  • Squareness of the two walls if the run turns a corner, plus whether skirting is being removed or scribed around.
  • Position of downlights, air-conditioning diffusers, sprinkler heads, curtain boxes and cornices that fall within or above the wardrobe zone.
  • Switches, outlets, thermostat panels and headboard lighting that sit on a wall the doors will slide across or swing past.

Send the raw measurements, not a cleaned-up plan dimension. Our design team works from the as-measured figures and marks the tolerance line into the carcass detail, which is where an out-of-plumb wall gets absorbed by a scribe panel instead of an uneven door gap.

2. Door system: the decision that drives the whole plan

Glass wardrobes are specified by door type first, finish second. Each option changes the clearance you need to reserve.

Door typeWhat it demands on siteWhere it works
Sliding glass doors — glass sliding door wardrobes Level head and bottom tracks, a structural pocket or wall for the leaf overlap, clear access in front of the opening for the door travel path Bedrooms where a bed or an en-suite entry leaves little swing room
Hinged glass doors — glass hinged wardrobes A clear swing arc, solid blocking behind the frame for hinge fixings, consistent reveal on adjacent walls Wide rooms, walk-in openings, and runs where you want full visual access at once
Framed glass — smoked glass aluminum frame wardrobes Tight frame tolerance at the head and jamb; aluminium frame takes up less clear opening than a timber rebate Contemporary schemes where a fine shadow line matters, and higher-traffic guest rooms
Walk-in glazed runs — glass walk in wardrobes A door opening that is usable with arms full, internal lighting wired before the panels close up, ventilation strategy for an enclosed room Dressing rooms and master suites with a dedicated closet room

Decide the system before the ceiling grid, the flooring order and the electrical first fix are locked. Changing from hinged to sliding after the floor is laid means new tracks, new packing and a rebuilt base.

3. Glass specification: what to write into the order

"Smoked glass" covers a range of tints, reflectivities and surface treatments, and two samples that read the same in a showroom can behave very differently once they are five metres apart in a lit bedroom. Confirm these items in writing:

  • Tint depth and whether the glass is reflective or plain — a reflective coating mirrors the room and changes how deep the interior reads.
  • Whether the tint sits on the outer face, inner face or between layers, which decides what shows when the door is open.
  • Safety construction for the project. In most residential and hospitality work, glass in doors and low-level panels is specified as laminated or toughened; the exact build is set by the specifier and local requirements, so state it on the order rather than assuming a default.
  • Edge treatment — polished edges are visible through smoked glass, and a ground edge will show against a dark frame.
  • Cut-outs for handles, integrated pulls or an internal light switch, all of which must be made before toughening.

Related finishes in the same glazing family — frosted glass wardrobes, bronze glass wardrobes and ribbed glass wardrobes — are often mixed into one bedroom scheme. If you are mixing them, note which panels are tinted and which are textured on the elevation, because texture changes both privacy and how much interior detail shows.

Order a full-size sample of the actual door leaf, not a 100 mm offcut. Look at it in the room at night under the wardrobe's own lighting before you sign off the glass.

4. Interior layout and services: locked before the doors are made

Smoked glass only earns its keep if what is behind it is worth seeing. Set out the internal plan against how the client actually stores clothes:

  • Hanging zones split by length: long garments, shirts and jackets, and a double-hang section for shorter items.
  • Drawer bank height and depth — drawer focused modular wardrobes suit clients with a lot of folded and accessory storage; shelf-heavy layouts suit boxes and linens.
  • Shoe storage at the base, and whether the base is a plinth or a drawer sitting on the finished floor.
  • Open display niches for items you want visible through the tint, versus closed panels where clutter should stay hidden.
  • Internal lighting: vertical strips in the hanging zones, puck lights over shelves, and a door-triggered or motion switch. Run the cable and put the driver somewhere serviceable — behind a removable panel, never sealed inside a carcass.
  • Load-bearing decisions that affect fixings: wall-hung rails, tall built-in towers and heavy drawer banks all need blocking or a floor-supported frame confirmed at the drawing stage.

Where a run includes an awkward return or a corner, glass corner wardrobes and angled corner carcasses keep the depth usable; a square corner behind a sliding door usually becomes dead space.

5. Sequence and access: the site programme around the delivery

Glass and made-to-measure carcasses arrive late and cannot be re-cut on site, so the plan has to say who is out of the room when.

MilestoneMust be complete before it
Final survey and sign-off drawingsFloor finish chosen, ceiling levels set, electrical first fix located
Production releaseGlass build, tint sample, handle type and interior layout all confirmed in writing
Delivery to siteRoute from loading bay or front door clear, lift or stair dimensions checked, protected storage area assigned
Carcass installationWet trades finished and dry, paint base coat on walls behind the run, floor laid and protected
Glass and doors fittedCarcass levelled and fixed, tracks set, hardware adjusted
Snag and handoverDoors adjusted for parallel travel, soft-close tested, lighting circuits proven, glass cleaned

Two practical points people forget: the lift or stairwell has to accept the longest leaf at its packaged angle, and smoked glass panels need a dry, upright, padded storage spot — leaning them against a wall in a corridor is how a job loses a panel two days before fitting.

6. Tolerances, defects and the snag list

Write the acceptance criteria into the plan so the handover is not an argument:

  • Floor level across the track run, measured and recorded — sliding systems are adjusted by packing, not by bending a track.
  • Plumb and line at both jambs, with the agreed scribe width on out-of-plumb walls.
  • Door gap consistency and leaf alignment when closed; soft-close engagement on every leaf.
  • Glass checked for scratches and edge chips before protective film is removed, with any damage photographed on the day of installation.
  • Interior lighting on a working circuit with an accessible driver, and switch behaviour confirmed at each door.
  • Cleaning and care instructions issued for the specific tint and frame finish, since ammonia-based cleaners are not suitable for every coating or laminate surface.

Our furniture installation for interior projects covers on-site fitting, inspection and snag closure, with spare parts available for hardware that wears over time. For projects where our team is not the fitting crew, we still issue the setting-out drawings and adjustment details so the local installer works to the same tolerances.

7. Procurement trail: what a complete enquiry looks like

A wardrobe order that comes back with the right dimensions and no rework usually starts with a complete brief. Send:

  • Room drawings plus the as-measured figures from Step 1, with photos of each wall.
  • The chosen door system and frame finish, plus the glass build you want quoted.
  • The interior layout sketch: hanging lengths, drawer counts, shelves, lighting points.
  • Project location, delivery address type and access notes — apartment lift limits in particular.
  • Programme dates: survey date, required delivery window and installation window.

That information lets us quote the right configuration the first time. Each smoked glass wardrobe in the Glass Door Wardrobes collection is made to measure, so finish, layout and dimensions are specified per room rather than picked from a fixed size list — which is exactly why the installation plan has to exist before production does.

If you are planning a glazed wardrobe run for a villa or hospitality project, send us the drawings and site measurements and we will return setting-out details, a glass specification to confirm and a configuration proposal for each room.