Glass partitions look simple on a drawing. They are one of the easiest items in a fit-out to under-order, over-order and delay, because the glass, the frame, the door leaf, the track and the wall finish behind it are usually bought from different places. This guide walks through how we count quantities for glass partitions and how we keep the products around them coordinated, so that a villa or hotel package arrives as one set instead of five separate problems.
Start With Zones, Not Panels
Before anyone measures anything, mark up the plan room by room and decide what each glass element is actually doing. In our work on villa and hospitality projects the same sheet of glass can sit in four different roles, and each role changes how it is counted:
- Fixed screen. A single panel that closes off a shower area or separates an entry from a living space. Counted as one piece per opening.
- Door assembly. Glass sliding doors and glass folding doors are counted as leaves, not openings. A four-leaf bifold is one opening but four manufactured units plus the hardware set.
- Operable wall. Glass sliding panels and partition sliding systems divide one large space into two usable rooms. Here the number of panels depends on the stack you want when the wall is opened, not only on the span you want to close.
- Fixed joinery in wet or shared walls. Wall panel systems, niche detailing and integrated door-and-paneling runs share the same setting-out lines as the glass, so they have to be measured at the same time.
Writing the schedule this way means each line has one clear owner and one clear quantity. It also exposes the items that are not glass at all: headers, floor tracks, skirting returns, architraves and the substrate behind any panel that will carry a hinge or a clamp.
How We Count Quantities
Our partitions are made to measure, so there is no standard module to fall back on. We build the quantity sheet from the opening schedule rather than from a panel catalogue, in four passes.
Pass 1: One line per opening
Every opening gets a number that will appear on the drawing, the packing list and the installation sequence. A bathroom may only have three lines; a lobby with an operable wall and several screens may have twenty. The opening number is what prevents a panel made for level 1 arriving at level 3.
Pass 2: Panels, leaves and hardware per line
For each opening we record the fixed panels, the moving leaves, the track length and the hardware set separately. Sliding and folding systems are sold as a kit: leaves plus track plus guides plus handles. Counting only the glass is the most common cause of a site stoppage, because the hardware often ships in a different crate.
Pass 3: Finish and layout variants
Finish, layout and dimensions are specified per project, so two openings of the same size are not automatically interchangeable if one faces a guest corridor and the other faces a bedroom. Each variant is its own line with its own quantity.
Pass 4: Spares for anything that can be broken after handover
For a private villa, spare glass is rarely worth holding. For a hotel or a serviced apartment block it usually is, and the sensible moment to order it is with the first package, while the specification is still open and the batch is still running.
Coordination: The Four Interfaces That Decide the Programme
| Interface | What has to be agreed | Who usually gets caught out |
|---|---|---|
| Glass and floor | Recessed or surface track, floor build-up depth, threshold detail at tile and at timber | Flooring supplier, who lays the finish before the track is fixed |
| Glass and wall | Substrate behind clamps and hinges, setting-out line shared with custom niche paneling and panelling runs | Wall finisher, who panels over an opening that was never set out |
| Glass and services | Shower valves, drains, lighting and switches kept clear of vertical mullions and clamp positions | M&E contractor, whose first fix assumes a different partition line |
| Glass and doors | Matching frame profiles between partitions, integrated door and paneling and pocket or flush doors in the same corridor | Joinery package, ordered to a different frame depth |
When those four interfaces are drawn once, on one sheet, the rest of the coordination falls out naturally. When they are not, the glass is blamed for problems that belong to another trade.
Ordering Glass in the Same Package as the Rest of the Fit-Out
A partition rarely stands alone. In a bathroom it sits next to vanities, basins and wall finishes; in an open-plan living space it sits next to media walls, storage and lighting. Because SANTERSON produces furniture and building materials under one roof, we schedule partitions together with the joinery and finishes they touch, which gives three practical advantages:
- One setting-out survey. The same site visit captures partition openings, niche depths and cabinet recesses, so everything is measured off the same datum line.
- One finish board. Frame colours, veneers and metal finishes are matched across partitions, doors and cabinetry before production starts, instead of being reconciled from photographs afterwards.
- One delivery sequence. Crates arrive in the order the site needs them, with hardware sets grouped to their openings. Our logistics covers freight forwarding, packaging and container loading, customs paperwork and door-to-door delivery, and installation support follows the same sequence on site.
For projects that also need acoustic separation rather than visual separation, acoustic sliding panels are counted the same way as glass sliding panels, but the performance target for the selected configuration has to be confirmed at the specification stage, because it drives panel build-up and track detail.
A Practical Quantity Checklist
- Opening schedule with numbered openings, one line per opening, cross-referenced to the drawing.
- Panel and leaf counts separated from opening counts, including stack direction for sliding systems.
- Track length, guides, handles and clamps listed as their own lines.
- Finish variant noted per line, not assumed across identical sizes.
- Survey date recorded, with floor build-up and wall finishes confirmed before release to production.
- Spare panels decided per project type, ordered with the main package where they make sense.
- Interface details drawn for floor, wall, services and adjacent doors before ordering.
Send Us the Opening Schedule
If you already have a drawing with openings marked, send it over with the room list and we will return a panel-by-panel schedule, flag the interfaces that need resolving and quote the partitions alongside the joinery, wall finishes and doors they sit against. If you are still at concept stage, we can set out the partition lines with you first, so quantities and coordination are settled before anything goes into production.