On most villa and multi-room projects, the materials schedule is drafted around the obvious big-ticket items: flooring, wall finishes, cabinetry, lighting, bathroom fixtures. Built-in media furniture rarely gets its own line until someone asks, halfway through the build, where the television will actually go and what sits behind it. That is usually when a Floating TV Unit turns from a nice idea into a late change order, with matching effects on wall preparation, electrical rough-in and the delivery calendar.

A floating TV unit is a wall-mounted media cabinet with no floor contact. Because it is made for one wall and one project, it has to be captured in the schedule at the same time as the joinery and finishes it attaches to and sits against. The sections below walk through where it belongs in a whole-project materials schedule and what to specify so the unit, the wall and the services all arrive coordinated.

Why floating TV units break the usual schedule logic

Freestanding media furniture can be picked late. Buy it off a catalogue, drop it into the FF&E budget, deliver it near handover. Floating units cannot be treated that way for three practical reasons.

  • They fix dimensions early. A floating unit is normally made to measure, so its width, depth and mounting height have to be confirmed before the wall finish is ordered, not after.
  • They depend on the wall behind them. A unit hung on timber framing behaves differently from one hung on masonry or steel studwork, and the fixing method follows the wall build-up, which the schedule already describes.
  • They interact with services. Power, data and low-voltage cabling for the screen and components are routed through the same wall. If the unit is not on the schedule, nobody coordinates the recessed boxes that feed it.

In other words, the floating TV unit is less a piece of furniture than a junction between three things the schedule already tracks: the built-in joinery package, the wall finishes, and the electrical set-out. It earns a place in the schedule for the same reason a wardrobe does — it is fabricated, it is project-specific, and it has dependencies.

Where the unit sits in the schedule structure

If your project uses a trade-by-trade materials schedule, the floating TV unit belongs under the built-in furniture section rather than loose furniture. At SANTERSON, floating TV units sit within the same built-in furniture range as media walls and integrated storage, so they are manufactured, finished and shipped with the rest of the joinery package instead of arriving separately. That has a direct scheduling benefit: one fabrication package, one approval, one container.

In a room-by-room schedule, give the living room or media room its own line items for the unit: carcass, front panels, any open shelving or display recesses, and the finish. Vague single-line entries like "TV unit" are how discrepancies slip through approval. Explicit line items let the design team sign off the exact composition before cutting starts.

What to specify before the schedule is frozen

Three input decisions should be locked while the schedule is still open for comment.

1. Exact dimensions and wall layout

Record the overall width and depth of the unit, its mounting height, and the clearance between the base of the unit and the floor. For projects with multiple units, each one is sized to its own wall, so the schedule should carry a room reference against every set of dimensions rather than one blanket size. Confirm the wall is actually available at that size once doors, skirting and other built-ins are located on it.

2. Material and finish, matched to the joinery package

Specify the carcass material, the door and shelf materials, and the finish — including the sheen and grain direction if the unit sits in a run with other built-in furniture. When the same finish appears on custom built-in kitchen cabinets, wardrobes or vanities elsewhere on the project, note the shared reference in the schedule so one approval covers all of them and no one re-specifies a near-match in a different room. Where a unit is designed as part of a wider built-in furniture scheme, say so on the line item; that is the difference between the factory producing a coordinated run and producing an orphan.

3. Configuration: open, closed, or combination

Decide what the unit has to hide and what it has to show. Component storage, consoles, games equipment and wiring typically want closed or partially closed storage; display and decorative pieces want open recesses. Note on the schedule which parts are closed cabinets, which are open shelves and whether any section is intended for equipment ventilation. This decision is cheap on paper and expensive to change once panels are cut.

Coordination items to schedule alongside the unit

Once the unit is in the schedule, a handful of related items should be listed against the same room or the same wall reference so nothing is assumed.

  • Wall backing and framing. Note the wall construction behind the mounting zone and confirm solid fixing support at the mounting points. If the schedule already lists a wall build-up for that room, cross-reference it; if not, the backing needs its own line.
  • Electrical and low-voltage set-out. Power outlets, data points and cable routes for the screen and components should appear on the set-out drawing with the same coordinates the unit will be hung at. Mismatched coordinates are the single most common reason a "floating" install ends in visible surface trunking.
  • Screen and bracket assumptions. If the project intends a specific screen size or mounting arrangement, record it. The unit width, the recess geometry and the bracket all relate to one another.
  • Adjacent finishes. Where the unit meets decorative wall paneling, a media wall panel or a painted finish, list the interface. A schedule that shows the unit and the wall as separate trades with no interface note is inviting a site argument later.

Lead time and sequencing

Because floating TV units are made to measure, they follow the same production lead time as the rest of the built-in joinery. Two sequencing points are worth noting in the programme that sits behind the schedule.

First, get the unit into the approval round with the joinery, not after it. Late approval of one floating unit can hold up the whole joinery shipment. Second, schedule the delivery and installation of the unit after the wall finish is complete and the set-out has been verified on site. A unit installed before the wall is finished tends to get damaged; installed long after, it tends to reveal that the set-out moved during finishing works. The clean sequence is: wall built and backed per schedule, set-out verified, wall finish completed, unit hung, screen and components connected.

For projects ordering through a one-stop supplier, the practical way to hold this sequence is to keep the floating unit inside the built-in furniture package from design coordination through production and door-to-door delivery, and to book the on-site installation visit for built-ins so the unit goes up with the same crew that installs the wardrobes and vanities. The coordination burden then sits with one team instead of being split across three trades at the worst possible moment.

A short schedule checklist

Before the materials schedule goes to tender or production, check that every floating TV unit on the project has:

  • A room reference and its own dimension set, not a shared "typical" entry
  • Carcass, panel and finish specification cross-referenced to the wider built-in joinery package
  • A stated open/closed configuration with any equipment ventilation needs noted
  • A cross-reference to the wall construction and fixing support at the mounting zone
  • A matching electrical and low-voltage set-out with coordinates that agree with the unit geometry
  • A line in the programme that places approval with the joinery round and installation after the wall finish

None of these items is complicated on its own. The reason they get missed is simply that floating TV units are treated as décor in the first schedule draft and as construction in the last one. Moving them into the built-in furniture section of the schedule from day one — specified, cross-referenced and sequenced like the joinery they are — is what keeps them off the change-order list at handover.

If your project needs floating TV units produced as part of a coordinated built-in furniture package — made-to-measure sizing, matched finishes and delivery together with the rest of the joinery — contact SANTERSON to review your materials schedule and confirm specifications before production starts.