A media wall looks simple on a drawing: a panel, a screen recess, some shelving. On site it is one of the last elements to arrive and one of the first things a client judges. If the panels land late, damaged, or without the fixings your installer needs, the whole handover slips. This guide walks through how we plan international delivery for a project order of Santerson Integrated TV Panels: the shop drawings that lock the size down, the crate list, the freight booking and the site checks on arrival.

Why integrated TV panels need their own delivery plan

Integrated TV panels are made to the wall, not to a catalogue size. Finish, layout and dimensions are specified for each space, so a project order is manufactured to your opening, your screen and your storage configuration. That has direct consequences for logistics:

  • No off-the-shelf replacement. A damaged panel cannot be swapped from stock; it goes back into production, which takes longer than re-ordering a standard item.
  • Oversize and weight. Full-height panels exceed standard parcel limits, so they travel as crated project cargo, usually by sea.
  • Trade dependencies. The panels sit behind electrical first-fix, behind plasterboard, and in front of flooring and final decoration. A late delivery blocks more than one trade.
  • Mixed finishes on site. Media walls are often specified alongside other wall finishes and joinery from the same order; splitting deliveries across vessels creates matching and scheduling problems.

For that reason we treat a media wall as a scheduled package inside the wider furniture and building materials project procurement, not as an accessory added at the end.

Step 1: Lock dimensions, finishes and services before production starts

Almost every delivery problem we see on site traces back to a specification that was still open when production began. Before your order is released, confirm the following in writing:

Item to confirmWhy it matters for delivery
Final wall dimensions and floor levelPanel heights are cut to the finished floor. A slab or screed change after production means remanufacture.
Screen model, size and mounting typeDetermines the recess, the backing substrate and the load path in the crate.
Cable routes, sockets and any integrated lightingFixings and electrical components are packed with the matching panel group, so they must be known early.
Finish and material selectionVeneer, lacquer and laminate batches are ordered together; a late finish change re-sequences production.
Storage layout: open niches, closed cabinets, shelvingDetermines crate count and the assembly sequence on site.
Room access: door widths, lift size, stair turns, loading bayLargest single panel must physically reach the wall. Measure it before the crate list is written.

If your project also uses Santerson Full Height Media Walls or Santerson Sliding Panel TV Systems, specify them in the same order. Panels, sliding mechanisms and cabinet carcasses from one production run arrive together, with matching batch finishes and one set of paperwork.

Practical rule: do not release a media wall into production until the site has confirmed finished floor levels and the electrical first-fix layout. Everything after that point is expensive to change.

Step 2: Choose Incoterms and a freight mode deliberately

Our logistics and door-to-door delivery service covers freight forwarding by sea, air and rail, together with customs paperwork, packing, container loading and shipment tracking. For a project order of integrated TV panels the choice usually comes down to this:

  • Sea freight (LCL or FCL): the normal choice for full-height panels and joinery travelling with the rest of the fit-out. Lowest cost per cubic metre; longest transit.
  • Air freight: reserved for a short, light component set such as hardware kits, brackets or a replacement panel sent after an on-site damage claim.
  • Rail: an option on the land corridors where it is available, sitting between the two on cost and time.

Work backwards from your site program rather than forwards from the factory. Take the date the media wall must be installed, subtract installation and snag time, subtract customs clearance and inland transport to the door, then subtract transit, and keep a buffer for port congestion and inspection. Book the vessel against that backward date, not against "as soon as possible".

Decide the Incoterms with your broker before the order is signed. Ex-works puts more of the freight and clearance burden on you; door-to-door keeps one party accountable from our loading bay to your site entrance. Either option can be right. What matters is that landed cost, insurance and the point where responsibility transfers are all stated once, in the order confirmation.

Ask us for cargo insurance options when the quotation is issued. Glass-fronted elements and high-gloss panel faces are the parts most often claimed for in transit, and the cover should be arranged before loading, not after damage appears.

Step 3: Pack for the last metre, not just the voyage

Ocean packaging protects a panel between ports. On site, the same panel has to survive a lift, a corridor and a turn into a living room. Our packing and container-loading planning therefore works from the crate list backwards:

  • Vertical crating for full-height panels, with edge protection on the visible face and corner boards that also serve as lifting points.
  • Panel groups labelled by room and wall, not just by SKU, so the installer can find crate 3 of 8 without opening everything.
  • Hardware and fixings split by panel group, with a duplicated kit set held aside in case one box is mislaid on site.
  • High-gloss and veneer faces separated in the container, with bracing that stops panels sliding against each other during rolling.
  • A crate list that matches the assembly drawings, so the sequence on the delivery note is the sequence on the wall.

Step 4: Clear customs with a complete document set

Delays at destination are rarely about the cargo itself; they are about paperwork. For each shipment we prepare the commercial invoice, packing list and certificate of origin, and support import permits where the destination requires them. To keep clearance moving, make sure the documents agree with each other on:

  • Description of goods: "media wall panels, manufactured to project dimensions" reads better than a vague category that invites inspection.
  • Gross and net weight and cubic metre figures per crate, matching the packing list line by line.
  • Declared value consistent between invoice, insurance and bill of lading.
  • Correct destination and notify party, including your customs broker.

Import duty rates and valuation rules differ by country and change over time. Confirm the treatment for your destination with your own broker or agent before you budget; we supply the documents and the declarations they need, but the assessment is theirs to make.

Step 5: Receive, inspect and install in the right order

Delivery is not finished when the truck leaves. Build these checks into your site program:

WhenWhat to do
At the doorCount crates against the packing list before signing. Photograph any crushed or wet crate with the label visible.
Within two working days of arrivalOpen panel crates in sequence, check faces and edges, and report damage while the claim window is open; do not wait for installation day.
Before installers startConfirm finished floor levels and the position of sockets and cable outlets against the shop drawings.
During installationFollow the crate sequence in the assembly drawings; keep protective film on until decoration is complete.
At handoverRecord any spare panels, keys and hardware left over, and keep the crate list with the project file for future service.

Our installation and after-sales support covers on-site installation, inspection and snagging, plus spare parts and replacement when a panel is damaged in transit or on site. Where the project team prefers their own joiners, we send the assembly drawings and fixing schedule with the shipment and stay available for queries during fitting.

How this fits a wider Australian or overseas project

Media walls rarely travel alone. On villa and hospitality projects we consolidate integrated TV panels with cabinetry, wardrobes, bathroom fixtures, lighting, flooring and wall finishes into one coordinated programme under our turnkey interior project solutions. Consolidation means one crate list to manage, one customs entry where the destination allows it, and one production schedule so that matching veneers and lacquers leave the factory in the same batch. Our published project references include villa work in Willoughby, Perth, North Turramurra, Melbourne and Sydney; scope and detail for each case are set out on the individual project case pages.