High gloss wood effect cabinets look straightforward on a mood board and far more demanding on a site. The shine shows every misaligned door, every inconsistent grain match, and every late substitution. If your cabinet order is going to travel internationally and be installed by a team that did not build it, quantity planning and product coordination matter as much as the finish sample. The checklist below follows the order we work through on our own kitchen projects, from the first set of drawings to the container loading sheet.

Start From A Door List, Not A Cabinet Count

A single number such as "40 metres of kitchen" tells a factory nothing useful. Before any quantity is fixed, we ask for a door list: every run of cabinetry, the number of doors and drawers on it, the appliance envelope for each tall unit, and the height of each tall unit against the finished floor level. That list becomes the shared reference for the quotation, the production order and the site team, and it is what lets us confirm that a high gloss wood effect cabinet front specified on drawing revision A is still the front on the delivery note at handover.

Three items cause most of the rework when they are left open: finished floor levels, the position of the flue and services risers, and the exact opening of the built-in oven, dishwasher and refrigerator. High gloss fronts do not forgive a 3 mm gap difference between adjacent doors, so those dimensions need to be locked before the panels are cut.

Quantity Planning: The Lines That Usually Go Wrong

We build the bill of quantities in groups, because each group fails in a different way.

  • Carcase panels and fronts. Count fronts by door style and finish, not by kitchen. A project mixing gloss fronts with a tall bank in a different finish needs two separate quantity lines.
  • Worktops. Measure the developed length including the return to the wall and any upstand, then state the edge profile once. A cut made to the wrong edge spec cannot be recovered on site.
  • Hinges, runners and handles. Quantify these from the door list, then add a small spares allowance shipped in the same container. Replacement hardware arriving two months after installation is what turns a clean handover into a second mobilisation.
  • Plinth, trims and scribe panels. These are the parts most often missed on the purchase order, and they are the parts the installer notices first.
  • Integrated lighting and the transformer or driver that goes with it. Specify the cable run and the access point at the same time.

For a gloss kitchen, we also confirm the total front area against the batch, because a re-order six weeks later is a different production run. Where a project has several identical bathroom or kitchen-type repeats, such as an apartment scheme, we take the quantity per floor and multiply, rather than re-measuring each unit against a plan that may change between revisions.

Product Coordination: Matching The Front To The Rest Of The Job

Gloss wood effect fronts sit at the junction of several trades. Before production we sign off the front against the worktop edge, the splashback, the flooring and the adjoining joinery, using physical samples placed side by side rather than a PDF board. Grain direction on a wood effect gloss front is what makes two nominally identical panels look mismatched, so the direction is written into the shop drawing for each door and the grain is laid out on the elevation, not left to the workshop.

That coordination extends past the kitchen. In the villa projects we have delivered in Sydney and Melbourne, the same cabinet front logic carries into bedroom storage and media walls, which is why interior fixtures are released on one drawing set rather than three. Where the design carries the finish across rooms, we order the fronts together, with one reference number for the finish and one revision number per elevation.

Appliance selection belongs in the same coordination step. Oven, hob, dishwasher, refrigerator and extraction each set a cabinet dimension and a ventilation requirement, and on a handleless gloss run the drawer front profile has to clear the appliance handle or pull. We prefer to confirm appliance models before the fronts are cut, and to record any substitutions in writing with the date they were approved.

For specification packages, the same fronts appear under different collections, so we cross-check related ranges such as handleless high gloss cabinets against the door profile detail on the drawing, in case the design intent is a finger pull rather than a profile handle.

Sequencing Production, Packing And Handover

Once quantities and finishes are frozen, the sequence decides whether the site run is calm or not. Our order of work is: confirmation drawings signed, sample front approved, production and quality control, packing and container loading, shipment tracking, then installation and snagging through installation and after-sales support.

Packing gets the same attention as production. Gloss fronts are protected face to face, packed by room and by elevation, and every crate carries the drawing reference on the outer label. For a multi-unit job we pack one apartment at a time, so the installer is not sorting a mixed pallet on a site with limited storage. The packing list states crate contents by elevation reference, which is what makes the missing-panel conversation a ten minute check rather than a site stoppage.

A Pre-Release Check You Can Run In One Meeting

  • Every elevation carries a revision number, and the quotation, the production order and the packing list all quote that number.
  • One approved physical front sample is signed and kept, with the finish reference written on it.
  • Grain direction, door swing and handle type are marked on each elevation drawing.
  • Appliance models, worktop edge profile and splashback material are confirmed in writing, with the date of approval.
  • Hardware and trim quantities include a spares allowance, shipped in the same container.
  • Access panels, ventilation and the transformer location for cabinet lighting are shown on the services drawing.

If those seven points are signed off, gloss wood effect cabinetry is no riskier to deliver than any other fitted furniture. If two or three are still open, fix them before the panels are cut, because that is the point where correction costs a drawing change rather than a container.

Send us the drawings and the door list, and we will return a quantity schedule with finish references and a production sequence mapped to your programme, as part of our turnkey solutions service.