A 7-metre swim spa looks simple on a mood board and complicated on a setting-out plan. Before the slab is poured or the deck framing goes in, the selected unit has to be reconciled with drawings, services and access. This guide uses the Outdoor Swim Spa WS-PC07A as the worked example, so every dimension, equipment count and power figure below can be traced back to a real catalogue entry rather than to an average spa.

Start with the shell dimensions, then add your own clearances

The WS-PC07A is catalogued at 7000 × 3000 × 1470 mm. Treat those three numbers as the starting point of a coordination exercise, not as the final footprint. On plan you need to show the shell, plus working clearance for entry and exit, plus the plant zone where the control system, filtration and any optional equipment sit. On section, the 1470 mm depth tells you how much of the unit can be sunk into a raised deck before the water line interferes with coping levels or with the loungers and seating arranged around it.

Practical rule for the drawing set: never dimension to the spa alone. Dimension to the finished deck edge, then show the offset from that edge to the shell on at least two adjacent sides. A single offset repeated around the perimeter is what lets a contractor lift the unit out later without cutting paving.

What the design team needs in writing before they draw

Most coordination clashes come from a specification that says "swim spa, approx. 7 m" and nothing else. Send the architect or designer a short confirmed brief instead:

  • Model and configuration. The same shell size covers different builds. On our catalogue the WS-PC07A is listed with water jets, LED lighting and ozone, while the closely related WS-PC07A-T adds a swim training system. That single line item changes nozzle positions, plant space and power draw.
  • Jet layout. The WS-PC07A specification lists 62 jets in total with four water pumps and one filter pump. Jet positions drive the seat and bench lines inside the shell, which in turn decide where users stand on the deck and where handrails are useful.
  • Options to be priced now, not later. Catalogue options for this range include control systems, UV sterilisation, additional water pumps, heat pumps, sand filtration, insulation and steps. Each option has a footprint. Sand filtration and a heat pump in particular need their own location on the plan before the landscape layout is fixed.
  • Power figure for the selected build. The WS-PC07A entry states a total power of 9.55 kW; the -T variant with a swim training system is listed at 11.55 kW. Give the electrical engineer the number for the exact configuration, and ask us to confirm it in writing before the distribution board is sized.

Site requirements to resolve on the ground, not only on paper

Drawings describe an ideal site. Four checks belong on the actual plot:

  • Support and access for delivery. A 7000 mm shell needs a route wider than the deck gap suggests, including turning space at corners and a hard standing area where lifting gear sits. Confirm gate widths, overhead cables and whether the unit can travel along the side of the building before the fencing goes up.
  • Structural support under and around the shell. A partially recessed installation transfers water weight plus occupant load to whatever surrounds it. Deck framing, footings and retaining edges should be designed by the local structural engineer with the catalogue dimensions in hand — we supply the product data; they sign off the local structure and any barrier requirements that apply where you build.
  • Drainage and drain-down. Show an intended path for splash-out, cleaning discharge and any full drain-down. Where the spa sits below finished deck level, this needs a sump or a gravity route decided at drawing stage, not discovered on site.
  • Equipment recess or plant area. The control system, filter pump and service access need enough room for a person to reach components with the lid open. If the plan hides everything behind a fixed screen, ask for an access panel on the drawing now.

The site also decides what the spa is used for. A resort or gym pool deck is specified for lap swimming and recovery between sessions; a private villa terrace usually carries hydrotherapy use, so jet count and seating depth matter more than swim distance. State the intended use in the brief, because it changes which variant of the same shell you order.

Reading the specification sheet against your own drawings

Before a project order is released, ask us for the confirmed specification for your configuration and compare it line by line with the architectural set. The four items worth marking up are:

  • Overall shell dimensions versus the setting-out dimensions on the landscape plan, including finishes such as stone coping that reduce the opening.
  • The listed equipment count — pumps, filter pump, jets and lighting — against what the mechanical drawings actually show routed and connected. The WS-PC07A entry lists one control system, four water pumps, one filter pump and one LED light fitting; if your mechanical set shows a different count, the difference is a configuration change that needs to be agreed in writing.
  • Total power and circuit arrangements against the electrical drawings, including isolator location and cable route.
  • Steps, insulation and any optional accessories against the built detail, since steps project beyond the shell and change deck levels.

Where a catalogue figure and a project drawing disagree, resolve it in favour of the confirmed order documents. Catalogue listings describe standard configurations; your signed specification describes what is being manufactured and shipped.

Fitting the spa into a wider outdoor package

On villa and resort projects the swim spa is rarely ordered alone. Poolside seating, pergolas, sun loungers, daybeds and hardtop shade structures share the same deck, the same drainage falls and the same delivery window. Ordering them as one turnkey outdoor package means a single coordination cycle: one set of layout drawings, one consolidated packing list, and one delivery to co-ordinate with your builder's programme. Our swim spa range covers the shells in this family, and our interior design and space planning service can produce furniture layouts and 3D renderings for the whole area, so the spa, the circulation routes and the seating zones are resolved together rather than in three separate emails.

If the plot shape does not suit a rectangular shell, our customisable outdoor spa covers square, round, oval and curved configurations with an acrylic shell and structural reinforcement, which is the route to take when the architecture, not the product range, sets the geometry.

A coordination checklist before you place the order

  • Model variant confirmed — base configuration or with swim training system, and why.
  • Shell dimensions and required clearances drawn on the landscape plan with finished levels marked.
  • Options selected and shown on plan: heat pump, sand filtration, insulation, steps, UV sterilisation.
  • Total power for the exact configuration issued to the electrical engineer; isolator and cable route located.
  • Lifting route, gate widths and standing space for lifting gear checked on site photographs or a site visit.
  • Local structural design, barrier requirements and any permits handled by the local engineer and certifier.
  • Drain-down and overflow route agreed with the civil or plumbing consultant.
  • Delivery date matched to the builder's programme, with storage space identified if the deck is not ready.

Send us your drawings — plan, section and the services layouts that touch the pool area — and we will check the WS-PC07A or the variant you have chosen against them, flag what needs local engineering sign-off, and quote the configuration rather than a generic model. That single exchange of marked-up drawings is usually what keeps a swim spa installation inside its original programme instead of turning into a concrete-cutting exercise on site.