A mirrored hinged wardrobe looks simple on a drawing. It is a tall box with mirrored doors, and most schedules treat it as one line item near the end of a joinery list. That is exactly where problems start. On a multi-unit or whole-house job, the wardrobe sits at the junction of flooring, wall finishes, ceiling lines, door swings, lighting and electrical work. If it enters the materials schedule late and without clear fields, the corrections surface on site, when the screed has dried and the paint is finished.

This guide covers how to place Mirrored Hinged Wardrobes inside a whole-project materials schedule — what the line item needs to carry, which trades have to be coordinated around it, and how one supplier covering built-in furniture, interior fixtures and finishes reduces the number of handovers between packages.

Why mirrored hinged wardrobes are scheduled differently from other built-ins

Three characteristics change how this item should be handled in a schedule, compared with a plain painted carcass or a loose furniture piece:

  • Mirrored door leaves carry weight and are fragile. Door mass drives hinge selection, the number of hinges per leaf and whether the carcass frame needs a fixing detail to a solid substrate. It also changes how the unit is packed, handled and moved into position on site.
  • Hinged doors need clear swing space. A hinged front requires an unobstructed arc in front of it. Beds, bedside tables, door leaves of the room itself, skirt boards and radiators all have to be checked against that arc before the layout is frozen.
  • Mirrored faces are finish-sensitive. Once installed, a mirror edge cannot be trimmed on site the way a timber panel can. The opening has to be right the first time, which means the schedule must record who sets out the opening and who signs it off.

What each wardrobe line item should carry in the schedule

A single row reading "wardrobe, mirrored doors, to design" transfers risk to whoever reads it last. Each mirrored hinged wardrobe location needs its own row, keyed to a room code from the room schedule, with these fields completed:

Schedule fieldWhat to recordWhy it matters on site
Location and referenceRoom code plus a wardrobe tag that matches the joinery drawing numberPrevents units being delivered to the wrong level or swapped between similar rooms
Made-to-measure dimensionsFinished width, height and depth at the location, taken from the coordinated setting-out drawing — not a nominal module sizeHeight depends on finished floor levels and ceiling set-down; nominal sizes do not survive real tolerances
Carcass material and finishBoard type, edge treatment, interior and exterior finish, and the finish reference used elsewhere in the projectKeeps the wardrobe face consistent with built-in furniture in adjoining rooms
Door type and mirror specificationHinged configuration, number of leaves, mirror thickness and edge finish, plus any safety backing requirement for the market of installationDetermines hinge count, swing clearance and whether a replacement leaf can be re-manufactured to match
Interior layoutRail heights, shelf counts and depths, drawer banks, and any lighting provision inside the carcassInterior fittings are usually fixed at manufacture; changing them after production starts means a new unit
Interface responsibilitiesWho supplies and installs skirting, architrave, ceiling trim and floor transition at the wardrobe faceThis is the most common gap between the joinery package and the finishing trades
Fixing substrateWhether walls behind and above the unit are block, stud with noggings, or plasterboard, and what fixing method followsDetermines anchor type; discovered too late it becomes a chase-out or packing exercise
Lead time and delivery sequenceManufacture window, packaging standard, container or truck booking, and the floor or level it is staged toBuilt-ins arrive after wet trades but before loose furniture; wrong sequence blocks either side
Product pages list made-to-measure sizing, material and finish options, and project-tailored layouts for this collection. They do not fix dimensions or mirror specification for a given job. Confirm the dimensions and selected specifications for each location before the order is released.

Coordinating the wardrobe with the rest of the package

Flooring first, then height

Wardrobe height is measured to finished floor level. If engineered flooring or a screed-and-tile build-up is still open in the schedule, every wardrobe height below it is provisional. Fix the floor build-up for bedrooms and corridors before joinery dimensions are signed, and record the finished level on the same drawing that carries the wardrobe elevations.

Wall finishes and reveal lines

Decide whether the wardrobe butts to the wall finish or is set back with a shadow gap, and whether architrave stops at the carcass or returns behind it. Both answers change the manufactured width. Where the project uses decorative wall panels or wall cladding in the same room, the panel module and the wardrobe face should be drawn together so the reveal reads as one line rather than two competing edges.

Door swings and circulation

Check the hinged arc against the room door, the bed swing position and any corridor behind the room door. On bedroom layouts this is where a hinged wardrobe is most often swapped for another configuration after the fact — a change that resets production. Resolve it on paper with the furniture layout, not during installation.

Lighting and electrical

If interior lighting or a shaver socket is intended inside the carcass, the cable route and isolator position must be shown before first fix. A wardrobe ordered without that provision cannot be wired later without surface trunking or a partial strip-back.

Why scheduling built-ins with other fixtures reduces handover risk

Wardrobes rarely fail on their own; they fail at the interface. When cabinetry, wall panelling, interior doors and bathroom joinery come from separate suppliers, each package carries its own setting-out assumption, and the difference is resolved on site by whoever arrives first. A turnkey project approach puts these lines under one production and coordination scope: the same team reads the drawings for wardrobes, kitchen cabinets, panelling and doors, so a finish reference or floor level is decided once and applied consistently.

For projects outside China, that single scope also covers freight forwarding, packaging and container loading, customs paperwork and door-to-door delivery, plus site installation and snagging. For an importer managing several fit-out packages, this means one production schedule to track and one interface list to police rather than several.

A short pre-order checklist for each wardrobe location

  • Finished floor level confirmed for that room, in writing, on the coordinated drawing
  • Setting-out dimensions signed by whoever controls the openings — not taken from an architectural outline
  • Hinge count and hinge type recorded against mirror leaf size and weight
  • Mirror specification agreed, including edge finish and any safety backing for the destination market
  • Interior layout locked: rails, shelves, drawers, lighting provision
  • Interface list signed: skirting, architrave, ceiling trim, floor transition, who does each
  • Fixing substrate confirmed at every wall the unit attaches to
  • Delivery sequence agreed against wet trades and loose furniture, with staging area named

Send us the room schedule and the joinery drawings for your project. We will return wardrobe elevations with made-to-measure dimensions, finish references matched to your other built-in lines, an interface list for the finishing trades, and a production and delivery sequence you can build into the programme.