A classic wooden hinged wardrobe is one of the easier built-in items to specify and one of the easier ones to get wrong. The doors look simple, so buyers order them the way they order loose furniture: pick a style, pick a count, move on. That works for a single bedroom. It falls apart across a villa floor, a guest-house wing or a run of apartments, where wardrobe quantities interact with wall openings, ceiling heights, door swing clearance and the cabinetry, doors and joinery ordered around them.

This guide covers how we approach quantity take-off and product coordination for classic wooden hinged wardrobes on residential and villa fit-out projects: what to count, how to group the units into an order, which related products have to be decided at the same time, and where the handover between design, production and site usually breaks down.

Start From Openings, Not From Room Counts

The most common quantity error is counting rooms. A bedroom may carry one full-height wardrobe, a short robe beside an en-suite entry, or a run that turns a corner into a dressing area. Count the openings you intend to fill and the linear length of each opening instead.

  • Record the clear width, height and depth of every niche or wall run, taken from finished surfaces rather than structural lines.
  • Note floor level differences, skirting, architraves, cornices, radiators, switch plates and any door or window reveal that intrudes into the run.
  • Mark fixed obstructions above the line — beams, bulkheads, ductwork, sprinkler heads — because they decide whether a unit can be built to ceiling.
  • Record the swing side of the room entry door. A hinged wardrobe door that clashes with the room door is a layout problem, not a hardware problem, and it must be fixed on paper.

Every SANTERSON wardrobe in this collection is made to measure, so an opening does not have to match a standard module width. What matters is that the take-off is complete before widths are divided into doors, because door count drives the internal layout and the visible rhythm of the elevation.

Turn Lengths Into Door Widths Before You Count Units

Hinged wardrobe elevations read well when door widths stay in a comfortable band and repeat consistently across an elevation. Once you divide each run into doors, three things follow automatically: the number of carcasses, the position of every vertical standard, and how much internal fit-out sits behind each pair of doors.

Run lengthTypical door groupingWhat to check at this stage
Short robe, single openingOne or two doors on one carcassHinge side relative to the room door; whether the top is boxed in or left open
Standard bedroom wallTwo to four doors across two or three carcassesWhere carcass joints fall against the bed axis and lighting
Long wall or full-width featureRepeated pairs, with one wider central bay if requiredJoint detailing between carcasses; whether handles or push-open are used throughout
Corner or L-shaped runTwo returns meeting at an angled or square corner unitCorbel depth, blind-corner access, and which return is shortened to keep door widths even

Grouping decisions are cheap on paper and expensive after production. If the elevation spans more than one wall face, send the client two grouping options rather than one; the difference in cost between them is usually small, and the difference in how the room reads is not.

Specify Each Unit With Three Independent Choices

A wardrobe order becomes ambiguous when the door style, the material and the internal layout are discussed as one decision. Separate them, and the same take-off can be quoted against several finishes without re-measuring.

  • Door style. The classic wooden look is carried by the panel — flat, paneled or arched. Flat panel hinged wardrobes sit quietly in a room and suit simpler mouldings; paneled hinged wardrobes carry more profile and should be matched to the skirting, architrave and door casing already specified for the project.
  • Material and finish. Species, grain and sheen are chosen once per project or per floor, not per room. If solid-wood doors appear elsewhere in the property — classic paneled solid wood wardrobes in a principal suite, for example — order the wardrobe doors, internal doors and any matching cabinetry from the same batch reference so the tones hold together under site lighting.
  • Internal layout. Hanging heights, shelf rows, drawers, trouser racks and lighting are decided per unit, based on who uses the room. Long-hang for guest rooms and staff rooms; double hang and more drawer rows for principal suites.

Because material, finish and layout are specified independently, a buyer can lock the quantity schedule early and still refine finishes through the custom and OEM service without reopening the take-off.

Coordinate Wardrobes With the Doors and Built-in Furniture Around Them

Wardrobes rarely fail on their own; they fail where they meet something else. On a project order, the following items should be decided together with the wardrobe schedule, by one person, against one set of drawings.

  • Room doors and architraves. Hinge lines, floor coverings under the swing, and the reveal where a wardrobe butts into a door casing all need one decision-maker. Our built-in furniture and the interior door ranges are produced to the same measured openings for this reason.
  • Floor and ceiling finishes. Whether the wardrobe sits on the finished floor or on a protective base changes both height take-off and skirting detail. Bulkheads built for ductwork should appear on the elevation, not be discovered on site.
  • Lighting. Interior wardrobe lighting needs cable routes decided before carcasses are assembled; surface-fitted fittings after the fact look applied rather than designed.
  • Adjacent cabinetry. Vanities, laundry joinery and kitchen cabinets in the same corridor should share finish references and profile language, so a run of built-ins reads as one package instead of four purchases.

A practical rule: if two trades can each be told "the other one will handle it", that detail belongs on a drawing with a name against it. Most wardrobe snag lists are coordination gaps — a skirting fitted through a door swing, a cornice left in place, a handle clashing with a light switch — not manufacturing faults.

Build the Order Schedule So Production and Site Agree

Once openings are measured and elevations are drawn, put everything into one schedule that both the factory and the site team work from. For each unit record: a unique room and unit code, the opening dimensions, the carcass grouping and door widths, the finish reference, the internal layout code, the hinge and handle selection, and the required delivery sequence.

  • Sequence by installation order, not by purchase order convenience. Wardrobes installed before floor finishes are laid will be damaged; installed after too many other trades have used the room as storage, they get knocked.
  • Keep spare door panels and matching hardware with the last delivery of the package, so late site adjustments do not require a new production run in a different batch.
  • Have one drawing set issued for production and for installation. Two versions — an architectural elevation and a workshop detail — is where mismatched heights come from.

SANTERSON handles this as one chain, from design consultation and space planning through material selection, manufacturing, project management and site coordination to final handover, which is what turnkey interior project solutions are meant to remove: the argument about who owns a dimension.

Three Checks Before You Release the Order

  • Clearance check. Open every door on the elevation and confirm it clears the bed, the en-suite swing, and any radiator or column. Reduce a door width or move a carcass joint now.
  • Consistency check. Read the schedule top to bottom for finish codes, handle codes and hinge directions. A single transposed code is invisible until delivery day.
  • Sign-off check. The client signs elevations, not a quantity list. Quantities alone never reveal that a door width looks wrong against the bedhead.

If you have drawings or a room list for an upcoming project, send them to us and we will return a measured wardrobe schedule with door grouping, finish options and an installation sequence, so the quantities are settled before production starts.